Safeco Surety and C. A. Walker Construction v. J.P. Southwest Concrete, Inc.

Court of Appeals of Texas·Decided October 29, 2013·No. 01-12-00672-CV·Published

Opinion

Opinion issued October 29, 2013

In The

Court of Appeals

For The

First District of Texas

NO. 01-12-00672-CV

SAFECO SURETY AND C.A. WALKER CONSTRUCTION, Appellants V.

J.P. SOUTHWEST CONCRETE, INC., Appellee

On Appeal from the 189th District Court Harris County, Texas

Trial Court Cause No. 2005-70198

MEMORANDUM OPINION

This is the second appeal in this dispute between C.A. Walker Construction and Safeco Surety (collectively “Walker”) and J.P. Southwest Concrete, Inc. (“J.P.”). See C.A. Walker Constr. Co. v. J.P. Sw. Concrete, Inc., No. 01-07-00904-

CV, 2009 WL 884754 (Tex. App.—Houston [1st Dist.] Apr. 2, 2009, no pet.) (mem. op.). In the first appeal, we remanded for a new trial on damages. Walker now appeals from the trial court’s judgment on remand, which awarded J.P. $74,193.90 in actual damages, as well as attorney’s fees and pre- and post- judgment interest. Walker contends that the trial court erred in allowing J.P. to present new damages theories and evidence that were precluded by our 2009 opinion in this case. It also challenges the trial court’s findings of fact and conclusions of law and contends that the evidence is legally and factually insufficient to support the judgment. We modify the trial court’s judgment to exclude the award of retainage in the amount of $7,105.28, and we affirm the judgment as modified.

Background

2007 Trial and First Appeal Our first opinion sets forth in detail the factual background that gave rise to this dispute. Walker was the general contractor on a Spring Branch Independent School District construction project. J.P. was a subcontractor. In their written contract, Walker agreed to pay J.P. $243,000 to do all the concrete work for the project. The contract price for J.P.’s work was later revised via change orders to $274,149.

When J.P. began work in September 2004, it encountered severe subsoil obstructions that prevented it from drilling pier holes. Walker instructed J.P. to prepare and submit written change orders to cover the removal of the obstructions. J.P. submitted a number of written change orders, but Walker only approved some of them.

The contract provided that J.P. would be paid in monthly installments as the work progressed. Accordingly, as work on the project progressed, J.P. submitted applications for payment along with supporting documentation. As of December 2004, J.P. had been paid $57,349.25. In January 2005, J.P. requested further payment of $79,796. Later, J.P. sought payment of $17,099 for work done in February 2005. On March 16, 2005, Walker paid J.P. $84,756.35. In exchange for that payment, J.P.’s president, Jeff Pantle, executed a “Subcontractor Affidavit of Payment and Partial Release of Lien” on behalf of J.P. The release states that the payment received on March 16, 2005 “constitutes full payment for the work performed to date and any and all change orders or claims for additional work performed.” The release further provides:

Subcontractor waives, releases, relinquishes and discharges all known and unknown causes of action, including, but not limited to those arising out of contract, by statute, in tort or otherwise, and waives, releases, relinquishes and agrees to discharge any suits, debts, accounts, bonds, contracts, promises, damages, liens, encumbrances, judgments, claims and demands whatsoever, in law or equity, which

are against the Contractor . . . that the Subcontractor now has or might hereinafter obtain that relates directly or indirectly to the aforesaid relationship, Contract, and/or Project.

J.P.’s work on the project continued after it entered into the release. Walker told J.P. that subsoil debris and obstructions had been removed and requested it continue drilling pier holes. J.P. went to the site, bringing with it another drilling subcontractor, but was unable to perform the work due to subsoil debris and obstructions. J.P.’s last day at the site was March 22, 2005. Walker acknowledged that it owed J.P. for work that was done after March 16, but contended the amount owed was only $2,848.

For several months, J.P. attempted to collect payment from Walker. J.P.

eventually sued for breach of contract, and Walker counterclaimed. In its pre-trial disclosures and at the 2007 bench trial, J.P. asserted that it was entitled to recover the following damages: $19,501 for unpaid work and $58,000 for lost profits, for a total of $77,501.

However, in its motion for entry of judgment filed several weeks after trial, J.P. sought new and different damages. The motion asserted J.P. was entitled to recover damages in the amount of $74,059.52, consisting of the following:

• $17,099 for unpaid contract work in February 2005;

• $21,748.52 for unpaid contract work in March 2005;

• $8,389 for retainage;

• $26,823 for extra work completed for unsigned change orders; and

• $3,600 for attorney’s fees J.P. paid Transit Mix, another subcontractor on the project, after Transit Mix sued J.P. to recover payment for supplies Transit Mix provided for the project.

In addition, instead of the $58,000 originally sought for lost profits, J.P. requested a lost profits award of $26,499.05. The trial court rendered judgment, awarding J.P. $47,000 in damages, but did not indicate how it reached that figure. It entered no findings of fact or conclusions of law.

In Walker’s first appeal, we reversed the trial court’s damages award, but otherwise affirmed the judgment. We held that J.P. released all claims for any amounts due for work performed before March 16, 2005 by signing the March 16, 2005 release and that “any lost profits incurred before March 16, 2005 are not properly included in the award.” C.A. Walker Constr. Co., 2009 WL 884754, at *5–6. With respect to lost profits, we concluded that J.P. failed to present “objective facts, figures, or data from which the amount of lost profits can be ascertained” and that therefore “the evidence [was] factually insufficient to support an award of lost profits.” Id. at *6. In addition, we held that J.P. was not entitled to “any damages for a suit filed against J.P. by Transit Mix for services or materials, or the attorney’s fees incurred by Transit Mix and paid by J.P,” because

the plain language of the parties’ contract excused Walker from paying any damages for a suit filed against J.P. Id. at *7. Finally, we held that Texas Rule of Civil Procedure 193.6 precluded J.P.’s recovery of damages that had not been disclosed before trial. TEX. R. CIV. P. 193.6, 194.2(d); C.A. Walker Constr. Co., 2009 WL 884754, at *7. We concluded that the trial court erred in awarding $47,000 in damages, “because the figure could not have been reached without taking into consideration amounts that were disclaimed by the release, were for lost profits, were for Transit Mix’s lawsuit, or were not properly disclosed before post trial.” C.A. Walker Constr. Co., 2009 WL 884754, at *8. Accordingly, we remanded the case to the trial court “for the limited purpose of conducting a new trial on the issue of damages.” Id. at *8. New Trial on Damages and Second Appeal On remand, Walker moved for summary judgment, asking the trial court to enter judgment awarding J.P. $2,848 in damages. Walker contended this was the only amount supported by evidence that had not been rejected by this Court’s opinion. The trial court denied the motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Safeco Surety and C. A. Walker Construction v. J.P. Southwest Concrete, Inc., (Tex. Ct. App. 2013).

Safeco Surety and C. A. Walker Construction v. J.P. Southwest Concrete, Inc. (Safeco Surety and C. A. Walker Construction v. J.P. Southwest Concrete, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of San Antonio v. Pollock
284 S.W.3d 809 (Texas Supreme Court, 2009)
ERI Consulting Engineers, Inc. v. Swinnea
318 S.W.3d 867 (Texas Supreme Court, 2010)
Briscoe v. Goodmark Corp.
102 S.W.3d 714 (Texas Supreme Court, 2003)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Hudson v. Wakefield
711 S.W.2d 628 (Texas Supreme Court, 1986)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Holt Atherton Industries, Inc. v. Heine
835 S.W.2d 80 (Texas Supreme Court, 1992)
Norfolk Southern Railway Co. v. Bailey
92 S.W.3d 577 (Court of Appeals of Texas, 2002)
Cedillo v. Gaitan
981 S.W.2d 388 (Court of Appeals of Texas, 1998)
McWhorter v. Sheller
993 S.W.2d 781 (Court of Appeals of Texas, 1999)
Williams v. County of Dallas
194 S.W.3d 29 (Court of Appeals of Texas, 2006)
Anthony Equipment Corp. v. Irwin Steel Erectors, Inc.
115 S.W.3d 191 (Court of Appeals of Texas, 2003)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Manon v. Solis
142 S.W.3d 380 (Court of Appeals of Texas, 2004)
Dyer v. Cotton
333 S.W.3d 703 (Court of Appeals of Texas, 2010)
Nguyen v. Yovan
317 S.W.3d 261 (Court of Appeals of Texas, 2009)
Marin v. IESI TX CORP.
317 S.W.3d 314 (Court of Appeals of Texas, 2010)