Ruckstuhl & Fick, Inc. v. Parish of Jefferson

207 So. 2d 170, 1968 La. App. LEXIS 5275
CourtLouisiana Court of Appeal
DecidedFebruary 5, 1968
DocketNo. 2892
StatusPublished
Cited by2 cases

This text of 207 So. 2d 170 (Ruckstuhl & Fick, Inc. v. Parish of Jefferson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruckstuhl & Fick, Inc. v. Parish of Jefferson, 207 So. 2d 170, 1968 La. App. LEXIS 5275 (La. Ct. App. 1968).

Opinion

JOHNSON, Judge.

These cases were consolidated in the lower court for trial and in this court for argument. There was judgment for plaintiff in each case. The cases are now before this court on a suspensive appeal by defendant, Parish of Jefferson.

On March 30, 1962, Ruckstuhl & Fick, Inc., (hereinafter referred to as Contractor) entered into a written contract with the Parish of Jefferson, Governing Authority of the East Jefferson Waterworks District No. 1, (hereinafter referred to as Parish) to make repairs to five settling basins located East of the Mississippi River in Jefferson Parish for the sum of $81,-511.00. The contract provided that the Contractor would perform all work and services in accordance with the contract documents prepared by T. Edward Ernst, Consulting Engineer, employed by the Parish. On April 18, 1962, the Contractor made a subcontract with Frank C. Voss Co., Inc., (hereinafter called Subcontractor) to perform certain painting and sandblasting of the settling basins for the price of $15,275.00, which work it contends was performed in a workmanlike manner under the direct supervision of a Mr. Flotron, representing the Parish engineer.

On August 4, 1965, the Contractor instituted suit against the Parish, the Subcontractor and other parties connected with the project by written petition for a declaratory judgment to recover the sum of $29,285.39 for work completed under the contract and for “change orders and extras.” The next day the Subcontractor filed suit against the Contractor and the Parish in solido to recover $60,567.21 including $15,275.00, for the painting and sandblasting under its subcontract, for which amount it had previously filed a materialman’s lien for labor and material used on the job.

After issue was joined, the two suits were consolidated for the purpose of trial. After a three-day trial, judgment was rendered on April 25, 1967, in each suit: (1) In the suit by the Contractor the judgment was in favor of the Contractor and against the Parish for $23,793.29, with interest and costs; the reconventional demand by the Parish against the Contractor and the [172]*172third-party demand against the Contractor’s bonding insurance company for de-murrage were dismissed. (2) In the suit by the Subcontractor against the Contractor and the Parish there was judgment in favor of the Subcontractor for $15,567.21, with interest and costs; a third-party demand in this suit by the Parish against the Contractor was dismissed.

On May 5, 1967, the Parish filed two motions, one for a new trial and one for a suspensive appeal. On May 8 the trial judge granted a suspensive appeal from the two judgments signed April 25, 1967, the appeal to be returnable to the Fourth Circuit Court of Appeal on June 30, 1967. On the same day, May 8, the trial court signed one order for a rule to issue calling upon the plaintiffs in the two cases to show cause on May 15, 1967, why a new trial should not be granted limited to the correction of the calculation of the amounts in the judgments. The reason for this was that the original judgments of April 25 required the Parish to pay the total of the two judgments of nearly $40,000.00. The rule was heard on May 15, 1967, and as a result on May 23, 1967, the trial court signed one judgment in the consolidated cases correcting or more particularly explaining that the total obligation of the Parish was $23,793.29, with interest and costs, of which amount $15,567.21, with interest, is to be paid first to the Subcontractor and the remainder of the $23,793.29, with interest, is to be paid to the Contractor.

As noted above, a suspensive appeal was granted on May 8, before the new trial was heard on May 15 and before the correcting consolidated judgment was rendered on May 23, 1967. There was no new motion for an appeal and no other order of appeal entered. No point was made of this by any counsel and properly so for the reason that the correcting judgment of May 23, 1967, had the effect of reinstating the original judgments of April 25, 1967, as corrected. LSA-C.C.P. art. 1951; Sanders v. Pacific Indemnity Company, 186 So.2d 887 (cert. denied).

The Contractor also appealed suspensively only insofar as the judgment is against it and in favor of the Subcontractor.

The Parish had constructed this plant some 12 years before this general contract was entered into between the Parish and the Contractor for major repairs. The plant for purification of water from the Mississippi River consisted of five settling basins. Three of these basins are called precipitators. The other two are called acceptors. They all serve the same functional purpose, though of somewhat different structural design. During the life of these facilities the Parish performed from time to time maintenance consisting of some painting and routine repairs. The specifications in this litigation called for removal of certain structural steel and installation of new steel in the three precipi-tators. The old steel was not removed and no new steel was installed in the acceptors. Removal and installation of the steel, welding and other phases of the work under this contract on the precipitators were let out to other subcontractors. They are not now parties to these suits.

The Subcontractor herein was given the subcontract to do sandblasting and painting in all five basins. This work on acceptor No. 1 was done first. The specifications called for preparation of the old steel by a type of sandblasting referred to as No. 2 sandblasting. The paint required was a sophisticated system called epoxy. Sandblasting was to clean the surface to be painted of rust, corrosion, etc. The Subcontractor’s work was done under the supervision of Mr. Flotron, an engineer representing T. Edward Ernst, for the Parish. Mr. Voss testified that Mr. Flotron devoted much time and close inspection and supervision of this job as the work progressed. When the sandblasting preparation was completed on acceptor No. 1 he approved it and ordered the paint applied. When the painting was finished Mr. Flo-[173]*173tron approved and accepted the work as being in compliance with the specifications. The Parish then paid the Contractor for the sandblasting and painting job on acce-lator No. 1, but later when defects developed a back charge for the amount was made against the contractor.

Mr. Voss testified that within about a month or so rust spots and pin holes did appear, which would require pointing-up. This he did under the supervision of Mr. Flotron. The Parish put the basin into use until October of that year when accelator No. 1 was drained and it was discovered that there was considerable rust and weld splatter, particularly in areas at the old steel welded joints. Mr. Voss contends that he could have corrected that even at that time, but the Parish would not permit him to do it. The surface of the steel in accelator No. 1 was not in good condition when the work started, but it must be remembered that this was the first major conditioning that had been attempted since its construction about 1950.

The Subcontractor complied with the specifications in the sandblasting of accelator No. 1 to prepare the surface to receive the paint. Mr. Flotron, a qualified engineer for the Parish, was continuously on the job and the application of the paint was done under his supervision. Apparently, sandblasting No. 2 did not properly prepare the surface completely. For the other basins, the specifications were changed to require sandblasting No. 1. Therefore, the Parish cannot now complain if the end result was not satisfactory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruckstuhl & Fick, Inc. v. Parish of Jefferson
209 So. 2d 40 (Supreme Court of Louisiana, 1968)
Frank C. Voss Co. v. Ruckstuhl & Fick, Inc.
207 So. 2d 175 (Louisiana Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
207 So. 2d 170, 1968 La. App. LEXIS 5275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruckstuhl-fick-inc-v-parish-of-jefferson-lactapp-1968.