This text of Rufus Gaut, C. W. Crouch, Omni Capital Corporation, and Credwell Corporation v. Amarillo Economic Development Corporation and American Airlines, Inc. (Rufus Gaut, C. W. Crouch, Omni Capital Corporation, and Credwell Corporation v. Amarillo Economic Development Corporation and American Airlines, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Rufus Gaut, C. W. Crouch, Omni Capital Corporation,
and Credwell Corporation, Appellants
Amarillo Economic Development Corporation and American Airlines, Inc., Appellees
PER CURIAM
Appellants (1) sought a temporary injunction to restrain any expenditure of funds under a contract, the "Air Service Agreement," between Amarillo Economic Development Corporation (AEDC) and American Airlines. This appeal arises from the trial-court order denying appellants' request for temporary injunctive relief. See Tex. Civ. Prac. & Rem. Code Ann. § 51.14(4) (West Supp. 1995); Tex. R. App. P. 42(a)(1). Because the trial court has now rendered a final judgment in the underlying proceeding, we will dismiss the appeal as moot.
On November 1, 1995, the trial court rendered a final judgment in appellees' favor, declaring the "Air Service Agreement" valid and enforceable. If a trial court renders a final judgment during the appeal of an order denying temporary injunctive relief, the cause on appeal becomes moot. Isuani v. Manske-Sheffield Radiology Group, P.A., 802 S.W.2d 235, 236 (Tex. 1991); PCA Health Plans of Tex., Inc. v. Rapoport, 882 S.W.2d 522, 525 (Tex. App.--Austin 1994, no writ). When a cause becomes moot on appeal, the appellate court must set aside all orders relating to the temporary injunction and dismiss the cause. Isuani, 802 S.W.2d at 236; Texas Foundries, Inc. v. International Moulders & Foundry Workers' Union, 248 S.W.2d 460, 461 (Tex. 1952); Christie v. Argonaut Ins. Co., 530 S.W.2d 334, 336 (Tex. Civ. App.--Austin 1975, no writ). To decide the appeal under these circumstances would constitute an advisory opinion on an abstract question of law. Texas Parks & Wildlife Dep't v. Texas Ass'n of Bass Clubs, 622 S.W.2d 594, 596 (Tex. App.--Austin 1981, writ ref'd n.r.e.). On the other hand, to dismiss only the appeal would effectively affirm the trial-court judgment without consideration of any assignments of error. Texas Foundries, Inc., 248 S.W.2d at 461.
Accordingly, we set aside the order denying the request for temporary injunctive relief and dismiss the portion of the cause pertaining to the request for temporary injunctive relief. Id. We express no opinion as to the final judgment that declared the contract valid as it is not before this Court for review in this appeal. See Davis v. Huey, 571 S.W.2d 859, 861-62 (Tex. 1978); Public Util. Comm'n v. Coalition of Cities for Affordable Util. Rates, 776 S.W.2d 224, 226 (Tex. App.--Austin 1989, no writ) (in interlocutory appeal, review is confined to validity of order that denies injunctive relief).
Before Chief Justice Carroll, Justices Jones and B. A. Smith
Order Set Aside and Cause Dismissed
Filed: December 6, 1995
Do Not Publish
1. 1 Appellant Rufus Gaut was the plaintiff in the trial court. Appellants C. W. Crouch, Omni Capital Corporation, and Credwell Corporation were intervenors.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Rufus Gaut, C. W. Crouch, Omni Capital Corporation, and Credwell Corporation v. Amarillo Economic Development Corporation and American Airlines, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rufus-gaut-c-w-crouch-omni-capital-corporation-and-credwell-texapp-1995.