Russell v. Stillwell

288 P. 785, 106 Cal. App. 88, 1930 Cal. App. LEXIS 564
CourtCalifornia Court of Appeal
DecidedMay 27, 1930
DocketDocket No. 7234.
StatusPublished
Cited by1 cases

This text of 288 P. 785 (Russell v. Stillwell) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Russell v. Stillwell, 288 P. 785, 106 Cal. App. 88, 1930 Cal. App. LEXIS 564 (Cal. Ct. App. 1930).

Opinion

THE COURT.

COURT. —• This is an action to recover fees for architects’ services alleged to have been performed by respondents under a contract entered into by them with appellants to furnish plans, specifications, detailed drawings and superintendence of the building of a class “A” apartment house in the city of Long Beach. Judgment was entered in favor of plaintiffs for $43,950, and from such judgment defendants have appealed.

In April or May, 1923, the respondents were verbally employed by appellants to prepare preliminary sketches or working plans for the construction of the building in question, which they did. On October 1, 1923, the architects prepared and submitted to the owners a standard form of architect’s contract, which so far as is necessary to a consideration of the questions here presented is as follows: “For a compensation to the architects of five (5%) per cent of the cost of the building, the architects, Russell & Alpaugh, agree to furnish promotion drawings, consisting of typical floor plan, first floor, basement and perspective drawings, and to furnish preliminary sketches, contract working drawings, and specifications, detail working drawings, and to furnish General Superintendence and do audit all accounts for the erection of a Class ‘A’ Apartment building. . . . Terms of payment to be as follows: %% upon acceptance of preliminary" plan. %% when working plans are one-half complete. 1% when working plans and specifications are com *91 píete. 2%% to be made to the architects as the building progresses in proportion to the cost of the work executed. It is further understood and agreed that the architects will proceed with the above contract and accept payments as follows: One thousand ($1000) dollars on or before one week after the execution of this contract and the sum of one thousand dollars ($1000) each and every week thereafter until a total of twelve thousand ($12000) has been paid by the Owners to the Architects. . . . The amount of the Architect’s compensation is to be reckoned upon the total cost of the building, including all stationary fixtures.” The contract not being satisfactory to appellants, the following addendum was added: “It is further understood and agreed that in case a satisfactory bond issue and financing cannot be arranged after the termination of the twelve weekly payments and the completion of the plans, we can pay the balance of the payments at the rate of five hundred dollars per week until the total of twenty-five thousand has been paid, which shall be liquidated damages. Also, Russell and Alpaugh shall each take two single apartments at the present rates as final payment of architects fees. A blue print for each apartment shall be furnished without additional cost if required and sufficient blue prints for salesmen or promotion. ’ ’

Numerous objections are urged as to findings not being supported by the evidence, but if there is merit in the points made by appellants that the court erred in finding that defendants had stipulated that the contract sued upon was ambiguous and required oral testimony to interpret and explain, it erred in admitting and considering parol evidence to vary the terms of the written contract, and finding the contract entirely different from the written contract set up in plaintiff’s complaint, the ease is disposed of, and discussion of objections to other findings becomes unimportant.

It will be observed that in the contract the payment of the five per cent commission is divided into four classes— ‘%% upon acceptance of preliminary plan; %% when working plans are one-half complete; 1% when working plans and specifications are complete; 2½/% to be made to the architects as the building progresses in proportion to the cost of the work executed.” When the contract was presented to appellant Charles H. Stillwell he stated, according *92 to the testimony of respondent Russell: “ ‘$25,000.00 is all I want to gamble.’ "We said ‘all right,’ so I dictated that clause myself, and we put it in and it was signed under that arrangement. ’ ’ The addendum, which was then signed with the contract as one instrument, contains the provision: “It is further agreed that in ease a satisfactory bond issue cannot be arranged after the completion of the plans, we can pay the balance . . . until the total of twenty-five thousand has been paid which shall be liquidated damages. ’ ’

We can see but one construction that can be placed upon the words in the added clause “the completion of the plans,” and that is all plans before mentioned in the contract—not merely preliminary plans. The words themselves require no explanation. If they did it could be found in the contract itself. In the absence of fraud, where the parties have reduced to writing what appears to be a complete and certain agreement, parol evidence will not be permitted for the purpose of varying the written contract. Section 1647 of the Civil Code and section 1860 of the Code of Civil Procedure simply enact the common-law rule, and it is not within their contemplation that a contract reduced to writing and executed shall have anything added to it nor taken away from it by evidence of surrounding circumstances; the rule is only employed where upon the face of the contract itself there is doubt, and the evidence is used to dispel this doubt (United Iron Works v. Outer Harbor Hock & Wharf Co., 168 Cal. 81 [141 Pac. 917]). Respondents do not controvert this rule, but rely for support of the court’s finding on the ground that the contract is ambiguous because it is so stipulated by the parties, basing their claim in this respect on the following: “The Court: Do you claim the contract is ambiguous? Mr. Hammon: No. The Court: Then all the conversations are embodied in the contract, are they not ? Mr. Hammon: Under section 1860 of the Code of Civil Procedure we are permitted to show the circumstances. The Court: You are permitted, provided you allege ' the contract is ambiguous. Mr. Wheeler: We agree that it is ambiguous and have no objection. The Court: That settles it. There is no allegation in the pleadings of that character.” And during the examination of respondent Russell by his counsel appears the following: “Q. Then do I understand that I may offer these *93 three layouts or preliminary sketches of that building 100 by 100 feet? I would like to have them admitted in evidence by way of illustration. The Court: What was the objection? Mr. Hammon: Objected to on the ground they are irrelevant and immaterial. There is no issue on that point in the pleadings. Mr. Wheeler: They serve the purpose of explaining. How is the court to arrive at when we are entitled to $25,000.00 and when we are entitled to $80,000.00? We are to do one lot of work for $25,000.00, and we are to do a totally different work for $80,000.00, and we cannot explain the difference without introducing these plans in their periodic contractual relationship. That is why I say this contract is ambiguous; that it applies to one subdivision of these plans only, not to all of them. The Court: Sustained under the pleadings. ’ ’

From the foregoing, which is all that is called to our attention by either of the parties, we do not see any justification for the claim that appellants stipulated that the contract is ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Russell
47 P.2d 305 (California Court of Appeal, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
288 P. 785, 106 Cal. App. 88, 1930 Cal. App. LEXIS 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/russell-v-stillwell-calctapp-1930.