Rugo Const. Co. v. New England Foundation Co.

172 F.2d 964, 1950 A.M.C. 1206, 1949 U.S. App. LEXIS 3739
CourtCourt of Appeals for the First Circuit
DecidedFebruary 28, 1949
DocketNo. 4375
StatusPublished
Cited by7 cases

This text of 172 F.2d 964 (Rugo Const. Co. v. New England Foundation Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rugo Const. Co. v. New England Foundation Co., 172 F.2d 964, 1950 A.M.C. 1206, 1949 U.S. App. LEXIS 3739 (1st Cir. 1949).

Opinion

WOODBURY, Circuit Judge.

This is an appeal from a final decree entered in a libel in admiralty brought by [966]*966the owner of a derrick lighter against her demise charterer to recover damages resulting from the sinking of the lighter. There is no longer any dispute over the essential facts.

The libellant-appellee, New England Foundation Company Incorporated, purchased the lighter involved on April 10, 1941, for $6,300. It took out hull and collision insurance on the lighter; had it repaired (as a result of which it was put into excellent condition) and slightly altered, at a cost of $1,216.81, and then it used the lighter in the performance of a contract which it had with the Bureau of Yards and Docks of the Navy Department for the construction of two piers at the Navy Yard in South Boston. In this employment the iibellant received $2,409.50 as rental for the lighter. On August 28, 1941, the libellant, having no further immediate use for the lighter in its own work, chartered it on the bare boat basis at a rental of $800 per month to the respondent, Rugo Construction Company, Inc. The latter used it until October 15, and then returned it to -the libellant, but on November 5, Rugo chartered the lighter again on the same basis as before except that the hiring was by the' month without “split months.”

During the night of December 3, 1941, while the lighter was under the control and in the possession of the respondent under this second charter, it sank in the crash boat slip at the Naval Air Station at Squantum, Massachusetts, where the respondent, in the performance of a contract which it had with the Navy Department, had been using the lighter for pulling piles, work for which she was properly fitted and in which she was expected to engage. It has been found, and it is now conceded, that the lighter was seaworthy and in good condition before she sank, that she had been tied up for the night of December 3; in the crash boat slip on orders of a representative of the Navy Department, and that the crash boat slip was a clear berth.

On the day following the sinking the libellant’s president and a marine surveyor employed by the company carrying the insurance on the lighter went to Squantum to examine the wreck. They found the lighter lying on the bottom of the slip with her bow in shore and out of water but her stern submerged and her decks awash even at low tide. Although it was impossible as the lighter lay to go aboard her or even for a diver to observe the extent of the damage to her hull, the marine surveyor, with the knowledge and approval of the libellant’s president, made arrangements for and later supervised the work of raising her. This work was begun immediately, but it proceeded slowly, because with the outbreak of hostilities there were frequent demands by the Army and Navy for the equipment and personnel engaged therein. Then, from January 8 to February 23, 1942, the lighter was iced in at the slip and all work upon her had to be temporarily abandoned. However, early in March she was raised by means of slings placed under her bottom and supported by other lighters she was removed to a marine railway in Chelsea where she was hauled out of the water and where for the first time it became possible to make a complete examination of her hull.

This examination disclosed that in addition to the loss of most of her superstructure caused by floating ice and damage to her machinery caused by submersion, her bottom'planking, which was sound and free from rot, had eleven holes in it, apparently caused by her having settled on submerged piling in the bottom of the crash boat slip, and that she needed re-caullcing. Temporary repairs costing $331.11 were made to the lighter while it was on the marine railway so that she could be floated away from it, and when that was done she was tied up to a nearby wharf. While there she was examined by a marine surveyor other than the one who had arranged for and superintended her salvage who estimated that it would cost $10,000 to restore the lighter to the condition in which she had been before she sank. The libellant did not have her repaired, however, but some four months later sold her in “as is and where is” condition for $750.

On these facts the court below concluded that the “libellant was entitled to a decree against the respondent for its damages” and entered an interlocutory decree referring the libel to .a Commissioner to ascertain the amount of those damages. The Commis[967]*967sioner held hearings, at which only the libellant offered testimony, as a result of which he found that although it was impossible while the lighter lay on the bottom of the crash boat slip to tell what damage it had sustained “the raising of her was justified to find out her condition”; that $6,-345.90 had reasonably and properly been expended in raising the lighter, moving her to the marine railway and hauling her out for inspection; that $331.11 had reasonably and properly been spent in making temporary repairs to the lighter while she was hauled out “so she would float when launched from the railway”; that it would cost $10,000 to make permanent repairs to the lighter; and that the value of the lighter at the time she sank was “more than the cost of the repairs.” On the basis of these findings the Commissioner ruled that the lighter was a partial loss and under applicable principles of law the libellant was’entitled to recover as damages (1) the expense of raising the lighter, removing her to the railway, hauling her out, etc., in the amount of $6,345.90, (2) the expense of the temporary repairs made to the lighter while it was on the railway in the amount of $331.11, and (3) the estimated expense of permanent repairs in the amount of $10,000, making a total of $16,-677.01. But the Commissioner ruled that the $750 the libellant had received for the lighter should be deducted from this amount and in consequence found the libellant’s damages to be $15,927.01.

When this report came in the libellant moved in the court below for its confirmation, and the respondent for recommittal to the Commissioner. The court below after hearing on these motions, found “no substantial basis to justify” the conclusion that the lighter was worth at least $10,000 at the time she sank. But it sustained the other findings and conclusions of the Commissioner, and, determining that the value of the lighter when she sank was $7,500, it deducted $2,500 from the gross award made by the Commissioner and as so modified confirmed his report. Thereupon the court below entered a final decree for the libellant in the amount of $13,427.01, with interest thereon of $4,905.53 plus costs taxed at $931.62, making a total of $19,-264.16, upon which it awarded interest from the date of the decree, and the respondent thereupon took this appeal.

The respondent now concedes that it was reasonable to commence salvage operations on the lighter, and that $6,345.90 was a reasonable amount to expend for that work. Its contention is that the libellant is not entitled to recover that amount as an item of its damages, however, because in fact the costs of salvage were not borne by the libellant but were paid by its insurance carrier on its own responsibility and in pursuit of its interest to avoid payment of a total loss. And furthermore the respondent contends that since the court below found that the value of the lighter when it sank was less than the cost of repairing it, i. e., that it was a total loss, the libellant cannot recover the cost of the temporary repairs ($331.11) made to the lighter while it was on the marine railway. We do not agree with either contention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Short v. Marinas USA Ltd. Partnership
942 N.E.2d 197 (Massachusetts Appeals Court, 2011)
Gaspar v. United States
460 F. Supp. 656 (D. Massachusetts, 1978)
Com. of Puerto Rico v. SS Zoe Colocotroni
456 F. Supp. 1327 (D. Puerto Rico, 1978)
In Re the Complaint of Sincere Navigation Corp.
327 F. Supp. 1024 (E.D. Louisiana, 1971)
American Cement Corp. v. Healy Tibbitts Construction Co.
249 F. Supp. 891 (S.D. California, 1966)
Stevens v. United States Lines Co.
187 F.2d 670 (First Circuit, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
172 F.2d 964, 1950 A.M.C. 1206, 1949 U.S. App. LEXIS 3739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rugo-const-co-v-new-england-foundation-co-ca1-1949.