Russell v. Bohn Mfg. Co.

85 F. 991, 29 C.C.A. 681, 1898 U.S. App. LEXIS 2241
Procedural entryThis page is a short order in Russell v. Bohn Mfg. Co.. Read the opinion of the Court — 83 F. 976
Court of Appeals for the Seventh Circuit·Decided March 5, 1898·No. No. 408·Published

Opinion

PER CURIAM.

The petition for rehearing upon the merits is overruled, but the prayer that the new trial ordered shall be general and not restricted, ns stated in the opinion handed down, to “the question whether the plaintiff in error is entitled to recover for an excess of payments over the aggregate prices of the lumber received of the defendant,” is granted. The mandate will show simply that ihe judgment below is reversed, at the costs of the defendant in error, with direction to grant a new trial. See 28 C. C. A. 243, 83 Fed. 976.

Free access — add to your briefcase to read the full text and ask questions with AI

Russell v. Bohn Mfg. Co., 85 F. 991, 29 C.C.A. 681, 1898 U.S. App. LEXIS 2241 (7th Cir. 1898).

85 F. 991 (Russell v. Bohn Mfg. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Russell v. Bohn Mfg. Co.
83 F. 976 (Seventh Circuit, 1898)