S. S. Thompson & Co. v. County of Atlantic

148 A. 626, 106 N.J.L. 355, 1930 N.J. LEXIS 192
CourtSupreme Court of New Jersey
DecidedFebruary 3, 1930
StatusPublished
Cited by1 cases

This text of 148 A. 626 (S. S. Thompson & Co. v. County of Atlantic) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. S. Thompson & Co. v. County of Atlantic, 148 A. 626, 106 N.J.L. 355, 1930 N.J. LEXIS 192 (N.J. 1930).

Opinion

The opinion of the court was delivered by

Walker, Chancellor.

This was an action at law in the Supreme Court for damages. The defendant denied liability and the case was tried before Circuit Court Judge Sooy and a jury. The trial court struck out the first and third counts of the complaint and ordered a nonsuit as to the second and fourth counts, and directed that a general verdict be entered in favor of the plaintiff and against the defendant *356 upon the fifth count in the sum of-$3,035.08. Judgment was thereafter duly entered for the directed verdict, with costs. The plaintiff appeals to this court from the whole of the judgment entered in the cause in the court below. Undoubtedly it did not intend to appeal from the directed verdict, but on the ground that it was entitled to recover a larger sum; and assigns as grounds of appeal (1) the granting of the motion to nonsuit on the second and fourth counts of the complaint, and (2) the striking of the first and third counts.

The plaintiff-appellant entered into a contract with the county of Atlantic for the building of a bridge spanning Inside Thorofare in Atlantic City, known as Albany avenue bridge, taking down the entire superstructure of the then present bridge, with certain piers, supports, &c.; and agreed to complete the entire work on or before the expiration of two hundred working days after the approval of working contract and bond, as provided in the specifications. The contract was made and dated December 30th, 1926, and required the work to be begun within ten days thereafter. Certain specifications of forms were submitted to prospective bidders, including the plaintiff, who secured the award of contract for doing the work. Among the specifications for bids were the following:

“Prospective bidders are hereby directed to carefully read and consider the plans and specifications and to visit the site of the work so that they may thoroughly familiarize themselves with the conditions, particularly the difficulties, existing at the site; no consideration will be given to any claim that a bid was made without full comprehension of the conditions to be encountered.
“The contractor must assume all risks and responsibilities for accidents and damage of any kind whatsoever during construction of the work, and he must sufficiently barricade the work, at all times, with proper lights at night, until final completion of it. Any loss or damage, arising from unforeseen obstructions or difficulties encountered in the prosecution of the work, must be sustained by the contractor.”

*357 And in the form of a bidder’s blank submitted along with the specifications, the bidder, including the plaintiff, was required to certify, and plaintiff-appellant did certify that:

“Having carefully examined the specifications and all plans covering the proposed reconstruction of the bridge spanning Inside Thorofare in Atlantic City, known as the Albany avenue bridge, upon which bids have been invited by advertisement to be submitted to you on December 15th, 1926, and having carefully studied the site of the work to ascertain the conditions, particularly the difficulties, existing there, the undersigned will provide all necessary machinery, tools, apparatus and other means of construction, will do all work and furnish all materials required by the plans and specifications and in the manner shown by the plans and in accordance with the instructions of your engineer.”

It will be observed that in the first specification for bids above set out a prospective bidder was directed to read carefully and consider the plans and specifications and visit the site of the work, so as to be thoroughly familiar with the conditions, particularly the difficulties existing at the site; and the second, that any loss or damage arising from unforeseen obstructions or difficulty encountered in the prosecution of the work must be sustained by the contractor; and in the third, or form of bid submitted by the plaintiff-appellant, it was stated that having carefully examined the specifications and plans, and having carefully studied the site of the work to ascertain the conditions, particularly the difficulties existing there, the bidder offered to enter into the contract. The truth is that the city of Atlantic City at that time had and maintained at the locus in quo a large pipe or water main, which was being removed. If anything were wanting to show that the plaintiff-appellant knew exactly what was being done, it is supplied in the testimony of Mr. Thompson, president of the S. S. Thompson Company, the plaintiff-appellant. He was examined as follows:

“Q. When you made the examination before this bid, will you tell us what you found? A. Well, practically two or *358 three weeks before we made the bid, before the time for the bids to be received, I visited the site, went over the bridge and looked around; went down and saw what is known as the east side; saw some men with two machines, operating divers, etc.; removing the pipe line; saw the rest of the bridge in toto, as was; asked some questions. Q. Did you obtain information as to what those men were doing? A. Yes, sir. Q. And as the result of the information that you obtained, what did you find out about this pipe line? A. Well, I asked them how long they would be before the pipe line would be out of there. I asked- the man I saw was the foreman on one of the scows. Q. And what information did you receive as to the length of time before the pipe line would be out? A. About a month.” And on cross-examination: “Q. You visited the locus in quo, or scene of this bridge, before preparing your bid; did you not? A. Yes, sir. Q. And you saw men there removing the water pipe? A. Yes, sir. Q. You therefore knew the water pipe was there; didn’t you? A. Yes, sir. Q. You knew at that time that the men removing that water pipe were not employes of Atlantic City; didn’t you? A. I didn’t ask them that. ,Q. Did you make any inquiry as to who they were or who the water pipe belonged to, or anything of that kind? A. No, sir. I assumed that the water pipe belonged to Atlantic City. Q. And you afterwards found that that was correct; did you not? A. Yes, sir; as far as I know; I assumed-I assume it is yet.”

Cross-examining counsel says that the question: “You knew at that time that the men removing that water pipe were not employes of Atlantic City; didn’t you?” is incorrectly set forth, and it should be “were employes of Atlantic City.” The word “not” appears in the printed case. But it practically makes no difference which is right and which wrong. Concededly, Atlantic City owned the pipe line and it makes no difference whether it was removing it itself or through an independent contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Friedlander v. Gross
164 A.2d 761 (New Jersey Superior Court App Division, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
148 A. 626, 106 N.J.L. 355, 1930 N.J. LEXIS 192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-s-thompson-co-v-county-of-atlantic-nj-1930.