Russell, Inc. v. Oper

26 Fla. Supp. 135
CourtCircuit Court of the 11th Judicial Circuit of Florida, Miami-Dade County
DecidedJune 2, 1966
DocketNo. 65-C-6513
StatusPublished

This text of 26 Fla. Supp. 135 (Russell, Inc. v. Oper) is published on Counsel Stack Legal Research, covering Circuit Court of the 11th Judicial Circuit of Florida, Miami-Dade County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Russell, Inc. v. Oper, 26 Fla. Supp. 135 (Fla. Super. Ct. 1966).

Opinion

JAMES LAWRENCE KING, Circuit Judge.

Findings and supplemental decree of foreclosure: The court has carefully considered all the pleadings filed in this cause and all the testimony and proofs submitted at the trial.

The court finds that on June 14, 1965, the plaintiff filed a complaint to foreclose its mechanic’s lien against the defendants.

The defendant owners moved to dismiss on the grounds that the complaint failed to state a cause of action against either of the defendants and that the complaint failed to state a claim for relief in behalf of the plaintiff against either of the defendants. No other grounds for dismissal were alleged. However, at the hearing on the defendants’ motion, counsel for the defendants orally argued as grounds for the dismissal of the plaintiff’s complaint that the plaintiff lienor did not serve on the defendant owners of the property a statement under oath in accordance with the provisions of §84.061 (3) (d) 1, Florida Statutes, prior to the filing of the complaint.

§84.061 (Liens of persons not in privity; proper payments) provides that when the final payment under a direct contract becomes due the contractor shall give to the owner an affidavit stating, if that be the fact, that all lienors have been paid in full or, if the fact be otherwise, showing the name of each lienor who has not been paid in full and the amount due or to become due each for labor, services or materials furnished. The section further provides that the contractor shall have no lien or right of action against the owner for labor, services or materials furnished under the direct contract while in default by reason of not giving the owner such affidavit, and that the contractor shall execute said affidavit and deliver it to the owner at least five days before instituting suit as a prerequisite to the institution of any suit to enforce his lien under this chapter.

At the hearing counsel for the plaintiff urged that §84.051 of the statutes contains an exception for a person who contracts directly with the owner, and provides “. . . No lienor under this section shall be required to serve a notice to owner as provided in §84.061 (2), Florida Statutes”, and hence that the provisions of §84.061 were not applicable.

[137]*137According to the allegations of the plaintiff’s complaint — upon motion to dismiss for failure to state a cause of action all allegations well pleaded are admitted — the plaintiff was in direct privity with the defendant owners. Therefore, assuming the allegations of the complaint to be true, as the court must for the purpose of the motion, the motion to dismiss admits the furnishing of the materials and the performance of the labor services to the defendant owners. Accordingly, the motion to dismiss was denied.

In this case, it was even unnecessary that any notice of the claim .of lien be filed, although such claim of lien was filed for record on June 3, 1965, and the defendants served with such notice. See Maule Industries, Inc. v. Trugman, Fla., 59 So.2d 27, which is controlling on these points.

With full knowledge of this, the defendants answered the plaintiff’s complaint setting forth a general denial, but admitting— (a) that the defendant Arnold A. Oper did contract with the plaintiff corporation whereby the plaintiff agreed to provide complete landscaping and caretaking services for defendants’ residence; (b) that the plaintiff provided materials, labor and services some time during the period January 4 to March 12, 1965; and (c) that the defendants refused to pay the amount claimed by the plaintiff.

The defendants’ answer contained a counterclaim (upon the same contract) alleging that the plaintiff agreed to provide the mentioned services in exchange for the furnishing by the defendant Arnold A. Oper to plaintiff, of noncompensatory medical services for the employees of plaintiff corporation and their families.

Generally it may be said that where the owner contracts directly with one whose only obligation is to alone render personal services incident to the improvement, or with a materialman whose only obligation is to furnish materials to the project, and if the contract is one which under customary business practices excludes the notion that the services of a subcontractor are likely in order to consummate it, (such as Russell, Inc., in the case at bar), then the rule stated in Maulé Industries, supra, and followed in Orange Plumbing & Heating Co. v. Wolfe, 89 So.2d 671 (Fla. 1956), is applicable and does not do violence to the legislative intent expressed by §84.061(3) because the defendant owners could not be and were not adversely affected. The sworn statement is not necessary to the acquisition of the lien but operates to protect the owner against the possibility of paying more than once for the same items of labor or materials.

In a given case (such as the case at bar), the defendant property owners may waive the right to the statutory sworn statement and may even become estopped to require the statement. The rule of [138]*138reason applies here, as elsewhere in the law. So it is as here, that where the contract by its very nature is one that cannot entail the services of a subcontractor or the furnishing of labor or materials by another, the sworn statement could not serve any useful purpose and would have not been required.

The defendants allowed the cause to proceed for more than ten months because of the allegations of their counterclaim; and throughout the dealings hereunder, the defendant owner Arnold A. Oper was directly in privity with the plaintiff. The court further finds that since the statute contains an exception for a person who contracts directly with the owner, and that the established facts and evidence at the trial upon the merits meet the test by which to create the exception, no sworn statement was necessary in this suit.

The court is of the opinion and finds that the equities of this suit are with the plaintiff; that the court has jurisdiction of the subject matter hereof and of the parties hereto and that it has been proved by a preponderance of evidence — (a) that the defendants, Arnold A. Oper and Eileen A. Oper, his wife, are indebted to the plaintiff, Russell, Inc., a Florida corporation, in the sum of $3,011.17 for materials, services and labor furnished by the plaintiff corporation (for the purchase and planting of certain shrubberies, plants, trees, including but not limited to landscaping, servicing, trimming, fertilizing, spraying, leveling and grade filling placed and planted on the property of the defendants) which property is described as follows — lot 1, block 5, Highland Woods #2, according to the plat thereof recorded in plat book 68, page 33 of the public records of Dade County, Florida, a/k/a 2045 N. E. 179th Terrace, Miami, Dade County, Florida; (b) that no part of such indebtedness of $3,011.17 has been paid; (c) that to secure the payment of such indebtedness the plaintiff corporation has a lien on the mentioned property hereinabove described; (d) the defendants contend, but have failed to prove, and I find no evidentiary basis, nor was any competent evidence whatever submitted in support of the averment that there was a legal, binding and enforceable agreement or contract by which the plaintiff corporation expressly or impliedly authorized any employee or any other person, to provide complete landscaping at the mentioned premises, in exchange for the furnishing without charge, by the defendant, Dr. Arnold A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maule Industries v. Trugman
59 So. 2d 27 (Supreme Court of Florida, 1952)
Orange Plumbing & Heating Company v. Wolfe
89 So. 2d 671 (Supreme Court of Florida, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
26 Fla. Supp. 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/russell-inc-v-oper-flacirct11mia-1966.