S-M-M-S v. United States

30 Cont. Cas. Fed. 70,573, 1 Cl. Ct. 188, 1982 U.S. Claims LEXIS 2293
United States Court of Claims·Decided November 30, 1982·No. No. 602-82C·Published·Cited by 3 cases

Opinion

OPINION

YANNELLO, Judge.

Plaintiff, S-M-M-S, a joint venture, one of whose members is Santa Fe Engineers, Incorporated, filed a Complaint on November 22, 1982, seeking declaratory and injunctive relief. Plaintiff also filed a Motion for a Temporary Restraining Order on November 24, 1982, accompanied by a brief in support of its motion. A hearing was scheduled by order filed Tuesday, November 23,1982, and was conducted on Monday, November 29,1982, beginning at 10:00 a.m., during which both parties were represented and presented argument.*

At the outset of the hearing, the court provided an opportunity for the raising of any jurisdictional or other threshold defenses and none were presented to nor discerned by the court.

DISCUSSION

The facts surrounding this controversy were substantially uncontroverted and may be summarized briefly as follows.

At the jobsite in issue, there are presently ongoing a number of fixed price contracts. One such contract is being performed by [189] Santa Fe Engineers, Incorporated (in its own individual capacity). Other fixed-price contracts are being performed by several joint ventures comprised of members not in issue in this case. [The formation of joint ventures to perform certain contracts (particularly construction contracts) is not an unusual practice as indicated by the number of joint ventures presently performing fixed-price contracts on the jobsite in issue.]

The Santa Fe fixed-price contract is not expected to be completed until mid-1983.

In mid-October 1982, the Government issued a Request for Proposal (RFP) for a cost-plus-fixed-fee contract (CPFF) on the same jobsite. (The proposals submitted in connection with that RFP have been scheduled to be opened at 4:00 p.m., EST, on Monday, November 29,1982, the date of the hearing in the instant action as noted above.)

At a pre-bid conference, the Government advised that DAR 18-114 would be applicable to the RFP and this general statement of applicability was also contained in the RFP itself.

DAR 18-114 provides, in essence, that a contractor performing a fixed price contract should not be awarded any contract which contains cost variation or cost adjustment features where such [cost-type] contract would be performed concurrently [with the fixed-price contract] and at the same [job] site.

On October 19, 1982, the RFP was amended to address specifically the DAR provision and its applicability to specific companies. Amendment number 0003 to the RFP stated:

In accordance with DAR 18-114 this cost reimbursement contract will not be awarded to the following contractors currently performing work [at the jobsite] either as individual entities or as members of a joint venture: * * * Santa Fe Engineers; * * *. This prohibition extends to any intended newly formed joint venture consisting of any aforementioned contractor. * * *

(Also listed with Santa Fe were the individual members of the joint ventures which are also performing fixed-price contracts on the site as noted above. The amendment also went on to address the matter of subcontractors, but this discussion was subsequently deleted by further RFP amendment.)

In essence, the amended RFP provided that the contract would not be awarded to certain named corporations or to certain business formations of which they might be a part, and thus also implied that any proposals submitted by such entities would not be considered by the Government in connection with any award of the cost-type contract.

The plaintiff joint venture, of which Santa Fe Engineers is a member, advised the Government that it intended to submit a response to the Government’s RFP for a Cost-Plus-Fixed-Fee contract (CPFF).

In response to inquiry from the plaintiff joint venture, the Government, in a letter of November 15, 1982, further explained that, in its view, the plaintiff joint venture was precluded from receiving the contract because one of its members was concurrently performing a fixed-price contract on the same site. The Government stated that:

* * * potential labor and administrative problems [addressed by DAR 18-114] are not eradicated merely by the fixed-price contractor reincarnating itself in a joint venture for the cost reimbursement contract. The members of a joint venture do not lose their individual identity by forming such a partnership and each of them will incur costs, onsite and/or offsite. Accordingly, S-M-M-S will be ineligible for award unless Santa Fe Engineers’ fixed-price contract is fiscally complete by the date of award.

Notwithstanding this opinion by the Government, the plaintiff joint venture, on or about November 29, 1982, submitted its proposal in response to the Government’s RFP.

Plaintiff joint venture filed its Complaint in this court contending, essentially, that the joint venture was entitled under the [190] DAR to submit a proposal and to have that proposal considered for possible award of a contract. The plaintiff contended that, as a joint venture, it was not the same “contractor” as was performing the fixed-price contract (i.e., Santa Fe Engineers), but, rather, was a separate and distinct legal entity.1

In support of its position, plaintiff cited, inter alia, a decision of the GAO upholding the Government’s position that a bid was nonresponsive when the bid was in the name of a single company whereas, the bidder was described on the accompanying bond as the individual company and its president and vice president as a joint venture; the decision states as follows:

Consequently, the procuring activity determined that Roe’s bid was nonresponsive, since there was a discrepancy between the legal entity shown on the bid and the legal entity shown on the bid bond.

Matter of A.D. Roe Company, Inc., B-181692, October 8, 1974, 74-2 CPD 194. (Many similar decisions by GAO were also cited.)

The Government argued that the presence of Santa Fe in the joint venture, when Santa Fe was concurrently performing a fixed-price contract on the same site, may well give rise to the types of difficulties (administrative and otherwise) which the DAR was intended to prevent.

The Government agreed that a joint venture and its individual members were separate legal entities and that with respect to any contractual obligations, the members’ liability would be joint, rather than separate.

The Government further noted that, had plaintiff S-M-M-S been an incorporated entity, rather than a joint venture, an award of the cost-type contract may well not have been prohibited by the regulation, even though Santa Fe may have been one of the incorporated owners or shareholders.2

The Government noted several differences between the various types of business formations (joint ventures, partnerships, agencies, incorporations), and contended that these differences may justify different treatment under the DAR.

Free access — add to your briefcase to read the full text and ask questions with AI

S-M-M-S v. United States, 30 Cont. Cas. Fed. 70,573, 1 Cl. Ct. 188, 1982 U.S. Claims LEXIS 2293 (cc 1982).

30 Cont. Cas. Fed. 70,573 (S-M-M-S v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

KDH Corp. v. United States
37 Cont. Cas. Fed. 76,087 (Court of Claims, 1991)
Quality Transport Services, Inc. v. United States
34 Cont. Cas. Fed. 75,264 (Court of Claims, 1987)
Big Bud Tractors, Inc. v. United States
30 Cont. Cas. Fed. 70,974 (Court of Claims, 1983)