S & S Building Corp. v. Fidelity Storage Corp.

310 A.2d 778, 270 Md. 184, 1973 Md. LEXIS 674
CourtCourt of Appeals of Maryland
DecidedNovember 6, 1973
Docket[No. 43, September Term, 1973.]
StatusPublished
Cited by21 cases

This text of 310 A.2d 778 (S & S Building Corp. v. Fidelity Storage Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & S Building Corp. v. Fidelity Storage Corp., 310 A.2d 778, 270 Md. 184, 1973 Md. LEXIS 674 (Md. 1973).

Opinion

Smith, J.,

delivered the opinion of the Court.

Failure on the part of appellant, S & S Building Corporation (S & S), to provide a warehouse with a sprinkler system “in compliance 100% with Maryland Fire Rating Bureau requirements” was the basis of a judgment in favor of appellee, Fidelity Storage Corporation (Fidelity), against S & S in the amount of $152,418.68. We shall affirm that judgment.

On July 7, 1970, S & S and Fidelity entered into an agreement called a lease. S & S was to build a warehouse for Fidelity in its Hanson-Beltway Industrial Center. This was to be constructed according to plans and specifications to be approved by both parties and then attached to the lease agreement. This included a requirement:

“Sprinkler system should be dry system, must be in compliance 100% with Maryland Fire Rating Bureau requirements and must extend into office and driver’s area.”

*186 The lease was to be for a term of twenty (20) years beginning “on the first day of the month following the actual date of ‘occupancy,’ (but in no event prior to April 1, 1971).” The agreement said it was anticipated that the term of the lease would begin on or about April 1, 1971, “unless commencement of the term [should] be postponed ... as [t]hereinafter provided.” “ ‘[0]ccupancy’ [was] defined as receipt by [Fidelity] of a Certificate of Occupancy from the appropriate governmental authority of Prince George’s County, for a warehouse, for the storage of household goods, and office space, after prompt and proper application by [Fidelity] therefor.” The agreement provided that if possession were “not tendered to [Fidelity] in such condition that an occupancy permit [could] be obtained for the purpose [previously] set forth ... on or before June 1, 1971, [Fidelity should] have the right and option to cancel [that] Lease . . . .” Fidelity was to “have the right to use the premises in advance of completion and before ‘occupancy,’ provided such use [did] not interfere with completion of the Building.” If an occupancy permit were issued on a day other than the first day of a calendar month, then Fidelity was to pay from that date a pro-rata portion of the monthly rent. The agreement spelled out that the criteria in it represented “the elements necessary for the approval of a warehouse by the United States Government.” A large part of Fidelity’s business is the storage of household goods of military personnel moving from one station to another.

Fidelity moved in its equipment and began accepting storage on June 25, 1971. As S & S puts it in its brief, “For reasons not here relevant and at the agreement of both parties the lease term commenced July 1, 1971.” The certificate of occupancy was issued July 2, 1971.

When S & S brought suit for rent for two months which it said was due, Fidelity filed a counterclaim for lost income. At trial before a jury the parties stipulated as to the back rent. Fidelity then went ahead to prove its counterclaim. S & S rested at the conclusion of Fidelity’s case. It made a motion for a directed verdict, but presented no evidence. The jury returned a verdict of $18,068 in favor of S & S against *187 Fidelity and a verdict of $170,486.68 in favor of Fidelity against S & S. A motion by S & S for judgment n.o.v. was denied. At that time, judgment was entered in favor of Fidelity against S & S for the net amount of $152,418.68.

S & S claims (1) Fidelity failed to prove a breach of the terms of the lease, (2) Fidelity failed to prove legally recoverable damages, and (3) that the trial court committed prejudicial error in admitting into evidence (a) two letters received by Fidelity from the Department of Defense, (b) testimony relative to business conducted in Virginia, and (c) testimony as to the effect of a letter from Mr. Schoolfield of the Fire Underwriters Rating Bureau upon the business of Fidelity. We shall develop additional facts in the process of discussing the points raised.

I

There is no dispute about the fact that the sprinkler system did not meet the standards required until September, 1971. S & S argues that for Fidelity “to sustain its assertion that S & S was in breach of contract, Fidelity must show that S & S was obligated to and could have achieved that goal earlier.” It points out that the lease did not specify a required completion date nor state that time was of the essence of the contract; that Fidelity had an option to cancel if possession was not tendered by June 1, 1971, which option was never exercised and which was not to be effective if the delay was caused by circumstances beyond the control of S & S; that the term of the lease was predicated upon “occupancy”; that the sprinkler system was installed in the building and had been functioning for some time prior to the issuance of the occupancy permit on July 2; that the sprinkler system had been approved by the fire marshal on June 16; that a rating by the Rating Bureau by occupancy date was impossible since it would make no inspection until occupancy was established and until an inspection was made the required test could not be performed or reported; that since time was not of the essence and there was not a fixed completion date the parties are left to what is reasonable under the *188 circumstances and “the evidence leads to the only conclusion that S & S acted in a reasonable and, in light of normal delays in construction, in a very prompt manner.”

When Mr. Schoolfield of the Maryland Fire Underwriters Rating Bureau made his inspection on July 14, 1971, he found a number of defects. One of the most serious was the presence of valves not approved by the Underwriters’ Laboratories. John C. Livingstone, Jr., president of the corporation which installed the sprinkler system, testified as to a meeting on the job site in the spring of 1971. Livingstone desired that certain changes be made, partially for his convenience. He said:

“I pointed out to the plumber during that meeting the valves in the — the valves were not U. L. approved and the underwriters would not approve the installation as it was, in my opinion. It had been my experience in the past that all valves in the fire line were required to be underwriters approved, and that these valves were not.”

In response to a question, he stated specifically that at the time of his conversation with the plumber those who were present and overheard the conversation with the plumber included the superintendent for the prime contractor and the architect. The architect was the agent of S & S. Livingstone further stated that it was these same valves that were later replaced at the direction of Mr. Schoolfield.

The premises had been tendered by S & S to Fidelity as of July 1 as meeting the terms and specifications of the lease agreement. It was at that time that the lease became operative. It would serve no useful purpose to prolong this opinion by setting forth other defects found by Schoolfield. The important point is that a specific requirement of the lease was that the sprinkler system “be in compliance 100% with Maryland Fire Rating Bureau requirements,” and there was uncontradicted evidence before the jury to the effect that it was not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Indoor Play v. Snowden Investment
Court of Appeals of Maryland, 2025
Bereano v. State Ethics Commission
944 A.2d 538 (Court of Appeals of Maryland, 2008)
Kang v. State
877 A.2d 173 (Court of Special Appeals of Maryland, 2005)
Hodge v. Babel
815 A.2d 910 (Court of Special Appeals of Maryland, 2003)
Ditto v. Stoneberger
805 A.2d 1148 (Court of Special Appeals of Maryland, 2002)
Clark v. State
781 A.2d 913 (Court of Special Appeals of Maryland, 2001)
St. James Construction Co. v. Morlock
597 A.2d 1042 (Court of Special Appeals of Maryland, 1991)
Wallace v. State
492 A.2d 970 (Court of Special Appeals of Maryland, 1985)
Attorney Grievance Commission v. Ripperger
483 A.2d 62 (Court of Appeals of Maryland, 1984)
Tichnell v. State
415 A.2d 830 (Court of Appeals of Maryland, 1980)
Robeson v. State
403 A.2d 1221 (Court of Appeals of Maryland, 1979)
Ellerba v. State
398 A.2d 1250 (Court of Special Appeals of Maryland, 1979)
Derby v. Jenkins
363 A.2d 967 (Court of Special Appeals of Maryland, 1976)
Pride Mark Realty, Inc. v. Mullins
352 A.2d 866 (Court of Special Appeals of Maryland, 1976)
Carter v. Correa
346 A.2d 481 (Court of Special Appeals of Maryland, 1975)
State v. Johnson
339 A.2d 289 (Court of Appeals of Maryland, 1975)
Sutton v. State
334 A.2d 126 (Court of Special Appeals of Maryland, 1975)
Lazorcak v. Feuerstein
327 A.2d 477 (Court of Appeals of Maryland, 1974)
Levine v. Rendler
320 A.2d 258 (Court of Appeals of Maryland, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
310 A.2d 778, 270 Md. 184, 1973 Md. LEXIS 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-s-building-corp-v-fidelity-storage-corp-md-1973.