Ryan v. Feeney & Sheehan Building Co.

202 A.D. 45, 195 N.Y.S. 365, 1922 N.Y. App. Div. LEXIS 4849

Opinion

Cochrane, P. J.:

On April 11, 1918, the government of the United States contracted with the defendant for the construction of a quartermaster interior storage depot at South Schenectady, N. Y., in accordance with drawings and specifications to be furnished by the contracting officer of the government. The building was constructed by the defendant according to such drawings and specifications. The entire length of the building was nearly one-third of a mile. Attached to the building at its side was a canopy in twelve sections of approximately 140 feet each in length. The canopy was supported by seven-eighths-inch truss rods extending at an angle from the side of the main building downward to the outer edge of the canopy. The distance between the rods was about 13 feet. These rods were constructed with four welds one at each end and two where a turnbuckle arrangement was adjusted in the middle. The purpose of the welds at the extremities was to transform the rods in»to plates so that one end might be adjusted to the side of the main building and the other to the outer edge of the canopy. The plates were two and one-half inches wide and one-half inch thick. The plate at the outer extremity was so fashioned with respect to the rod that the plate passed over the edge of the canopy and fitted against the outer side thereof and was bolted to the canopy. The building was completed January 31, 1919. On or before [47] March 29, 1919, there occurred a fall of snow containing much water which by reason of a strong wind was drifted onto the canopy in some instances to the depth of three feet. This unusual weight caused the canopy to fall in sections. Two sections fell during the night preceding the morning of March twenty-ninth. A gang of men was organized to place supporting columns under the remaining sections of the canopy. While thus engaged supporting one section another section fell and a son of the plaintiff was killed. Every supporting truss rod was broken at the exterior weld at the edge of the canopy, the rods themselves hanging from the side of the building. The plaintiff has recovered a judgment herein against the defendant for the loss she has sustained because of the death of her son.

The defendant has been held liable because the plan for the construction of the canopy was so obviously defective and dangerous to human life that a contractor of average skill and ordinary prudence would not have attempted its construction according to the plan proposed. That was the question submitted to the jury under the principle enunciated but not applied in Hardie v. Boland Company (205 N. Y. 336) and Cochran v. Sess (168 id. 372). Those were cases involving accidents occurring during the performance of building contracts. In the latter case the reason of the principle was stated as follows: Any one who participates in the construction of any structure which is obviously dangerous to human life is a party to the creation of a nuisance, and engaged in an active wrong for the consequences of which he may be subjected to pecuniary responsibility. It is upon this theory, and this theory alone, as it seems to us, that the defendants must be held responsible.” In Uggla v. Brokaw (117 App. Div. 586) it was held that in order to charge a landlord with the consequences of an accident due to a building being out of repair while in the possession of a tenant it must be shown that the accident was the result of a condition constituting a nuisance existing at the time the landlord surrendered possession to the tenant.

The contract under which the defendant constructed the building contained the following recitals:

“ Whebeas, the Congress having declared by Joint Resolution approved April 6, 1917, that war exists between the United States of Amercia and Germany, a national emergency exists and the United States urgently requires the immediate performance of the work hereinafter described, and it is necessary that said work shall be completed within the shortest possible time; and
“ Whebeas, it is advisable, under the disturbed conditions which exist in the contracting industry throughout the country, [48] for the United States to depart from the usual procedure in the matter of letting contracts, and adopt means that will insure the most expeditious results.”

The contract then provided that the contractor should in the shortest possible time ” furnish the labor and material necessary for the completion of the building “ in accordance with the drawings and specifications to be furnished by the contracting officer and subject in every detail to his supervision, direction and instruction,”

Free access — add to your briefcase to read the full text and ask questions with AI

Ryan v. Feeney & Sheehan Building Co., 202 A.D. 45, 195 N.Y.S. 365, 1922 N.Y. App. Div. LEXIS 4849 (N.Y. Ct. App. 1922).

202 A.D. 45 (Ryan v. Feeney & Sheehan Building Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hardie v. Charles P. Boland Co.
98 N.E. 661 (New York Court of Appeals, 1912)
Uggla v. Brokaw
117 A.D. 586 (Appellate Division of the Supreme Court of New York, 1907)