Sabatini v. General Electric Co.

96 A.D.2d 5, 468 N.Y.S.2d 352, 1983 N.Y. App. Div. LEXIS 19871
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 24, 1983
StatusPublished
Cited by2 cases

This text of 96 A.D.2d 5 (Sabatini v. General Electric Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sabatini v. General Electric Co., 96 A.D.2d 5, 468 N.Y.S.2d 352, 1983 N.Y. App. Div. LEXIS 19871 (N.Y. Ct. App. 1983).

Opinion

OPINION OF THE COURT

Rubin, J.

Plaintiff Hugo Sabatini, an employee of the Jersey Central Power and Light Co. (JC), was injured on May 8,1974, when he fell approximately 50 feet from the opening on the second level, to the first level of JC’s nuclear power electric generating plant at Forked River, New Jersey. His fall was during the annual close down of the plant for repair, maintenance, and improvements (outage). The plant had been built for JC by General Electric Company (GE) and was put into operation in 1970.

Hugo Sabatini commenced a negligence action, inter alia, against GE to recover damages for the personal injuries he allegedly sustained as a result of the fall and his wife brought a derivative action to recover for loss of her husband’s services. A bifurcated trial on liability was conducted. At the close of plaintiffs’ case the complaint and cross claims against Burns & Roe, Inc. and Riggs Distler & Co. were dismissed. Thereafter, the jury returned a verdict in favor of defendant GE and against plaintiffs. On appeal, plaintiffs contend that the trial court, in essence, charged them out of court. We agree.

Since plaintiffs’ appeal is predicated primarily on errors in the court’s charge, we have culled only the evidence, at the bifurcated trial, that sheds light on said issue.

THE TRIAL EVIDENCE

After the plant became operational in 1970, JC annually contracted with GE to provide its expertise for the contemplated outage. The contract for the 1974 outage provided that GE “will provide all technical direction and general supervision for the efficient conduct of the jobs”. Included among the listed jobs was work relating to “No. 3 and No. 6 CRY [combined reheat valve] valves, No. 3 minor, No. 6 major” (emphasis supplied), and job number 37c, described as “Finish grating under the reheat stop valves”.1 The [7]*7contract provided that GE’s services included the start-up of the “initial turbine-generator unit roll for a period not to exceed forty hours from the initial roll of the turbine-generator unit”. Pursuant to the contract, JC would be responsible for and provide, inter alia, the tools and equipment for the work, the crane and operator services, the scaffolding and planking, as required, and the “[c]leanup and janitorial services”.

The accident occurred in the turbine building, which was approximately 280 feet by 80 feet and had two levels. The upper level (also called the turbine or operating level or floor) was about 50 feet above the lower level (called the condensor bay). Most of the operating floor was made of reinforced concrete but a substantial part consisted of steel plate overlaid on and bolted to the underflooring of horizontal steel beams. The latter type of flooring included plates, each approximately 8 feet by 3 feet, weighing about 480 pounds, around each of the turbine generator’s six reheat valves. The massive reheat valves extended vertically from 9 feet above the operating floor level to 6 feet below it.

The original design of the plant contemplated access to the bottom of the reheat valves by the temporary erection of walk-up scaffolding from below. During the 1973 outage (the one just prior to the one at bar), a decision was made by GE and JC to provide access by a ladder from the operating floor down to a platform at the lower end of the number 6 valve to permit work to be performed on it. This required the removal of the 480 pound, 8 feet by 3 feet steel floor plate, surrounding the number 6 valve.

The 1973 plan for permanent access from the operating floor to the bottom of CRY number 6 contemplated the cutting out and hinging of a 3 feet by 2 feet hatch from the 8 feet by 3 feet plate so that it would no longer be necessary to remove the plate itself. This was not done in 1973, and at the end of the outage the 8 feet by 3 feet plate was put back in place.

GE’s report to JC of its completed 1973 outage work stated that access to the grating assembly around the reheat valves “was made down the permanent ladder from the turbine elevation. The access hatches with appropriate [8]*8rails will have to be made through the existing steel plates”. However, at the start of the 1974 outage, the suggested cutting out of an access hatch had not been done, so that if access was to be made to CRY number 6 from above, as in 1973, the lifting of the entire steel plate was again necessary.2

Edward Sienkowski, a JC maintenance engineer, called as plaintiffs’ witness, testified substantially as follows: he reported to Hugh Scott, a GE engineer at the plant, who assigned him and his crew to work on CRY number 6 when the 1974 outage began. This involved the removal of, and work on, various parts of the valve. They had the crane operator lift the 8 feet by 3 feet plate and this left “quite a large hole, so we turned the plate sideways, but at that it didn’t cover the hole. So I had the men lift it up and we put plywood under it and put the plate on top of the plywood”. This left a 3 feet by 2 feet opening through which they could descend by ladder to the platform at the lower part of the valve. Safety cones were placed around the opening to which were attached safety ropes. Sienkowski and his crew worked on the valve parts for about three weeks during which time various GE engineers were present. After the valve was reassembled, and after a conversation with a GE engineer, he and his crew left the area. During all of this time, the plate remained in the same position, with plywood on top and underneath it, with the opening surrounded by safety ropes and cones. During this period there were various sections of plywood placed in the area on the concrete and steel portions of the floor. Sienkowski also stated that after he and his crew had finished their work on the valve there was still further work to be done to activate the turbine and that that work was not part of JC’s job.

Plaintiff Hugo Sabatini testified that he became a JC employee in August, 1973, and that he and Robert Latchaw, his co-worker, were assigned by their JC foreman, Leo Sergevich, to work at the nuclear plant during the 1974 outage. His initial work included bringing stacked lumber, including 4 feet by 8 feet plywood to the [9]*9turbine floor. In the following weeks they worked on the turbine floor on turbine parts and grease fittings, on instructions, variously, from JC or GE personnel. On one occasion plaintiff Hugo Sabatini “came in and there was plywood laid on the floor”. Two days before the accident, upon completion of their work on the parts, their foreman, Sergevich, told them “to clean the lumber off the turbine room floor”. They proceeded to do this by placing a sling on the center of the turbine floor, picking up the plywood that was on the floor, placing it on the sling, and then when the sling was loaded, signaling to the crane operator who conveyed it to the loading well, down to a trailer where JC employees would put the load on the truck. Then the procedure would be repeated. Sabatini testified that although the crane operator was always a JC employee, there were occasions during the first day of pickup of plywood when they would have to wait their turn for use of the crane because it was being used for work being done or supervised by GE’s subcontractor.

Hugo Sabatini further testified that in the course of the second day of their work, he and Latchaw picked up a plywood section and, carrying it horizontally, walked and placed it on the sling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Meyer
114 A.D.2d 352 (Appellate Division of the Supreme Court of New York, 1985)
Sabatini v. General Electric Co.
104 A.D.2d 581 (Appellate Division of the Supreme Court of New York, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
96 A.D.2d 5, 468 N.Y.S.2d 352, 1983 N.Y. App. Div. LEXIS 19871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sabatini-v-general-electric-co-nyappdiv-1983.