Rust of Kentucky, Inc. v. TMS Contracting, LLC (In Re Rust of Kentucky, Inc.)

439 B.R. 409, 2010 Bankr. LEXIS 3835, 2010 WL 4510894
CourtUnited States Bankruptcy Court, W.D. Kentucky
DecidedNovember 10, 2010
Docket19-30161
StatusPublished

This text of 439 B.R. 409 (Rust of Kentucky, Inc. v. TMS Contracting, LLC (In Re Rust of Kentucky, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rust of Kentucky, Inc. v. TMS Contracting, LLC (In Re Rust of Kentucky, Inc.), 439 B.R. 409, 2010 Bankr. LEXIS 3835, 2010 WL 4510894 (Ky. 2010).

Opinion

MEMORANDUM-OPINION

JOAN A. LLOYD, Bankruptcy Judge.

This matter is before the Court on the Motion of TMS Contracting, LLC (“TMS”) *411 to Compel Arbitration and Stay Adversary Proceeding. The Court considered the Motion of TMS, the Motion of Fidelity & Deposit Company of Maryland (“Fidelity”) Joining in the Motion of TMS to Compel Arbitration, the Objection to the Motion to Compel Arbitration of Plaintiff/Debtor Rust of Kentucky, Inc. (“Rust”), the Reply of TMS and the comments of counsel for the parties at the hearing held on the matter. For the following reasons, the Court DENIES the Motion to Compel Arbitration and Stay Adversary Proceeding.

PROCEDURAL BACKGROUND

TMS entered into a contract to perform as general contractor for the City of Clarksville, Tennessee (“City”) to construct a marina, boat launch, park and storm water management system (the “Project”). TMS subcontracted the site work to Rust under two subcontract agreements whereby Rust was to do excavation work for the park and marina (“the Subcontracts”).

Fidelity, as surety on the Project, issued a payment bond to TMS as principal and the City as obligee. The purpose of the Bond is to jointly and severally bind TMS and Fidelity “to pay for labor, materials and equipment furnished by Claimants for use in performance of the contract ... ”. Fidelity also issued performance bonds to Rust naming TMS as obligee, assuring Rust’s performance of the Subcontracts.

Several disputes arose between Rust and TMS during the course of the Project. As a result of these disputes, TMS stopped making payments to Rust and Rust stopped work on the Project.

The subcontracts contain the following provisions:

13.7Direct Discussion
If a dispute arises out of or relates to this Agreement, the parties shall endeavor to settle the dispute through direct discussion.
13.8 Mediation
Disputes between Subcontractor and Contractor not resolved by direct discussion shall be submitted to mediation pursuant to the Construction Industry Mediation Rules of the American Arbitration Association. The parties shall select the mediator within fifteen (15) calendar days of the request for mediation. Engaging in mediation is a condition precedent to any form of binding dispute resolution.
13.9 Other Dispute Processes
If neither direct discussions nor mediation successfully resolve the dispute, the parties agree that the following shall be used to resolve the dispute.
13.9.1 Arbitration
Arbitration shall be pursuant to the Construction Industry Rules of the American Arbitration Association, unless the parties mutually agree otherwise. A written demand for arbitration shall be filed with the American Arbitration Association and the other party to the Agreement within a reasonable time after the dispute or claim has arisen, but in no event after the applicable statute of limitations for a legal or equitable proceeding has run. The arbitration award shall be final. This agreement to arbitrate shall be governed by the Federal Arbitration Act, and judgment upon the award may be confirmed in any court having jurisdiction.
13.9.2 Litigation
Action may be filed in the appropriate state or federal court.

In November 2009, pursuant to the Subcontract, Rust requested that the matter go to mediation. TMS refused to engage in mediation contending the parties had not engaged in direct discussions to re *412 solve the matter, a condition it asserted was a condition precedent to mediation.

In February 2010, TMS declared Rust in default under both Subcontracts. Shortly thereafter, on February 22, 2010, Rust filed its Voluntary Petition under Chapter 11 of the United States Bankruptcy Code. In the course of the Chapter 11 case, Rust moved to reject both of the Subcontracts.

Fidelity paid TMS $2,977,926.17 under the Performance Bond.

On June 30, 2010, Fidelity filed Proof of Claim No. 22 and subsequently amended that claim to $8,520,889, the amount Fidelity paid to TMS on the Performance Bond and the amount TMS paid on Rust’s Performance Bond.

On or about August 11, 2010, Rust initiated this adversary proceeding asserting claims against TMS for breach of the Subcontracts and against Fidelity under the Payment Bond on the Project.

LEGAL ANALYSIS

TMS and Fidelity seek an Order from this Court staying this adversary proceeding and compelling this matter to arbitration pursuant to subparagraph 3.9.1 of the Subcontract between Rust and TMS. Rust, however, contends that provision, when read in context with other provisions of the Subcontract, is not mandatory.

The Court begins its analysis with basic rules of contract construction. A contract will not be construed so as to reject any words as surplusage if they reasonably can be given meaning. Union Inv. v. Fidelity & Deposit Co. of Maryland, 549 F.2d 1107, 1110 (6th Cir.1977). Each individual provision should be given a meaning that allows the entire contract to be given effect. An interpretation that gives a reasonable meaning to all parts of the contract is preferred to one that leaves provisions meaningless. Id. A court should attempt to give meaning to all provisions of a contract. Cincinnati Gas & Elec. v. F.E.R.C., 724 F.2d 550 (6th Cir. 1984).

The Defendants’ request to compel arbitration of the underlying dispute relies only on one provision of the Subcontract and its interpretation cannot stand in light of the other sections of the Subcontract. Under paragraph 13.8, the Subcontract states, “Disputes between Subcontractor and Contractor not resolved by direct discussion shall be submitted to mediation ... ”. The paragraph prior to this one provides that if a dispute arises, “... the parties shall endeavor to settle the dispute through direct discussion.” Under paragraph 13.9, “If neither direct discussions nor mediation successfully resolve the dispute, the parties agree that the following shall be used to resolve the dispute ...” What follows this provision is subsection 13.9.1 on arbitration and subsection 13.9.2 which states, “action may be filed in the appropriate state or federal court.”

Reading all of these provisions together, the Court is convinced that the conditions precedent to referring the matter to arbitration did not occur before this action was filed. Rust sought to invoke direct discussions and mediation, prerequisites to any required arbitration, but its efforts were not successful. In fact, TMS, the party seeking to enforce the arbitration provision, refused to engage in mediation contending that the condition precedent to mediation, direct discussions under paragraph 13.7, had not occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
439 B.R. 409, 2010 Bankr. LEXIS 3835, 2010 WL 4510894, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rust-of-kentucky-inc-v-tms-contracting-llc-in-re-rust-of-kentucky-kywb-2010.