S. S. Silberblatt, Inc. And the Travelers Indemnity Company v. Lambert Corporation

371 F.2d 626
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 8, 1967
Docket23683
StatusPublished

This text of 371 F.2d 626 (S. S. Silberblatt, Inc. And the Travelers Indemnity Company v. Lambert Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. S. Silberblatt, Inc. And the Travelers Indemnity Company v. Lambert Corporation, 371 F.2d 626 (5th Cir. 1967).

Opinion

TUTTLE, Chief Judge:

This is the second appeal of this case, arising from the failure of the subcontractor on United States Government Housing Projects to pay the supplier of paint for some 800 family units at Fort Hood, Texas.

S. S. Silberblatt, having incorporated S. S. Silberblatt, Inc., successfully bid on the construction of five housing projects for family units at Fort Hood, Texas. Each of the five contracts, however, was entered into by a separate corporation. These were called Fort Hood Housing Corporation No. 6, No. 7, No. 8, No. 9 and No. 10 respectively. The construction contract for each of the projects was executed by Mr. Silberblatt as President of Silberblatt, Inc., and as president of each of the housing corporations. Five payment and performance bonds were executed covering this one construction contract, with Silberblatt, Inc. as principal, and the Travelers Indemnity Company, *627 as surety. A separate bond was executed for each of the housing corporations; each bond covered the particular project to be developed by the housing corporation to which it was issued.

Arcotex Painting Contractors, Inc. was the painting subcontractor on the construction contracts. Lambert Corporation supplied paints and painting materials to Arcotex for the five housing projects. It delivered to Arcotex at its Fort Hood Warehouse for use on the five projects $120,585.37 worth of paints and painting materials between March 4,1961 and July 6, 1962.

Lambert was not aware of the five separate housing corporations and had no control of or knowledge of the particular project in which the paints and painting materials were used; it merely supplied these items for the one construction project.

In February, 1962, Lambert advised Arcotex that further shipments would cease because of non-payment of the then due balance. Silberblatt, Inc., through Mr. Silberblatt, telephoned Lambert, following which Silberblatt, Inc. wrote a letter guaranteeing Arcotex’s obligation. 1 Thereupon, in reliance upon the letter, Lambert resumed shipment to Arcotex until all five projects were completed. Lambert continued to bill Arcotex at the prices originally quoted to Arcotex. On March 14, 1962, Arcotex paid Lambert $18,000 on its account, leaving with $20,-000 still due. Thereafter Arcotex paid for the continued shipments as the invoices for them became due. Arcotex issued its checks in the exact amount of the current invoices due and owing, noting on the checks the current amount due. Arcotex followed the system -of applying the payments on the balance due for current shipments. Lambert, on the other hand, credited these payments against the unpaid balance owed by Arco-tex. Upon completion of all housing projects and termination of shipments in July, 1962, there remained unpaid on Arcotex’s account $20,168.73. Arcotex and Silberblatt, Inc. refused to pay this balance. Notice of default payment was given by Lambert, I-nc. to Silberblatt, Inc. and Arcotex by letter dated July 31, *628 1962, and mailed August 2, 1962, and to Travelers by letter dated and mailed August 24, 1962. Lambert instituted suit on November 13, 1962, against Arcotex, Silberblatt, Inc. and Travelers, jointly and severally. Arcotex failed to answer and an interlocutory decree was entered against it on March 25, 1963.

Silberblatt, Inc. and Travelers answered and denied liability. The principal argument of appellants was that each bond covered only the materials furnished for the particular project covered by it; that the payments made subsequent to March 18, 1962, were “applied” by Arco-tex to current purchases, so that the unpaid balance represented paints and materials furnished prior to March 18, 1962, and used in one of the four projects completed on or before April 18, 1962; that recovery must be had, if at all, against the bonds covering these projects; that the notice of default of August, 1962, was not within the 90 day period required by such bonds, and that, therefore, Silber-blatt, Inc. and Travelers are not liable to Lambert.

The trial court, prior to the first appeal, held that it was unnecessary to determine which particular contract the paints supplied, by Lambert were used for. It made a conclusion of law, No. 2, to the effect that: “Gerrymandered application by the subcontractor [Arcotex] and/or prime contractor [Silberblatt, Inc.] of payment to the running account •of the supplier plaintiff [Lambert] would not bar the claim of the supplier who continuously furnished materials received by the subcontractor and used in the projects up to their final acceptance. Under the Miller Act . . . the plaintiff is entitled to recover the balance unpaid on all the materials which had been furnished up to the conclusion of the whole contract.”

This court held that the findings of fact made by the trial court were not sufficient upon which to rest the district court’s judgment, and concluded that the case must be remanded for further findings under the requirements of Federal Rules of Civil Procedure 52(a).

In remanding the case this court held, “A debtor making a voluntary partial payment of his indebtedness to a creditor may direct to which portion of the indebtedness the payment shall be applied, and the creditor must apply the payment as directed or return it [citing Jones v. United States, 7 Howard 681, 48 U.S. 681, 687, 12 L.Ed. 870], Thus the determinative issue is whether Arcotex did in fact direct Lambert to apply to current purchases the payments made after March 18, 1962.” S. S. Silberblatt, Inc. v. United States, 353 F.2d 545, 548 (5 Cir.).

Upon remand, the district court expressly made the finding that Arcotex did direct Lambert to apply the payments to current purchases. Nevertheless, the trial court, apparently failing to appreciate the significance of the legal basis of this court’s earlier action, proceeded to find that in effect the five separate contracts were one single contract and that the bonding company could be found liable if any one of the five contracts was in default, and timely notice had been given within the termination of the last of the contracts.

In view of the law of the case as announced by this court in its earlier decision, and because this law as there stated is correct, we must necessarily decide that the judgment of the trial court against the Travelers Indemnity Company was in error and it cannot stand. This is true because it is only as to the contract entered into on behalf of Fort Hood Housing Corporation No. 10, with completion date on July 6, 1962, that the notice of default served on the bonding company falls within the 90 day period required by the terms of the bond.

However, the case as against Silberblatt lies differently. The trial court, on both hearings, treated the letter of February 28th as a guarantee by Silberblatt of the payment of past due items as well as a guarantee that current payments would be made to Lambert. The trial court also found as a fact, on the second hearing, that the condition con *629

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
371 F.2d 626, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-s-silberblatt-inc-and-the-travelers-indemnity-company-v-lambert-ca5-1967.