S. A. Healy Co. v. United States

140 Ct. Cl. 554, 1957 U.S. Ct. Cl. LEXIS 144, 1957 WL 8276
CourtUnited States Court of Claims
DecidedDecember 4, 1957
DocketCong. No. 4—54
StatusPublished
Cited by1 cases

This text of 140 Ct. Cl. 554 (S. A. Healy Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. A. Healy Co. v. United States, 140 Ct. Cl. 554, 1957 U.S. Ct. Cl. LEXIS 144, 1957 WL 8276 (cc 1957).

Opinion

Opinion

per curiam:

A commissioner of this court, after a full hearing of the evidence, made findings of fact to which neither the plaintiff nor the Government has taken exception. The court adopts and approves those findings. They show [555]*555that tbe plaintiff entered into a contract with, the Government to perform certain construction work for a fixed sum of money. The contract contained no escalator clause or other language entitling the contractor to a larger compensation if its costs should be increased by increases in wage rates or material prices. The contract was negotiated at a time when hostilities in Europe had already ended and it was easily forseeable that hostilities in the Pacific would soon be over.

When Japan surrendered, the Government eased controls of wages and materials, and wages and prices went up. The plaintiff, largely through a subcontractor, performed its contract well, and it and the subcontractor lost money.

The plaintiff recognizes that it has no claim which could be maintained in a court proceeding at law or in equity. It claims, however, that, in the circumstances, the Government is bound in morals and honor to compensate the plaintiff for its losses. The court supposes that a considerable number of contractors with the Government, as well as a considerable number of contractors in private enterprises, suffered losses because of the removal of wage and price controls during the performance of their contracts. If this plaintiff is to be regarded as morally entitled to compensation for its losses, other contractors similarly situated would be. similarly entitled. The question thus becomes an important question of fiscal policy, which must be answered by the Congress. We think that, in these circumstances, it might be confusing rather than helpful for us to make a recommendation to the Congress. We therefore limit our report to the facts as we have found them.

FINDINGS OF FACT

The court, having considered the evidence, the report of Commissioner Roald A. Hogenson, and the briefs and arguments of counsel, makes findings of fact as follows:

1. Plaintiff, an Ohio corporation with its principal office at White Plains, New York, is the claimant named in Senate Resolution 240, 83rd Congress, 2nd Session, passed May 4, 1954, which provides as follows:

Resolved\ That the bill (S. 1162) entitled; “A bill for the relief of S. A. Healy Company,” now pending [556]*556in the Senate, together with all accompanying papers, is hereby referred to the United States Court of Claims pursuant to sections 1492 and 2509 of title 28, United States Code; and said court shall proceed expeditiously with the same, in accordance with the provisions of said sections, and report to the Senate, at the earliest practicable date, giving such findings of fact and conclusions thereon as shan be sufficient to inform the Congress of the nature and character of the demand, as a claim legal or equitable, against the United States, and the amount, if any, legally or equitably due from the United States to the claimant.

S. 1762, 83rd Congress, proposed that the Secretary of the Treasury be authorized to pay to plaintiff in full payment of all claims against the United States for losses plaintiff sustained in connection with contracts numbered NOy-12759 and NOy-12806, the sum of $547,803.87.

The petition in this case was filed on August 3, 1954.

2. On November 29, 1944, President Franklin D. Roosevelt, having been informed as to an impending emergency in the water supply of San Diego County, California, decided that the situation was of emergency importance to the Federal Government due to the “very large naval, other military, war industrial, and war-housing installations in the area,” and directed the construction of an aqueduct by the Bureau of Yards and Docks, Navy Department, to meet this emergency.

3. Construction contracts were awarded to various contractors on the basis of competitive bids submitted on various sections of the project pursuant to invitations to bid issued to a select group of bidders. Plaintiff heard of the proposed project and sent one of its engineers to San Diego where he requested the Navy to include plaintiff on the list of bidders. Plaintiff was placed on the list, and thereafter received invitations to bid on each of the sections of the aqueduct. Two of the several sections or parts of the project áre involved in this case.

4. The invitation to bid on specifications for contract NOy-12759, hereinafter called the pipeline contract, was issued on .June 26, 1945, with the requirement that the bid be submitted on or before August 1, 1945. The pipeline [557]*557contract envisaged the construction of a concrete pipeline and structures over a distance of about 24.5 miles in the vicinity of Escondido, San Diego County, California. The specifications required the furnishing of all materials, equipment and labor for excavations, construction and placing of concrete pipe, concrete vents, manholes, blowoff and riser structures, including appurtenant parts and accessories, and various crossings and fencing.

5. The invitation to bid on specifications for contract NOy-12806, hereinafter referred to as the tunnel contract, was issued on or about July 10, 1945, with the requirement that the bid be submitted on or before August 8, 1945. The tunnel contract envisaged the construction of the Rainbow, Lilac, Red Mountain and Oat Hills Tunnels, totaling about 11,750 linear feet in length, in San Diego County, California. The specifications required the furnishing of all materials for the construction of the four tunnels and the use of structural and reinforcing steel, timber, concrete aggregates, Portland cement and sewer pipe drains.

6. Upon receipt of the aforesaid invitations to bid, plaintiff sent three of its engineers to California to investigate the subject matter of the proposals and to advise plaintiff with respect to submission of bids. Their investigation consisted of an examination of the detailed specifications which had been prepared and filed by the Bureau of Yards and Docks, including the requirements with respect to materials and payment of minimum wage rates set forth in the specifications, physical examination of the site of the proposed pipeline and tunnels, and a telephone conversation with the secretary of the Secretary of the San Diego Building Trades Council to verify that there had been no error in printing of the minimum wages set forth in the specifications. Plaintiff made general inquiry and was advised, as the fact was, that the prevailing wages were those set forth in the specifications. Plaintiff received no information as to whether or not there was any contemplated change in wage rates.

7. The specifications prepared by the Bureau of Yards and Docks set forth the minimum rates which were to be paid to workers engaged in the construction performed under the contracts.

[558]*5588. At the time plaintiff prepared and submitted its bids, wage rates and material prices were controlled pursuant to Executive Order 9250, National War Labor Board General Order No. 18, and Maximum Price Regulations of the Office of Price Administration. These controls provided that an employer could not increase the wages of his employees without authorization from the National War Labor Board or the War Manpower Commission, and that materials might not be sold at prices higher than those contained in Maximum Price Regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lym v. United States
142 Ct. Cl. 143 (Court of Claims, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
140 Ct. Cl. 554, 1957 U.S. Ct. Cl. LEXIS 144, 1957 WL 8276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-a-healy-co-v-united-states-cc-1957.