S. Jackson & Son, Inc. v. United States

52 Cust. Ct. 493, 1964 Cust. Ct. LEXIS 1370
United States Customs Court·Decided April 7, 1964·No. Reap. Dec. 10713; Entry No. 2336·Published

Opinion

Lawkence, Judge:

This is an appeal for the reappraisement of' an electric transformer, manufactured in Italy by the Industrie-Electtriche Di Legnano (I.E.L.) and consigned to the Corps of Engineers, United States Army District Engineers, Nashville, Tenn., andinstalled at its Cheatham Power Plant on the Cumberland Liver in: Tennessee.

The merchandise was appraised on the basis of cost of production-,, as defined in section 402 (f) of the Tariff Act of 1930.

Plaintiff contends that the appraiser erroneously included as general expenses in his finding of value certain costs -incurred in the United' States, namely, (a) “Fee of the Legnano Elec. Corp.” and (b) “Bid and Performance Bond.”

It appears from the record that the merchandise was purchased om the basis of a contract awarded I.E.L. by the United States Department of the Interior, and the Corps of Engineers, United States Army.

The bids on the contract were submitted through the Legnano> Electric Corp., a wholly owned subsidiary of the I.E.L., but an independent corporation incorporated under the laws of New York.

Jack Richer, vice president of the Legnano Electric Corp., testified" on behalf of plaintiff that he was general manager in charge of alii affairs in the conduct of its business, acting as “manufacturers’ agents), sales agents, importers and exporters.” He stated that he was familiar with the details of the notice of award, dated December 23,. 1954, given by the Corps of Engineers of the United States Army to> Legnano Electric Corp. for “main power transformers for the Cheat-ham Power Plant at the Columbia River in Tennessee.” A copy of the award was received in evidence as plaintiff’s exhibit 1. (While Richer refers to the Columbia River, the award designates the Cumberland River, where the transformer was installed.)

Said exhibit 1 reads as follows:

Confirming telegram of this date you are hereby formally notified that your-bid in the amount of $137,351.00 for main power transformers and lightning: arresters for Cheatham Power Plant, Cumberland River, Tennessee, Invitation No. [ ?] is accepted.
Reference is made to Paragraph SC-5 of the specifications which requires the execution of a Performance Bond to cover the above-mentioned work. For your convenience there is inclosed Standard Form No. 25, Performance Bond, which has been partially completed. In completing the bond special care should be-exercised in the following particulars:
a. The premium charged must not exceed the duly authorized rates.
[495]*495'b. Tbe corporate seal of tbe corporation must be affixed following tbe sig-snature on tbe face of tbe bond and following tbe signature of tbe person executing the Certificate as to Corporate Principal on tbe back of the bond.
c. Tbe signatures of the Corporate Principal and tbe Corporate Surety must be attested to.
d. Tbe original and duplicate copies of tbe bond should be returned to this •office.
Upon receipt of tbe properly executed bond a signed copy of tbe contract will be forwarded for your files. Tbe prompt execution and return of tbe bond will be appreciated.

In the performance of its responsibilities under the award, the .Legnano Electric Corp. handled damage claims for repairs; furnished engineering personnel; supervised the erection of the transformers; and, in general, handled administrative and technical •questions regarding the execution of the contract.

It is observed that the award speaks of transformers in the plural .sense. This is explained by the fact that the award embraced a bid for three identical transformers. Two of them were involved in ■reappraisement 293912-A, which was the subject of decision by this ‘Court in United States v. S. Jackson & Son, Inc., 48 Oust. Ct. 626, Reap. Dec. 10229. In that case, the appraiser, in finding statutory -cost of production, did not include the amount of the fee and performance bond above described and his decision was affirmed, although upon a very unsatisfactory record which has been incorporated as a part of the record herein. It is not clear from the record why the ¡appraiser excluded the amount of the fee and performance bond in his finding of cost of production in the first importation and included "those items in the instant case.

During the course of the trial, counsel for plaintiff stated that, in ¡appeal 293912-A, which was the subject of Reap. Dec. 10229, supra—

* * * Exbibit 3 * * * sets forth tbe details upo.n wbieb tbe Government -wished to base an appraised value of 22,762,340 Italian lira each. And I wish to point out to tbe court that on this Exhibit 3 there is specified under tbe ¡beading of general expenses two items which we here contend should be non-■dutiable. Tbe first is specified as: “Eee of tbe Legnano Elec. Corp. ($4,738.50 •converted to Lira at 626.95) 2,970,802.” And the second item under general ■expenses wbieb is identified as: “Bid and Performance Bond ($4,733.40 converted to (Lira at 625) 2,958,375.”

It was agreed between adversary counsel that the calculations set ■forth in said exhibit 3 are the calculations for cost of production used ■by the appraiser in this particular case, but that the costs stated there•on * * xelate .to three transformers of equal value * *

[496]*496For greater clarity, the computation of the cost of production of one transformer as found by the appraiser, and the importer’s claimed value thereof, are here set forth:

Item One transformer appraised value (Italian lira) One transformer importer claims (Italian lira)
(1) Cost of material 12, 679, 000 12, 679, 000
(2) Cost of fabrication 3, 904, 000 3, 904, 000
(3) General expenses 16, 583, 000 16, 583, 000
Expenses 2, 288, 454 2, 288, 454
Fee to Legnano 990, 267. 33
Bond costs 986, 125 (y) 0
Total expenses 4, 264, 846. 33 2, 288, 454
(4) Total of (1) (2) and (3) 20, 847, 846. 33 18, 871, 454
(5) Packing 246, 666. 66 246, 666. 67
(6) Profit— (8% of (4)) 1, 667, 827 1, 509, 716. 33
Total cost of production 22, 762, 340 20, 627, 837

It is the opinion of the court, based upon the entire record, that it was error for the appraiser to include as part of the cost of production the “Fee to Legnano” and the bond costs, above referred to. These-charges relating to activities and services performed in the United States should not, in the opinion of the court, bé allocated to “general expenses.”

As a matter of fact, if any doubt survives this conclusion, that doubt should be resolved in favor of the importer to the end that the subject transformer be appraised in accordance with the cost of production of the two identical transformers involved in Reap. Dec. 10229, supra.

Based upon the foregoing, the court makes the following findings of fact:

1.

Free access — add to your briefcase to read the full text and ask questions with AI

S. Jackson & Son, Inc. v. United States, 52 Cust. Ct. 493, 1964 Cust. Ct. LEXIS 1370 (cusc 1964).

52 Cust. Ct. 493 (S. Jackson & Son, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related