S. Shore Cable Constr. v. Grafton Cable, Unpublished Decision (11-17-2004)

2004 Ohio 6077
CourtOhio Court of Appeals
DecidedNovember 17, 2004
DocketC.A. No. 03CA008359.
StatusUnpublished
Cited by2 cases

This text of 2004 Ohio 6077 (S. Shore Cable Constr. v. Grafton Cable, Unpublished Decision (11-17-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. Shore Cable Constr. v. Grafton Cable, Unpublished Decision (11-17-2004), 2004 Ohio 6077 (Ohio Ct. App. 2004).

Opinion

DECISION AND JOURNAL ENTRY
{¶ 1} Defendant-Appellant Grafton Cable Communications, Inc. ("Grafton"), appeals from a bench trial decision of the Lorain County Court of Common Pleas, which denied its counterclaims and awarded judgment to Plaintiff-Appellee South Shore Cable Construction, Inc. ("South Shore"). South Shore has cross-appealed certain aspects of the trial court's decision. We affirm in part and reverse in part.

I
{¶ 2} As this is essentially a dispute over unpaid invoices, we begin with a simplified and practical characterization of the two parties and their relationship. Grafton owns and operates certain cable television and internet lines, meaning the actual cables that carry the signal, either aboveground or underground. South Shore is a contractor that installs these types of cables. South Shore has worked for Grafton for years, installing their lines. There have been no written contracts, but merely an oral understanding that South Shore would complete the work as requested and invoice Grafton accordingly.

{¶ 3} This dispute stems from a single, large reinstallation project in which, without written contract, Grafton hired South Shore to install lines throughout six residential developments: Wellington, Grafton, Flint Ridge, River Ridge, Castleton, and Pheasant Run. This project totaled nearly $1.85 million in invoices from South Shore, of which Grafton paid $1.54 million without objection. However, in the fall of 2001, Grafton reportedly became dissatisfied with South Shore's work and stopped paying its invoices. Seventeen particular invoices went unpaid, for an amount totaling $305,031.96. Grafton's General Manager later explained that he stopped paying these invoices in an effort to compel South Shore to remedy what he viewed as widespread problems in the system, arising under previously paid invoices as well as some of the seventeen at issue.

{¶ 4} In May 2002, South Shore sued Grafton to recover the $305,031.96 due on the seventeen outstanding invoices. Grafton responded with an answer and a counterclaim. In its answer, Grafton admitted that it did not pay the seventeen invoices, but sought a set-off as an affirmative defense based on what it alleged was the unacceptable quality of work performed by South Shore. In its counterclaim, Grafton asserted six separate claims totaling $1.1 million, arising from the entire project and not limited to or dependant on the seventeen particular invoices: (1) breach of fiduciary duty; (2) fraud; (3) conversion; (4) unjust enrichment; (5) breach of contract; and (6) negligent breach of contract. Grafton also sought an additional $1 million in punitive damages and attorneys' fees. South Shore denied the allegations and asserted its own affirmative defenses.

{¶ 5} A four day bench trial began on September 2, 2003. On September 30, 2003, the trial court issued its decision in a journal entry. The journal entry began by addressing Grafton's first four counterclaim causes of action and concluded that Grafton had failed to prove any of them by a preponderance of the evidence. Thus, those claims were denied.

{¶ 6} The journal entry next addressed Grafton's breach of contract and negligent breach of contract causes of action, which encompassed the whole project, implicating some forty-nine invoices and seeking $1.1 million in actual damages. At trial, Grafton had promoted its theory that it had withheld payment of the seventeen invoices due to pervasive problems with the entire cable installation project. Towards that theory, Grafton presented testimony and evidence that alleged thousands of flaws throughout the system. While acknowledging that many of the seventeen contested invoices were themselves acceptable, Grafton extended the dispute well beyond those invoices by producing testimony and evidence to contest numerous paid invoices received prior to those seventeen. However, the trial court was not persuaded, and in the journal entry it went on to consider only the seventeen invoices at issue pursuant to South Shore's breach of contract. Thus, Grafton's entire counterclaim was denied.

{¶ 7} Finally, the trial court considered South Shore's claims on each of the seventeen invoices. The court began by noting that at trial Grafton had not contested several of the invoices, but on those that were contested Grafton was entitled to a certain quality of work even without a written contract. In the journal entry, the trial court individually addressed each invoice, weighing South Shore's claim and Grafton's affirmative defense. The trial court found nine of the seventeen to be without dispute and awarded the full amount to South Shore. The court reduced two invoices by a 100% set-off (#1831 and 1929), on its finding that the quality of work was insufficient, although each for a different reason. The court reduced two other invoices by a 15% set-off (#1829 and 1836) on its finding that noise in the system was due to the improper attachment of fittings. The court reduced three invoices by a certain dollar amount to comply with South Shore's price list for materials identified on the invoice (#1859, 1861 and 1928). Finally, the court reduced one invoice (#1931) by both a dollar amount, to comply with the price list, and a 15% set-off due to the reported noise. Therefore, after recalculating for a mathematical error, the trial court ultimately awarded South Shore $237,887.20 on its claim for $305,031.96.

{¶ 8} Grafton has timely appealed, asserting two assignments of error. South Shore has timely cross-appealed, asserting six assignments of error.

II
Assignment of Error Number One
"The trial court erred in failing to extend its findings and conclusions, as applied to invoice 1831, to [appellant's] entire under-ground construction breach of contract/negligent breach of contract claims; the court's failure to do so is contrary to the overwhelming evidence associated with said claims, and is against the manifest weight of the evidence."

Assignment of Error Number Two
"The trial court erred in not rendering judgment in favor of [Appellant] in the amount of $401,823.00."

{¶ 9} These two assignments of error present the same substantive argument. Effectively, Grafton Cable has argued that the trial court's denial of its counterclaim is against the manifest weight of the evidence. Specifically, Grafton Cable has argued that because the trial court found in favor of its affirmative defense to invoice 1831, it must necessarily extend this finding to the entire project. We disagree.

{¶ 10} Grafton insists that logic necessitates the outcome of this issue. That is, Grafton argues that because the trial court found that the cable installation did not comply with the requirements at a portion of Pheasant Run (some 2,305 feet of buried cable), the court awarded Grafton a set-off, which must also apply to other areas of noncompliance: Wellington, Grafton and the remainder of Pheasant Run. This charge implicates some 91,074 feet of buried cable, and 44 invoices for a total invoiced amount of $551,571. Before pointing to a flaw in Grafton's reasoning, it is worthwhile to lay out its complete argument, which unfolds in three successive syllogisms.

{¶ 11} First, if the underground cable installation is to comply with industry standards, then the cable must be installed 24 inches deep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
2008 Ohio 3311 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 6077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-shore-cable-constr-v-grafton-cable-unpublished-decision-11-17-2004-ohioctapp-2004.