UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
Rumi LLC, Plaintiff,
v. Case No. 23-cv-01741 (CRC) Burtak Irtanki, et al., Defendants.
OPINION AND ORDER
In 2022, Plaintiff Rumi LLC (“Rumi”) wired nearly half a million dollars to Defendant
Burak Irtanki for his company, Optimal Holdings, Inc. (“Optimal”), to construct a new restaurant
in Washington, District of Columbia. Irtanki, however, repeatedly delayed construction,
ultimately abandoning the project and ceasing communication with Rumi. Rumi then filed this
lawsuit against Irtanki and his mother-turned-business partner, Mihirban Tuncay, bringing fraud
and negligent misrepresentation claims, among others. Even though Irtanki and Tuncay have
been served, neither has responded to the complaint, and the Clerk has entered a default against
Irtanki.
In a prior opinion, the Court denied Rumi’s motion for default judgment without
prejudice, noting that Rumi had failed to brief several critical issues. Rumi’s second motion for
default judgment fares no better than the first. Because Rumi has not obtained a default against
Tuncay nor moved for a default judgment against her, while expressing its intention to do so, it is
premature for the Court to consider the motion against Irtanki. To avoid the possibility of
inconsistent judgments, the Court will again deny the motion without prejudice and permit Rumi
0 one last chance to file motions for default judgment against both defendants after obtaining a
default against Tuncay.
I. Background
The Court presumes familiarity with its prior opinion describing the procedural and legal
background of this case, so it provides only a summary of the relevant details here. See Op. &
Order, ECF No. 16 at 1–5.
According to the complaint, in 2021, Rumi began a project to open a restaurant in
northwest D.C. Compl. ¶ 10. After securing a lease, Rumi met with Irtanki to discuss
construction of the restaurant. Id. ¶ 14. Irtanki “held himself out . . . as a general contractor” and
told Rumi’s representatives that he had completed several similar projects in the area. Id. ¶¶ 15,
44–45. Accordingly, Rumi signed a contract with Optimal, a company controlled by Defendants
and purportedly headquartered in D.C. Id. ¶¶ 21, 26–27. Unbeknownst to Rumi, Optimal did
not register in D.C. or possess a General Contractor license until several weeks after the contract
was signed. Id. ¶¶ 38–41.
After Irtanki sent Rumi an allegedly fake proof of bond, Irtanki and Tuncay instructed
one of Rumi’s officers to convey a check to them in the amount of $186,000. Id. ¶¶ 22, 36.
Rumi did so in January 2022. Id. Two months later, Rumi wired a second payment of $290,000
to Irtanki. Id. ¶ 23. And over the next few months, Rumi tendered $22,000 in additional
payments, for a total of $498,000. Id. ¶ 24. Irtanki and Tuncay also met with one of Rumi’s
officers in in October 2022 and showed him construction materials that had purportedly been
purchased for the restaurant. Id. ¶¶ 80–82.
Despite accepting these large sums from Rumi and claiming to have bought construction
materials, Optimal has performed no work on the restaurant to date nor met any deadlines set
1 forth in the contract. Id. ¶¶ 72–73. And in October 2022, Irtanki stopped substantively
responding to Rumi’s requests for updates on the project altogether. Id. ¶ 74.
So, in June 2023, Rumi brought this lawsuit against Irtanki and Tuncay, alleging fraud,
negligent misrepresentation, civil conspiracy, negligence, and conversion. Id. ¶¶ 88–135, 150–
64. Rumi sought a declaratory judgment, replevin, and damages. Id. ¶¶ 136–49, 165–80.
Although both defendants were served, neither responded to the complaint. Rumi then sought
and received a default from the Clerk against Irtanki. Military Aff., ECF No. 10 at 1−2; Entry of
Default, ECF No. 11 at 1−2. Tuncay remains in the case, but no default has been registered or
entered against her.
In its prior opinion, the Court denied Rumi’s motion for default judgment against Irtanki
without prejudice, identifying several outstanding issues that prevented the Court from granting
the motion, including the effect of an arbitration clause in the contract between Rumi and
Optimal, the appropriate cause of action, and Rumi’s justification for the sizeable damages
requested. Op. & Order at 5–6. And, as particularly relevant here, the Court instructed Rumi to
clarify its intentions as to Tuncay, Irtanki’s joint tortfeasor and the other defendant in this case.
Id. at 6–7. The Court explained that “courts typically refuse to enter default judgment against
one defendant while a codefendant remains in the mix to avoid the possibility of inconsistent
rulings for joint tortfeasors.” Id.
Rumi has now filed a second motion for default judgment that attempts to address the
Court’s concerns. Second Mot. for Default J., ECF No. 18 at 9–22. Because Rumi indicates that
it plans to file a motion for default judgment against Tuncay but still has not yet done so, the
Court will again deny its motion without prejudice to avoid the risk of inconsistent judgments.
2 II. Legal Standards
Obtaining a default judgment is a two-step process. See Boland v. Cacper Constr. Corp.,
130 F. Supp. 3d 379, 382 (D.D.C. 2015). A plaintiff must first request that the Clerk of the Court
enter default against a party who has “failed to plead or otherwise defend.” Fed. R. Civ. P. 55(a).
The Court then decides whether default judgment is warranted. Fed. R. Civ. P. 55(b). Default
judgment is available when “the adversary process has been halted because of an essentially
unresponsive party.” Boland v. Elite Terrazzo Flooring, Inc., 763 F. Supp. 2d 64, 67 (D.D.C.
2011) (cleaned up). “Default establishes the defaulting party’s liability for the well-pleaded
allegations of the complaint.” Id. After establishing liability, the Court makes an independent
evaluation of the damages award, which it has “considerable latitude” to determine. Id. (citing
Jones v. Winnepesaukee Realty, 990 F.2d 1, 4 (1st Cir. 1993)). The Court may hold a hearing if
necessary or can rely on “detailed affidavits or documentary evidence” submitted by plaintiffs in
support of their claims. Boland v. Providence Constr. Corp., 304 F.R.D. 31, 36 (D.D.C. 2014)
(cleaned up).
III. Analysis
In its prior opinion, the Court observed that default judgments are generally not entered
against one defendant while a codefendant remains in the case to avoid the possibility of
inconsistent rulings for joint tortfeasors. Op. & Order at 6–7. Accordingly, the Court directed
Rumi to “clarify whether the Court should dismiss the case against Tuncay if it were to enter
default judgment against Irtanki.” Id. at 7. In its second motion for default judgment, Rumi
states that it “intended and still does intend to file a subsequent motion for default judgement
against Tuncay.” Second Mot. for Default J. at 10.
Free access — add to your briefcase to read the full text and ask questions with AI
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
Rumi LLC, Plaintiff,
v. Case No. 23-cv-01741 (CRC) Burtak Irtanki, et al., Defendants.
OPINION AND ORDER
In 2022, Plaintiff Rumi LLC (“Rumi”) wired nearly half a million dollars to Defendant
Burak Irtanki for his company, Optimal Holdings, Inc. (“Optimal”), to construct a new restaurant
in Washington, District of Columbia. Irtanki, however, repeatedly delayed construction,
ultimately abandoning the project and ceasing communication with Rumi. Rumi then filed this
lawsuit against Irtanki and his mother-turned-business partner, Mihirban Tuncay, bringing fraud
and negligent misrepresentation claims, among others. Even though Irtanki and Tuncay have
been served, neither has responded to the complaint, and the Clerk has entered a default against
Irtanki.
In a prior opinion, the Court denied Rumi’s motion for default judgment without
prejudice, noting that Rumi had failed to brief several critical issues. Rumi’s second motion for
default judgment fares no better than the first. Because Rumi has not obtained a default against
Tuncay nor moved for a default judgment against her, while expressing its intention to do so, it is
premature for the Court to consider the motion against Irtanki. To avoid the possibility of
inconsistent judgments, the Court will again deny the motion without prejudice and permit Rumi
0 one last chance to file motions for default judgment against both defendants after obtaining a
default against Tuncay.
I. Background
The Court presumes familiarity with its prior opinion describing the procedural and legal
background of this case, so it provides only a summary of the relevant details here. See Op. &
Order, ECF No. 16 at 1–5.
According to the complaint, in 2021, Rumi began a project to open a restaurant in
northwest D.C. Compl. ¶ 10. After securing a lease, Rumi met with Irtanki to discuss
construction of the restaurant. Id. ¶ 14. Irtanki “held himself out . . . as a general contractor” and
told Rumi’s representatives that he had completed several similar projects in the area. Id. ¶¶ 15,
44–45. Accordingly, Rumi signed a contract with Optimal, a company controlled by Defendants
and purportedly headquartered in D.C. Id. ¶¶ 21, 26–27. Unbeknownst to Rumi, Optimal did
not register in D.C. or possess a General Contractor license until several weeks after the contract
was signed. Id. ¶¶ 38–41.
After Irtanki sent Rumi an allegedly fake proof of bond, Irtanki and Tuncay instructed
one of Rumi’s officers to convey a check to them in the amount of $186,000. Id. ¶¶ 22, 36.
Rumi did so in January 2022. Id. Two months later, Rumi wired a second payment of $290,000
to Irtanki. Id. ¶ 23. And over the next few months, Rumi tendered $22,000 in additional
payments, for a total of $498,000. Id. ¶ 24. Irtanki and Tuncay also met with one of Rumi’s
officers in in October 2022 and showed him construction materials that had purportedly been
purchased for the restaurant. Id. ¶¶ 80–82.
Despite accepting these large sums from Rumi and claiming to have bought construction
materials, Optimal has performed no work on the restaurant to date nor met any deadlines set
1 forth in the contract. Id. ¶¶ 72–73. And in October 2022, Irtanki stopped substantively
responding to Rumi’s requests for updates on the project altogether. Id. ¶ 74.
So, in June 2023, Rumi brought this lawsuit against Irtanki and Tuncay, alleging fraud,
negligent misrepresentation, civil conspiracy, negligence, and conversion. Id. ¶¶ 88–135, 150–
64. Rumi sought a declaratory judgment, replevin, and damages. Id. ¶¶ 136–49, 165–80.
Although both defendants were served, neither responded to the complaint. Rumi then sought
and received a default from the Clerk against Irtanki. Military Aff., ECF No. 10 at 1−2; Entry of
Default, ECF No. 11 at 1−2. Tuncay remains in the case, but no default has been registered or
entered against her.
In its prior opinion, the Court denied Rumi’s motion for default judgment against Irtanki
without prejudice, identifying several outstanding issues that prevented the Court from granting
the motion, including the effect of an arbitration clause in the contract between Rumi and
Optimal, the appropriate cause of action, and Rumi’s justification for the sizeable damages
requested. Op. & Order at 5–6. And, as particularly relevant here, the Court instructed Rumi to
clarify its intentions as to Tuncay, Irtanki’s joint tortfeasor and the other defendant in this case.
Id. at 6–7. The Court explained that “courts typically refuse to enter default judgment against
one defendant while a codefendant remains in the mix to avoid the possibility of inconsistent
rulings for joint tortfeasors.” Id.
Rumi has now filed a second motion for default judgment that attempts to address the
Court’s concerns. Second Mot. for Default J., ECF No. 18 at 9–22. Because Rumi indicates that
it plans to file a motion for default judgment against Tuncay but still has not yet done so, the
Court will again deny its motion without prejudice to avoid the risk of inconsistent judgments.
2 II. Legal Standards
Obtaining a default judgment is a two-step process. See Boland v. Cacper Constr. Corp.,
130 F. Supp. 3d 379, 382 (D.D.C. 2015). A plaintiff must first request that the Clerk of the Court
enter default against a party who has “failed to plead or otherwise defend.” Fed. R. Civ. P. 55(a).
The Court then decides whether default judgment is warranted. Fed. R. Civ. P. 55(b). Default
judgment is available when “the adversary process has been halted because of an essentially
unresponsive party.” Boland v. Elite Terrazzo Flooring, Inc., 763 F. Supp. 2d 64, 67 (D.D.C.
2011) (cleaned up). “Default establishes the defaulting party’s liability for the well-pleaded
allegations of the complaint.” Id. After establishing liability, the Court makes an independent
evaluation of the damages award, which it has “considerable latitude” to determine. Id. (citing
Jones v. Winnepesaukee Realty, 990 F.2d 1, 4 (1st Cir. 1993)). The Court may hold a hearing if
necessary or can rely on “detailed affidavits or documentary evidence” submitted by plaintiffs in
support of their claims. Boland v. Providence Constr. Corp., 304 F.R.D. 31, 36 (D.D.C. 2014)
(cleaned up).
III. Analysis
In its prior opinion, the Court observed that default judgments are generally not entered
against one defendant while a codefendant remains in the case to avoid the possibility of
inconsistent rulings for joint tortfeasors. Op. & Order at 6–7. Accordingly, the Court directed
Rumi to “clarify whether the Court should dismiss the case against Tuncay if it were to enter
default judgment against Irtanki.” Id. at 7. In its second motion for default judgment, Rumi
states that it “intended and still does intend to file a subsequent motion for default judgement
against Tuncay.” Second Mot. for Default J. at 10. Nowhere does Rumi respond to the Court’s
concern about entering inconsistent rulings, however.
3 “If one of several defendants . . . make[s] default, . . . no final decree on the merits [can
be issued] until the case is disposed of with regard to the other defendants.” Frow v. De La Vega,
82 U.S. 552, 554 (1872); see 10A Wright & Miller’s Federal Practice & Procedure § 2690 (4th
ed. 2025) (“[W]hen one of several defendants who is alleged to be jointly liable defaults,
judgment should not be entered against that defendant until . . . all defendants have defaulted.”).
The D.C. Circuit has explained that the Frow principle guards against potential “inconsistent
adjudications as to joint liability.” Carter v. District of Columbia., 795 F.2d 116, 137 (D.C. Cir.
1986) (applying Frow when it “was necessary that judgment be entered against all of the
defendants in order to be effective” (citation omitted)).
Here, Rumi’s complaint broadly alleges that Irtanki and Tuncay were jointly liable on
four of the seven counts, including the fraud and negligent misrepresentation claims on which
Rumi now seeks a default judgment against Irtanki. Compl. ¶¶ 91–109, 112–126, 129–135, 152–
157. The factual allegations in the complaint identify Tuncay as jointly participating in at least
some of the allegedly fraudulent behavior. For instance, Rumi alleges that Tuncay and Irtanki
together instructed one of its officers to convey the first payment of $186,000 to them during a
January 2022 meeting attended by both. Id. ¶¶ 22, 36. Tuncay, along with Irtanki, is also said to
have attended a meeting that October during which they allegedly “showed [Rumi] numerous . . .
construction materials and represented [that] such materials were purchased for the Project.” Id.
¶¶ 80–82.
Rumi therefore cannot obtain a default judgment against Irtanki before a default has been
entered against Tuncay. Rule 55(a) requires a plaintiff to show by affidavit or otherwise that a
party has failed to plead in order for the Clerk to enter a default against them. Fed. R. Civ. P.
55(a). Rumi never applied to the Clerk for a default against Tuncay and as such, no default has
4 been entered against her, even though she has not answered the complaint. If the Court were to
grant Rumi’s motion for default judgment, therefore, it would risk separate and incongruous
judgments. For instance, if the Court were to enter judgment against Irtanki for fraud based on
soliciting the first payment at issue here, Tuncay would necessarily be liable, since both Tuncay
and Irtanki allegedly “instructed” Rumi to convey a check to them in the amount of $186,000
and then participated in “divert[ing]” this payment. Compl. ¶ 22, 120–22, 129.
Rumi responds that Tuncay’s “conduct towards Plaintiff was different from Irtanki as it
was also discrete.” Second Mot. for Default J. at 9. The Court recognizes the possibility that it
could find Irtanki, and not Tuncay, liable for some counts because only Irtanki is implicated in
the majority of the allegedly improper conduct. The D.C. Circuit has clarified that Frow applies
when “the theory of recovery requires that all defendants be found liable if any one of them is
liable—and when the relief sought can only be effective if judgment is granted against all.”
Whelan v. Abell, 953 F.2d 663, 674–75 (D.C. Cir. 1992). Nevertheless, while granting default
judgment here may not go so far as to “run afoul of ‘settled law,’” it still would be inappropriate
because granting judgment to Irtanki “could indirectly establish liability as to” Tuncay as well.
Zapata v. B. Coleman Flooring Installation, LLC, No. 18-cv-1134 (TJK), 2019 WL 13399854, at
*1 (D.D.C. Dec. 5, 2019).
On the other hand, the Court observes that unlike in many of the cases applying Frow,
Tuncay has not defended herself on the merits. The lack of a default entered against her is
therefore more of a technical problem, as it is unlikely at this stage that Tuncay will ever enter
the case and raise the specter of an inconsistent judgment. Nevertheless, Rumi represents in its
second motion for default judgment that it “had intended and still does intend to file a subsequent
motion for default judgement against Tuncay.” Second Mot. for Default J. at 10. Thus, it would
5 be more efficient for the Court to consider default judgment motions against the joint tortfeasors
together. See Fed. R. Civ. P. 54(b) (indicating that courts may delay final judgment if there is
“just reason for delay.”); see also In re Uranium Antitrust Litig., 473 F. Supp. 382, 389 (N.D. Ill.
1979) (recognizing the importance of avoiding “premature decision-making” in default judgment
cases). It would be a different story if Rumi were to dismiss Tuncay, as the Court noted in its
prior opinion. Op. & Order at 6–7.
Lastly, Rumi’s conflicting characterizations of Tuncay’s role in the fraudulent activity
confirms the Court’s conclusion. Rumi both identifies Irtanki as “the main actor” in the scheme,
Second Mot. for Default J. at 10, and then in the same breath argues that Tuncay “was the tail
wagging the dog.” Id. Given these inconsistencies, the Court views it as prudent to consider the
motions for default judgment against the defendants together.
The Court will, accordingly, deny the motion for default judgment without prejudice to
renewal after Rumi has obtained a default against Tuncay and filed motions for default judgment
against both defendants (or, alternatively, dismissed Tuncay as a defendant). 1
1 The Court will also deny without prejudice Rumi’s Application in the Alternative for a Stay Pending Arbitration, ECF No. 19, as the Court has not yet addressed the arbitration issue in this matter.
6 IV. Conclusion
For these reasons, it is hereby
ORDERED that [ECF No. 18] Rumi’s Second Motion for Default Judgment is DENIED
without prejudice; it is further
ORDERED that Rumi shall file a renewed motion for default judgment by August 13, 2025.
SO ORDERED.
________________________ CHRISTOPHER R. COOPER United States District Judge
Date: July 14, 2025