Russ Mitchell, Inc. v. Houston Pipe Line Co.

219 S.W.2d 109, 1949 Tex. App. LEXIS 1637
CourtCourt of Appeals of Texas
DecidedFebruary 24, 1949
DocketNo. 12038
StatusPublished
Cited by4 cases

This text of 219 S.W.2d 109 (Russ Mitchell, Inc. v. Houston Pipe Line Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Russ Mitchell, Inc. v. Houston Pipe Line Co., 219 S.W.2d 109, 1949 Tex. App. LEXIS 1637 (Tex. Ct. App. 1949).

Opinion

CODY, Justice.

The appellee, a corporation engaged in the transportation and sale of natural gas in South Texas, brought this action for damages against appellants, alleging the failure and refusal of appellants to complete the laying and salvaging of approximately 8,851 feet of 18 inch pipe line and 22,420 feet of 16 inch pipe line according to the terms of a written contract dated August 2, 1945. Appellants answered ap-pellee’s petition by the allegation that ap-pellee had itself cancelled the contract sued on, in conformity with an option so to do which was vested in appellee by the terms of the contract sued on, and that consequently appellee was not entitled to enforce any obligations which had ceased to exist. Then, by cross-action, appellants sued appellee for damages, alleging in that connection that appellee had caused appellant Russ Mitchell, Inc., reasonably to believe that appellee had cancelled the contract sued on by appellee. Appellants further alleged in their cross-action that ap-pellee had failed to perform its obligations, under the contract sued on, but that appellant Russ Mitchell, Inc., in addition to per-, forming its obligations under the contract-sued on up until the time that appellee cancelled same, that it performed labor for which'appellee was liable to it, and which appellee had never paid, and for which said appellant sought to recover by said cross-action.

The contract sued on by appellee was in-the form of a letter written by appellant Russ Mitchell, Inc., to appellee, dated August 2, 1945, and which letter was marked “accepted” by appellee in conformity with the provisions therein that such acceptance should be signified. Among the provisions . [111]*111of the contract was the requirement that appellant Russ Mitchell, Inc., should furnish appellee a performance bond. And appellant the United States Guarantee Company was surety on said performance bond, and was sued by appellee as such surety. Since said last mentioned appellant was obligated in connection with this suit only in virtue of the performance bond, hereinafter, when the term “appellant” (that is, when the plural is not used) is used, it is to be understood that Russ Mitchell, Inc., is referred to.

The terms of said written contract provided :

A. That the jobs covered thereby were located at thirty-two separate locations, as set out on attached maps, and further specified that the work to be performed by appellant was fully described in the attached specifications.

B. That appellant should furnish all labor; construction; supplies, except as otherwise expressly provided; equipment; machinery; etc.

C. That, as between the parties, appellant should be liable to appellee as an independent contractor.

“D. Should either party hereto be prevented from performance hereunder by what is usually termed ‘force majeure’ or be prevented in whole or in part from completing his or its obligations hereunder due to the inability to obtain the necessary materials, supplies or permits due to existing or future rules, regulations, orders, laws or proclamations of governmental authorities (both Federal and State, including both civil and military), the terms of this contract for any of the above reasons shall be suspended during the continuance of such inability so caused.

“E. Should any such inability occur so that the performance of this contract is suspended or shall cease, Houston Pipe Line Company shall have the option at that time of paying for so much of the work as has been done and canceling the contract as to the remaining work, or of holding the performance of such contract in abeyance until the inability so caused is remedied. It is understood that some of the pipe and material needed on this job which is to be supplied by Company has been ordered and should arrive before it is needed for the completion of this job, but in the event there is some delay in the delivery of such pipe and material to Company, such delay shall not affect the terms of this contract.

“F. The Houston Pipe Line Company agrees to pay Russ Mitchell, Inc., Contractor, $1.59 per lineal foot for laying, salvaging, hauling, and stringing approximately 8,851 feet of 18" pipe line and 22,-420 feet of 16" pipe line in accordance with the specifications referred to above and made a part hereof.

“G. On the first of each month an appropriate determination shall be made of the work completed by Russ Mitchell, Inc., Contractor, and the Houston Pipe Line Company shall pay to Russ Mitchell, Inc., Contractor, an amount equal to 85% of the value of work completed, the value to be determined by computing the work completed at the price referred to above. The remaining 15% shall be due and payable upon satisfactory completion of this contract.”

At the conclusion of all the evidence, appellants moved for an instructed verdict, which was refused. Certain special issues requested by appellants were refused, and the court submitted the case to the jury on 11 special issues which he conceived were made by the pleadings and the evidence. As answered by the jury, said issues were:

1. That appellant intended to abandon all work under the contract when it moved its equipment off the job about November 15, 1945.

2. That within a reasonable time after appellant so stopped its work, appellee notified appellant that appellee expected the work to be completed in accordance with the contract of August 2, 1945.

3. That appellee had paid appellant all money owing appellant for all work, including regular and extra work, except 99 feet of additional casing in connection with the job, which is identified in the contract as “Job 12”.

4. That appellant did not perform any work for which it was not paid except with [112]*112respect to “Job 12”, as specified in the special issue next above.

6. That the reasonable cost of said extra work on “Job 12” amounted to $150.

7. It was not the intention of appellee to terminate its contract with appellant when the work was stopped by appellant.

9. That appellee did not cause appellant to believe appellee had determined to terminate the contract.

Based on the foregoing- findings, and the finding that $3000 was the reasonable attorneys’ fees for appellee, and upon the court’s own findings, the court rendered judgment:

That appellee recover from appellants jointly and severally the sum of $10,487.-38 as damages, less $150 specified by the findings, or a total of $10,337.38, and that appellee recover its attorneys’ fees in the sum of $3000.

Appellants predicate their appeal upon thirteen points.

Appellants’ points I, II, III, VIII, IX, present that the court erred in overruling appellants’ motion for instructed verdict, and in overruling appellants’ motion for judgment notwithstanding the verdict, and in overruling appellants’ motion for instructed verdict with respect to appellee’s claim for damages for all the reasons set out in said motions. That the judgment is contrary to law and based on a verdict not sustained by the evidence. That the verdict is not sustained by the evidence in that the uncontradicted evidence shows that appellant stopped work because ap-pellee failed to provide the proper supplies, namely, pipe with which to continue performance of thé contract.

Appellants’ point IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ahlschlager v. Remington Arms Co.
750 S.W.2d 832 (Court of Appeals of Texas, 1988)
Spring Branch Bank v. Mengden
628 S.W.2d 130 (Court of Appeals of Texas, 1981)
Buzzard v. Mapco, Inc.
499 S.W.2d 352 (Court of Appeals of Texas, 1973)
H. B. Zachry Co. v. Travelers Indemnity Co.
262 F. Supp. 237 (N.D. Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
219 S.W.2d 109, 1949 Tex. App. LEXIS 1637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/russ-mitchell-inc-v-houston-pipe-line-co-texapp-1949.