Safeco Insurance Co. of America v. APAC-Mississippi, Inc.

982 F. Supp. 1225, 1997 U.S. Dist. LEXIS 17447, 1997 WL 690188
CourtDistrict Court, S.D. Mississippi
DecidedOctober 30, 1997
DocketNo. CIV.A. 3:97-CV-113BN
StatusPublished

This text of 982 F. Supp. 1225 (Safeco Insurance Co. of America v. APAC-Mississippi, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safeco Insurance Co. of America v. APAC-Mississippi, Inc., 982 F. Supp. 1225, 1997 U.S. Dist. LEXIS 17447, 1997 WL 690188 (S.D. Miss. 1997).

Opinion

OPINION AND ORDER

BARBOUR, District Judge.

This cause is before the Court on the Motion for Partial Summary Judgment filed by the Defendant APAC-Mississippi, Inc. (“APAC”) and the Cross-Motion for Summary Judgment filed by the Plaintiff Safeco Insurance Company of America (“Safeco”). Having considered the Motions, Responses, Rebuttals and supporting and opposing mem-oranda, the Court finds that the APAC Motion is well taken and should be granted, and the Safeco Cross-Motion is not well taken and should be denied.

I. Factual Background and Procedural History1

On April 17, 1992, J.J. Pryor Contractor, Inc. (“Pryor”) entered into a contract with the Mississippi Department of Transportation (“MDOT”) to perform certain highway construction on Highway 61 in Claiborne County, Mississippi (“Claiborne County Project”). On April 23,1992, APAC entered into a subcontract with Pryor to perform a portion of the work covered by the contract between Pryor and MDOT.

Pursuant to its contract with MDOT and as required by Mississippi law,2 Pryor obtained a payment bond from Safeco, as surety, the terms of which required Pryor and Safeco to jointly and severally “promptly pay ... all persons furnishing labor, material, equipment or supplies ...” for the Claiborne County Project. Although APAC timely performed its obligations under the subcontract,3 Pryor has failed and refused to pay APAC the balance of $107,271.70 which is due under the subcontract. Due to this failure, APAC demanded that Safeco, as the surety, promptly pay APAC in accordance [1227]*1227with the terms of the payment bond. Safeco, thus far, has refused to make such payment.

On February 20,1997, Safeco filed a Complaint for Declaratory Relief seeking a declaration from this Court that it has no liability to APAC regarding the Claiborne County Project. On May 15, 1997, APAC served its Answer and Counter-Claim seeking a judgment of $107,271.70 against Safeco, plus interest, prompt payment penalties and attorneys’ fees arising out of the labor, materials and equipment which APAC provided to Pryor in connection with the Claiborne County Project. Both parties have moved for partial summary judgment, and this issue is now ripe for decision.

II. Summary Judgment Standard

Rule 56 of the Federal Rules of Civil Procedure states in relevant part that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as td any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). The United States Supreme Court has held that this language “mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a sufficient showing to establish the existence of an essential element to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986); see also Moore v. Mississippi Valley State Univ., 871 F.2d 545, 549 (5th Cir.1989); Washington v. Armstrong World Indus., 839 F.2d 1121, 1122 (5th Cir.1988).

The party moving for summary judgment bears the initial responsibility of informing the district court of the basis for its motion and identifying those portions of the record in the ease which it believes demonstrate the absence of a genuine issue of material fact. Celotex, 477 U.S. at 323, 106 S. Ct. at 2552-53. The movant need not, however, support the motion with materials that negate the opponent’s claim. Id. As to issues on which the non-moving party has the burden of proof at trial, the moving party need only point to portions of the record that demonstrate an absence of evidence to support the non-moving party’s claim. Id. at 323-24, 106 S.Ct. at 2552-2553. The non-moving party must then go beyond the pleadings and designate “specific facts showing that there is a genuine issue for trial.” Id. at 324, 106 S.Ct. at 2553.

Summary judgment can be granted only if everything in the record demonstrates that no genuine issue of material fact exists. The district court, therefore, must not “resolve factual disputes by weighing conflicting evidence, ... since it is the province of the jury to assess the probative value of the evidence.” Kennett-Murray Corp. v. Bone, 622 F.2d 887, 892 (5th Cir.1980). Summary judgment is improper where the court merely believes it unlikely that the non-moving party will prevail at trial. National Screen Serv. Corp. v. Poster Exchange, Inc., 305 F.2d 647, 651 (5th Cir.1962).

III. Analysis

APAC asserts that its right to sue on the payment bond issued by Safeco commenced on or about June 13, 1996, which is the date MDOT published notice of final settlement of the Claiborne County Project. According to APAC, Miss.Code Ann. § 31-5-53, prior, to its amendment in 1994, guarantees APAC the right to file suit on the payment bond within one year from the date which MDOT published notice of final settlement, which was June 13, 1996. Because APAC asserted its counterclaim on the payment bond on May 15, 1997, APAC contends that the counterclaim was timely filed pursuant to Mississippi law which was in effect at the time the payment bond was executed. APAC claims that the time frame for filing suit contained in Miss.Code Ann. § 31-5-53 is substantive. Therefore, according to APAC, any amendment to this statute, absent clear legislative intent to the contrary, should be applied prospectively, rather than retroactively.

Safeco asserts that the 1994 amendment to Miss.Code Ann. § 31-5-53 is procedural, not substantive, and, therefore, should apply retroactively to any contracts in existence at the time of its enactment. Thus, if the 1994 amended version of the statute applies, Safe-co asserts that the statute of limitations began to run on June 3, 1995, when MDOT accepted the Claiborne County Project and [1228]*1228released Pryor from maintenance responsibility.4

In rebuttal, APAC asserts that pursuant to Miss.Code Ann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kennett-Murray Corporation v. John E. Bone
622 F.2d 887 (Fifth Circuit, 1980)
Rachel Moore v. Mississippi Valley State University
871 F.2d 545 (Fifth Circuit, 1989)
White v. Malone Properties, Inc.
494 So. 2d 576 (Mississippi Supreme Court, 1986)
Bonti v. Ford Motor Co.
898 F. Supp. 391 (S.D. Mississippi, 1995)
Bethlehem Steel Company v. Payne
183 So. 2d 912 (Mississippi Supreme Court, 1966)
United States Fidelity & Guaranty Co. v. Plumbing Wholesale Co.
166 So. 529 (Mississippi Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
982 F. Supp. 1225, 1997 U.S. Dist. LEXIS 17447, 1997 WL 690188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safeco-insurance-co-of-america-v-apac-mississippi-inc-mssd-1997.