Ruginis v. Rhode Island Contractors' Registration Board, 98-4005 (2000)

CourtSuperior Court of Rhode Island
DecidedJanuary 28, 2000
DocketC.A. Nos. PC 98-4005, PC 98-4057
StatusPublished

This text of Ruginis v. Rhode Island Contractors' Registration Board, 98-4005 (2000) (Ruginis v. Rhode Island Contractors' Registration Board, 98-4005 (2000)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruginis v. Rhode Island Contractors' Registration Board, 98-4005 (2000), (R.I. Ct. App. 2000).

Opinion

DECISION
These consolidated administrative appeals were taken by a homeowner, Robert Ruginis, and a contractor, Carl Benevides, from a July 9, 1998 decision of the Rhode Island Contractors' Registration Board which adjudicated the homeowner's claims against the contractor for deficiencies in the construction of a new residential dwelling. In that decision, the Board required the contractor, Carl Benevides, to strip the exterior paint on a home that he had built and sold to the homeowners, Robert and Kathleen Ruginis. In all other respects, the Board denied the homeowner's claims.

The contractor appeals from that portion of the Board's decision which requires him to strip the exterior paint on the home. The homeowner appeals from that portion of the Board's decision which requires him to paint the exterior of the home after it is stripped by the contractor, arguing that the contractor should be required to strip and paint the home, and from the Board's denial of his other claimed deficiencies, namely cracked kitchen grout, a leaking basement window and a flaking basement floor.

This Court has jurisdiction of these appeals pursuant to G.L. 1956 § 42-35-15(g). For the reasons set forth in this decision, the Board's decision is reversed in part and affirmed in part.

Factual Background and Procedural History
On June 20, 1996, Robert A. Ruginis and his spouse, Kathleen E. Ruginis (the "Buyer"), entered into a Purchase and Sale Agreement (the "Agreement") with a builder/vendor, Carl F. Benevides (the "Contractor"), to purchase for $335,000 a new home located at 176 Poppasquash Road in Bristol, Rhode Island that had been constructed by the Contractor. (Ex. 1.) The Agreement contained an Addendum which provided for additional obligations of the Contractor and the right of the Buyer to an additional inspection after completion of any of the Contractors' obligations that were not finished as of the date of the original inspection. The Addendum also stated that the Contractor would provide the Buyer with a one (1) year builder's warranty upon closing. (Ex. 1.) After an inspection on July 10, 1996, the Contractor agreed, by letter to the Buyer, to repair numerous additional items prior to the closing. (Ex. 3.) The Contractor specifically agreed to remedy "bubbles in paint on exterior" (Item 1). Id. Pursuant to this agreement, the contractor made certain repairs to attempt to alleviate the problem with paint bubbles on the exterior of the home. The closing on the house took place on August 16, 1996. Funds were not held in escrow, and no additional written warranties were provided at the closing.

According to the Contractor, he built the house "possibly two years before it was sold." The certificate of occupancy, according to the Contractor, issued just prior to the closing. He said he painted the house "about 1 1/2 years before selling, as soon as [he] could."

On September 9, 1996, the Buyer sent a letter to the Contractor regarding additional problems with the house that emerged after the closing, including a basement window leak, grout cracking in the kitchen, and continued problems with paint bubbles on the exterior of the house. (Ex. 6.) The Buyer sent numerous additional letters to the Contractor between September 20, 1996 and August 5, 1997, stating that there were various problems with the house and requesting a time when the Contractor would be making the necessary repairs. (Exs. 7-13.) The letters indicated, and the Buyer testified, that the Contractor continued to agree to make certain repairs, including fixing the paint bubbles, the cracked grout in the kitchen, and the leaking window well in the basement. Id. On August 7, 1997, the Contractor reversed his position and advised the Buyer by letter that the house was sold "as is," that he was not responsible for any problems with the house unless they concerned the roof, plumbing, heating or electrical matters, and that he had only made repairs previously as a gesture of good faith. (Ex. 14.) The Contractor took the position that the Buyer had received such a good deal on the purchase price of the house that any further necessary repairs should be funded out of those savings by the Buyer.

On August 14, 1997, the Buyer filed a Statement of Claim against the Contractor with the Board for negligent and improper work and breach of contract.1 The Buyer complained about four separate deficiencies: 1) bubbles in the paint existing on four sides of the exterior of the home (Item 1); 2) a basement window well that fills with water and leaks into the basement (Item 2); 3) kitchen floor grout that is cracked and pieces of grout that are falling out (Item 3); and 4) a basement floor that is continually flaking (Item 4). Along with the claim, the Buyer filed: 1) the Agreement; 2) the letter dated July 14, 1996 from the Contractor to the Buyer listing the items to be repaired before the closing; 3) the closing settlement statement; 4) correspondence from the Buyer to the Contractor on diverse dates from September 9, 1996 through August 15, 1997; and 4) a videotape depicting the alleged problems with the property. The Board assigned an investigator to go to the property and investigate the Buyer's claims. The investigator filed a report with the Board dated November 18, 1997, finding blisters in the paint on four sides of the exterior of the home, referencing the videotape showing leaks in the basement area, finding cracks in the kitchen floor grout and pieces falling away and finding no loose aggregate in the basement floor. The investigator determined that Item 4 (basement floor) was not a deficiency, that Item 3 (kitchen floor grout) was a deficiency, and that Item 2 (window well leak) could be a deficiency. He took no concrete position regarding Item 1 (exterior paint).

A hearing officer conducted administrative hearings on the Buyer's Statement of Claim on February 18, 1998 and April 7, 1998. The hearing officer took testimony from the Buyer and the Contractor. The hearing officer also took judicial notice of the investigator's report and reviewed the Buyer's videotape of the alleged deficiencies in the house. On April 21, 1998, the hearing officer rendered Findings of Fact, Conclusions of Law, and a Proposed Order. The hearing officer found that there was no flaking in the basement floor and thus no deficiency as to Item 4. He found that the cracks in the kitchen floor grout were not deficiencies, because the contractor is only obligated, under the Board's regulations, to make a one-time repair of such a problem which he fulfilled. The hearing officer found further, with regard to Item 2, that there was a deficiency connected to the leaking window well. As to Item 4, the bubbling paint on the exterior, the hearing officer found the condition to exist but determined it was not a deficiency because the Contractor addressed the problem once and there is no obligation, under the Board's regulations, to repair a paint problem that occurs later than one year after construction of the house. The hearing officer thus issued a Proposed Order that denied the Buyer's claims regarding the exterior paint, the kitchen grout, and the basement floor and ordered only that the Contractor "make the necessary repairs to the basement window to relieve the entrance of water into the basement." The Proposed Order required those repairs to be made within twenty (20) days, with a thirty (30) day license suspension and other possible penalties to be imposed for noncompliance.

The Buyer filed timely exceptions to the Proposed Order. The Board held a non-evidentiary hearing to review the hearing officer's decision on June 11, 1998.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Scientific Corp. v. Durfee
621 A.2d 200 (Supreme Court of Rhode Island, 1993)
Milardo v. Coastal Resources Management Council
434 A.2d 266 (Supreme Court of Rhode Island, 1981)
Newport Shipyard, Inc. v. Rhode Island Commission for Human Rights
484 A.2d 893 (Supreme Court of Rhode Island, 1984)
Caswell v. George Sherman Sand & Gravel Co.
424 A.2d 646 (Supreme Court of Rhode Island, 1981)
Casavant v. Campopiano
327 A.2d 831 (Supreme Court of Rhode Island, 1974)
Costa v. Registrar of Motor Vehicles
543 A.2d 1307 (Supreme Court of Rhode Island, 1988)
Nichols v. R.R. Beaufort & Associates, Inc.
727 A.2d 174 (Supreme Court of Rhode Island, 1999)
Padula v. J. J. Deb-Cin Homes, Inc.
298 A.2d 529 (Supreme Court of Rhode Island, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Ruginis v. Rhode Island Contractors' Registration Board, 98-4005 (2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruginis-v-rhode-island-contractors-registration-board-98-4005-2000-risuperct-2000.