S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas

2023 Ark. App. 194
CourtCourt of Appeals of Arkansas
DecidedApril 5, 2023
StatusPublished

This text of 2023 Ark. App. 194 (S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & J Construction Co., Inc. v. Engineering Services, Inc. And Ozark Mountain Regional Public Water Authority of the State of Arkansas, 2023 Ark. App. 194 (Ark. Ct. App. 2023).

Opinion

Cite as 2023 Ark. App. 194 ARKANSAS COURT OF APPEALS DIVISION I No. CV-20-356

S & J CONSTRUCTION CO., INC. Opinion Delivered April 5, 2023 APPELLANT APPEAL FROM THE NEWTON COUNTY CIRCUIT COURT V. [NO. 51CV-15-52]

ENGINEERING SERVICES, INC.; AND HONORABLE GORDON WEBB, OZARK MOUNTAIN REGIONAL JUDGE PUBLIC WATER AUTHORITY OF THE STATE OF ARKANSAS APPELLEES REVERSED AND REMANDED

WENDY SCHOLTENS WOOD, Judge

Appellant, S & J Construction Company, Inc. (“S & J”), appeals an interlocutory

order in which the Newton County Circuit Court denied S & J’s motion to amend a

summary-judgment order that inadvertently dismissed S & J’s claims against appellee

Engineering Services, Inc. (“ESI”). The circuit court denied S & J’s motion, stating it did not

have authority to amend the order. We reverse and remand.

On December 16, 2010, Ozark Mountain Regional Public Water Authority of the

State of Arkansas (“Ozark”) entered into multiple contracts with S & J for the construction

of water pipelines and the attachment of the pipelines to two bridges on Highway 65 in

Searcy County, Arkansas; and Highway 123 in Newton County, Arkansas. The contracts at

issue identified ESI as the designer of the projects. Upon initial testing in September 2012, the bridge attachments failed. In January 2013, S & J provided ESI with letters from two

experts who concluded that ESI’s defective design caused the failures; nevertheless, S & J

offered to pay half of the costs of repair. In October 2014, ESI sent a letter to Ozark alleging

that S & J’s faulty construction was the cause of the failures. Subsequently, S & J sent a letter

to Ozark asserting that ESI was the cause of the bridge-attachment failures, insisting that

Ozark pay S & J for the repair work done to the bridges and requesting that the retainage

on the contracts be released to S & J.

When Ozark refused to pay S & J the retainage and repair costs, S & J filed a breach-

of-contract action against Ozark in November 2015. In its complaint, S & J alleged that the

bridge attachments were improperly designed. In its answer and counterclaim for

interpleader against S & J and its third-party complaint for interpleader against ESI, Ozark

claimed that it withheld the remaining payments to S & J on the basis of ESI’s position that

the construction defects were the fault of S & J. Ozark sought to deposit the amounts due

under the contracts into the registry of the court pending determination of the party at fault.

On January 24, 2018, Ozark asserted a cross-claim against ESI alleging that its flawed

design, plans, and specifications were responsible for the failure of the pipeline-bridge

attachments. On January 26, ESI filed a cross-claim against S & J for contribution or

indemnity alleging that S & J’s construction was responsible for the pipeline failures. On

February 9, S & J answered ESI’s cross-claim and filed an amended complaint adding a

breach-of-contract claim against ESI alleging that the defects in the pipelines and bridge

attachments were caused by ESI’s defective designs.

2 In March 2018, ESI filed a motion for summary judgment alleging that Ozark’s claims

against ESI were barred by the statute of limitations. On February 21, 2019, the circuit court

issued a letter opinion finding that S & J had not named ESI as a party defendant in the

case. The court also granted ESI’s motion for summary judgment, stating that “[f]rom the

[c]ourt’s point of view, the only issue as to ESI’s liability, comes from Ozark[’s] . . . crossclaim

in January 2018 against ESI. . . . [T]he [c]ourt finds that ESI should be dismissed from the

lawsuit based on the effective [statute of] limitation using A.C.A. § 16-56-105.” The circuit

court directed ESI to draft the order.

ESI’s proposed summary-judgment order stated that “S & J did not sue ESI,” the

statute of limitations barred Ozark’s cause of action against ESI, and ESI was dismissed from

the lawsuit. The proposed order further stated that the court “retains jurisdiction to

determine the other claims and counterclaims pending in this action between S & J and

Ozark.”

Upon receipt of the proposed order, counsel for S & J, on March 1, 2019, notified

the circuit court of the “material mistake” in its letter opinion in finding that S & J had not

filed suit against ESI. S & J pointed out that its amended complaint named ESI as a party

defendant and that the circuit court’s letter opinion “appears to be based upon a mistaken

premise that S & J . . . had not sued ESI (when in truth and fact it had sued ESI over 1 year

previously).” S & J requested that the circuit court revisit the issue and further stated that

the proposed order submitted by ESI was “inaccurate and should not be entered.”

Nevertheless, on March 3, 2019, the circuit court entered ESI’s proposed order granting

3 summary judgment in favor of ESI that included the incorrect finding that “S & J did not

sue ESI.”

On March 8, the circuit court issued another letter opinion admitting “with

embarrassment” its mistake in stating that S & J did not sue ESI. After acknowledging its

error, the court directed ESI to prepare an amended summary-judgment order removing the

finding that S & J had not sued ESI. ESI did not prepare the amended summary-judgment

order as instructed by the court.

The circuit court’s March 8 letter opinion further instructed S & J to file a

supplemental brief within fifteen days addressing how the amended summary-judgment

order would affect the court’s dismissal of ESI. S & J timely filed a supplemental brief on

March 18 arguing that ESI was still a proper party to the case, that S & J’s claims against ESI

were rooted in contribution or indemnity, and that the statute of limitations on those claims

had not expired. In its March 25 supplemental brief, ESI asserted that S & J ’s amended

complaint raised only breach-of-contract claims against Ozark and ESI and that S & J’s

breach-of-contract claims against ESI had been resolved in a settlement agreement between

S & J and ESI on March 8, 2018.

Nearly three months later, on June 17, S & J wrote a letter to the circuit court asking

it to hold a conference call or to rule on the parties’ supplemental briefs. After another three

months with no response from the circuit court, on September 24, S & J filed a motion for

an amended order confirming that ESI is still a party in the lawsuit with regard to S & J’s

cross-claim against ESI. S & J asserted that its earlier pleadings alleged that the defects in the

4 pipelines and bridge attachments were caused by ESI’s defective design. S & J further argued

that ESI moved for summary judgment only against Ozark, the circuit court had not

considered S & J’s independent claims against ESI, and ESI failed to prepare the amended

summary-judgment order as directed by the court.

ESI responded on October 2, contending that the circuit court’s March 2019

summary-judgment order dismissing all claims against ESI was a final order, was never

appealed, and res judicata prevented consideration of S & J’s claims against ESI. ESI also

moved for summary judgment against S & J on October 2, arguing that S & J’s claims were

based in contract—not contribution or indemnity—and were barred by the statute of

limitations. On October 28, S & J replied and argued that the court’s March 2019 order was

not a final order from which it could have appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olsen v. East End School District
143 S.W.3d 576 (Court of Appeals of Arkansas, 2004)
Barker v. Clark
33 S.W.3d 476 (Supreme Court of Arkansas, 2000)
E-Z Cash Advance, Inc. v. Harris
60 S.W.3d 436 (Supreme Court of Arkansas, 2001)
Doe v. Baum
72 S.W.3d 476 (Supreme Court of Arkansas, 2002)
S. Farm Bureau Cas. Ins. Co. v. Parsons
2015 Ark. App. 95 (Court of Appeals of Arkansas, 2015)
McKim v. Sullivan
548 S.W.3d 835 (Court of Appeals of Arkansas, 2018)
Van DeVeer v. George's Flowers, Inc.
65 S.W.3d 488 (Court of Appeals of Arkansas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2023 Ark. App. 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-j-construction-co-inc-v-engineering-services-inc-and-ozark-arkctapp-2023.