S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas

2023 Ark. App. 194
Court of Appeals of Arkansas·Decided April 5, 2023·Published

Opinion

Cite as 2023 Ark. App. 194 ARKANSAS COURT OF APPEALS DIVISION I

No. CV-20-356

S & J CONSTRUCTION CO., INC. Opinion Delivered April 5, 2023 APPELLANT

APPEAL FROM THE NEWTON

COUNTY CIRCUIT COURT

V. [NO. 51CV-15-52]

ENGINEERING SERVICES, INC.; AND HONORABLE GORDON WEBB,

OZARK MOUNTAIN REGIONAL JUDGE

PUBLIC WATER AUTHORITY OF THE STATE OF ARKANSAS APPELLEES

REVERSED AND REMANDED

WENDY SCHOLTENS WOOD, Judge Appellant, S & J Construction Company, Inc. (“S & J”), appeals an interlocutory order in which the Newton County Circuit Court denied S & J’s motion to amend a summary-judgment order that inadvertently dismissed S & J’s claims against appellee Engineering Services, Inc. (“ESI”). The circuit court denied S & J’s motion, stating it did not have authority to amend the order. We reverse and remand.

On December 16, 2010, Ozark Mountain Regional Public Water Authority of the State of Arkansas (“Ozark”) entered into multiple contracts with S & J for the construction of water pipelines and the attachment of the pipelines to two bridges on Highway 65 in Searcy County, Arkansas; and Highway 123 in Newton County, Arkansas. The contracts at issue identified ESI as the designer of the projects. Upon initial testing in September 2012,

the bridge attachments failed. In January 2013, S & J provided ESI with letters from two experts who concluded that ESI’s defective design caused the failures; nevertheless, S & J offered to pay half of the costs of repair. In October 2014, ESI sent a letter to Ozark alleging that S & J’s faulty construction was the cause of the failures. Subsequently, S & J sent a letter to Ozark asserting that ESI was the cause of the bridge-attachment failures, insisting that Ozark pay S & J for the repair work done to the bridges and requesting that the retainage on the contracts be released to S & J.

When Ozark refused to pay S & J the retainage and repair costs, S & J filed a breach-

of-contract action against Ozark in November 2015. In its complaint, S & J alleged that the bridge attachments were improperly designed. In its answer and counterclaim for interpleader against S & J and its third-party complaint for interpleader against ESI, Ozark claimed that it withheld the remaining payments to S & J on the basis of ESI’s position that the construction defects were the fault of S & J. Ozark sought to deposit the amounts due under the contracts into the registry of the court pending determination of the party at fault.

On January 24, 2018, Ozark asserted a cross-claim against ESI alleging that its flawed design, plans, and specifications were responsible for the failure of the pipeline-bridge attachments. On January 26, ESI filed a cross-claim against S & J for contribution or indemnity alleging that S & J’s construction was responsible for the pipeline failures. On February 9, S & J answered ESI’s cross-claim and filed an amended complaint adding a breach-of-contract claim against ESI alleging that the defects in the pipelines and bridge attachments were caused by ESI’s defective designs.

In March 2018, ESI filed a motion for summary judgment alleging that Ozark’s claims against ESI were barred by the statute of limitations. On February 21, 2019, the circuit court issued a letter opinion finding that S & J had not named ESI as a party defendant in the case. The court also granted ESI’s motion for summary judgment, stating that “[f]rom the [c]ourt’s point of view, the only issue as to ESI’s liability, comes from Ozark[’s] . . . crossclaim in January 2018 against ESI. . . . [T]he [c]ourt finds that ESI should be dismissed from the lawsuit based on the effective [statute of] limitation using A.C.A. § 16-56-105.” The circuit court directed ESI to draft the order.

ESI’s proposed summary-judgment order stated that “S & J did not sue ESI,” the statute of limitations barred Ozark’s cause of action against ESI, and ESI was dismissed from the lawsuit. The proposed order further stated that the court “retains jurisdiction to determine the other claims and counterclaims pending in this action between S & J and Ozark.”

Upon receipt of the proposed order, counsel for S & J, on March 1, 2019, notified the circuit court of the “material mistake” in its letter opinion in finding that S & J had not filed suit against ESI. S & J pointed out that its amended complaint named ESI as a party defendant and that the circuit court’s letter opinion “appears to be based upon a mistaken premise that S & J . . . had not sued ESI (when in truth and fact it had sued ESI over 1 year previously).” S & J requested that the circuit court revisit the issue and further stated that the proposed order submitted by ESI was “inaccurate and should not be entered.” Nevertheless, on March 3, 2019, the circuit court entered ESI’s proposed order granting

summary judgment in favor of ESI that included the incorrect finding that “S & J did not sue ESI.”

On March 8, the circuit court issued another letter opinion admitting “with embarrassment” its mistake in stating that S & J did not sue ESI. After acknowledging its error, the court directed ESI to prepare an amended summary-judgment order removing the finding that S & J had not sued ESI. ESI did not prepare the amended summary-judgment order as instructed by the court.

The circuit court’s March 8 letter opinion further instructed S & J to file a supplemental brief within fifteen days addressing how the amended summary-judgment order would affect the court’s dismissal of ESI. S & J timely filed a supplemental brief on March 18 arguing that ESI was still a proper party to the case, that S & J’s claims against ESI were rooted in contribution or indemnity, and that the statute of limitations on those claims had not expired. In its March 25 supplemental brief, ESI asserted that S & J ’s amended complaint raised only breach-of-contract claims against Ozark and ESI and that S & J’s breach-of-contract claims against ESI had been resolved in a settlement agreement between S & J and ESI on March 8, 2018.

Nearly three months later, on June 17, S & J wrote a letter to the circuit court asking it to hold a conference call or to rule on the parties’ supplemental briefs. After another three months with no response from the circuit court, on September 24, S & J filed a motion for an amended order confirming that ESI is still a party in the lawsuit with regard to S & J’s cross-claim against ESI. S & J asserted that its earlier pleadings alleged that the defects in the

pipelines and bridge attachments were caused by ESI’s defective design. S & J further argued that ESI moved for summary judgment only against Ozark, the circuit court had not considered S & J’s independent claims against ESI, and ESI failed to prepare the amended summary-judgment order as directed by the court.

ESI responded on October 2, contending that the circuit court’s March 2019 summary-judgment order dismissing all claims against ESI was a final order, was never appealed, and res judicata prevented consideration of S & J’s claims against ESI. ESI also moved for summary judgment against S & J on October 2, arguing that S & J’s claims were based in contract—not contribution or indemnity—and were barred by the statute of limitations. On October 28, S & J replied and argued that the court’s March 2019 order was not a final order from which it could have appealed. S & J further argued that, assuming the March 2019 order constituted a judgment, which S & J disputed, Rule 60(b) of the Arkansas Rules of Civil Procedure allowed the court to modify its order. ESI replied, arguing that Rule 60(b) applies only to clerical errors, which it claimed were not at issue here, and that Rule 60(a) precluded the court from modifying or vacating a judgment ninety days after it had been entered.

Free access — add to your briefcase to read the full text and ask questions with AI

S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas, 2023 Ark. App. 194 (Ark. Ct. App. 2023).

2023 Ark. App. 194 (S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Olsen v. East End School District
143 S.W.3d 576 (Court of Appeals of Arkansas, 2004)
Barker v. Clark
33 S.W.3d 476 (Supreme Court of Arkansas, 2000)
E-Z Cash Advance, Inc. v. Harris
60 S.W.3d 436 (Supreme Court of Arkansas, 2001)
Doe v. Baum
72 S.W.3d 476 (Supreme Court of Arkansas, 2002)
S. Farm Bureau Cas. Ins. Co. v. Parsons
2015 Ark. App. 95 (Court of Appeals of Arkansas, 2015)
McKim v. Sullivan
548 S.W.3d 835 (Court of Appeals of Arkansas, 2018)
Van DeVeer v. George's Flowers, Inc.
65 S.W.3d 488 (Court of Appeals of Arkansas, 2002)