Ryan v. B & G Crane Service, Inc.

210 So. 2d 514, 1968 La. App. LEXIS 5086
CourtLouisiana Court of Appeal
DecidedMay 6, 1968
DocketNo. 3014
StatusPublished
Cited by2 cases

This text of 210 So. 2d 514 (Ryan v. B & G Crane Service, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryan v. B & G Crane Service, Inc., 210 So. 2d 514, 1968 La. App. LEXIS 5086 (La. Ct. App. 1968).

Opinion

JOHNSON, Judge.

The plaintiff, Harold Ryan (hereinafter called Ryan), an individual, brought this tort action for damages for accidental personal injuries against the defendants, B & G Crane Service, Inc., (hereinafter called Crane Service), and Aetna Casualty and Surety Company, the Crane Service’s public liability insurer. After trial on the merits the Civil District Court for the Parish of Orleans rendered judgment on July 14, 1967, in favor of the defendants, dismissing plaintiff’s suit and plaintiff has appealed.

The plaintiff was employed by Maritime Electric Company (hereinafter called Maritime), in a hazardous occupation. The accident happened on February 18, 1963, while plaintiff was performing his duties. This suit was filed on February 17, 1964, against defendant Crane Service as a third party tort-feasor. The Fidelity and Casualty Company of New York, for Maritime, paid workmen’s compensation to plaintiff and paid medical benefits on behalf of plaintiff. On April 16, 1964, the Fidelity and Casualty Company of New York intervened in this suit to recover the amounts paid. The judgment of the trial court of July 14, 1967, also dismissed this intervention.

To epitomize the allegations of plaintiff’s petition, it is alleged that Maritime was constructing a high voltage steel tower near Michoud in Orleans Parish; that the tower was to be built in excess of 200 feet in height and Maritime rented from Crane Service a crane of the crawler type with all necessary parts including a boom of sufficient length to reach the top of the tower; that the boom was made up of steel pipe or tubing in sections 30 feet long and about 5 feet square; that Crane Service employees delivered these boom sections to the site by truck and were unloaded by Maritime employees; that the boom sections are fastened end to end to extend the boom to the desired length; that with each section the Crane Service delivered two steel wire cables of about an inch and a half in diameter, conforming in length to each section, which are called pendant lines weighing about 125 pounds each; that they were placed lengthwise on top of each boom section on the truck when the boom sections were delivered to Maritime; that to unload the boom sections a smaller crane was used to lift the boom sections with the pendant lines from the truck; that plaintiff with two other Maritime employees went upon the truck to hook the lifting or spreader lines to the boom section and when the crane operator partially lifted the boom section from the bed of the truck the pendant lines lying on top of the section shifted position which caused the boom section to become off balance; that the spreader lines came unhooked from the section at one end causing the section to swing or turn and strike plaintiff, knocking him violently to the ground and injuring him seriously. The plaintiff alleges that Crane Service was negligent in failing to fasten the pendant lines to the boom section to prevent the lines from moving when the boom section is lifted off the truck; that the improperly secured lines without a safety catch attaching them to the section on the truck constituted a trap; that plaintiff should have been' warned of this condition, all of which was negligence on -the part of Crane Service and its employees.

The answer of defendant denies generally that there was any negligence on the part of Crane Service or its employees and defendants allege that the cause of the accident was the negligence of plaintiff [516]*516and others who were not under the control and direction of defendants. The answer admitted that Maritime had rented a large crane from Crane Service including the boom sections and that Crane Service was delivering the sections to plaintiff’s employer, but that the unloading of the parts was to be and was being done entirely by employees of Maritime, including the plaintiff.

As we understand it, the boom of some 200 feet long to be used on the large crane is made up of steel piping or tubing with crossbars and braces. The sections are fastened together to make up the boom and running with the sections are two pendant lines of heavy wire cable which are fastened together end to end along the entire length of the boom. They served in lifting and lowering the boom and we presume, though it is not clearly described, that these pendant lines are fastened at the top and bottom of the boom to act as a safety chain to give strength to the boom. Then there is a lift cable that runs from the drum at the bottom through the boom, around the top end and down to handle the work load. At the end of that lift cable is a large metal ball, called headache ball, to give weight to bring the line down when there is no load on it.

Two pendant lines were delivered with each 30 foot boom section conforming in length to each boom section and they were lying on top of the boom section on the truck when the truck arrived on the Maritime site. The sections and lines were delivered by Crane Service truck and employees but were unloaded by employees of Maritime. After having unloaded one section from the truck that morning without incident, the plaintiff and two other men got on the bed of the truck to fasten the two spreader lines, one to each end of the section. A small crane was used to unload the boom sections. These spreader lines were each about 20 feet long and after one end was hooked by plaintiff at the end of the leg of the section and one end of the other spreader line was hooked by the other two men to the opposite leg of the section at the other end, the two spreader lines are hooked into the main lift line from the small crane boom. In this manner the two spreader lines form an inverted “V”.

Referring to plaintiff’s testimony in his own behalf, he said that he was 46 years old and had worked for many years as a lineman electrician in the construction of high voltage towers. On that day he and other Maritime employees were unloading from a truck the 30 foot boom sections to be used on the large crawler crane to extend the boom to the desired length. These men had already unloaded one section from that same truck without incident and they went about unloading the second section in the same manner. The sections were exactly alike. Plaintiff got on the rear of the truck. The other men were on the front end next to the cab of the truck. Plaintiff’s job was to wrap one end of the spreader line around the outside leg of the section at the rear of the truck. It tightened itself as the section was picked up. The other men at the front end of the truck did the same thing with the other spreader line, but attached the line to the opposite leg of the section so that the lines were hooked “crisscross * * * one opposite the other” on the section. Plaintiff said he saw the pendant lines lying on the section when he attached the spreader line. When one of the men gave the word that the spreader lines were hooked the crane operator lifted the section about a foot or two above the bed of the truck and stopped it to check the load balance. The load seemed to be in perfect balance and plaintiff said it was time then to get off the truck. We quote the following from his testimony:

“After I secured my end I stood there waiting for them to come up, and when I saw them come up so far with it I started to make a turn sort of to get down, figuring everything was okay to get off the truck, and when I did the [517]*517next thing you know it looked like everything came at me, the whole thing came flying at me, and with that I leaped to keep it from knocking me off backwards, and the next thing I knew I went flying in the air and I don’t remember anything more than that.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. New Orleans Public Belt RR
375 So. 2d 395 (Louisiana Court of Appeal, 1979)
Ryan v. B & G Crane Service, Inc.
214 So. 2d 165 (Supreme Court of Louisiana, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
210 So. 2d 514, 1968 La. App. LEXIS 5086, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-v-b-g-crane-service-inc-lactapp-1968.