Ruckman & Hansen, Inc. v. State Highway Commission

546 S.W.2d 500, 1976 Mo. App. LEXIS 2343
CourtMissouri Court of Appeals
DecidedDecember 27, 1976
DocketNo. KCD 27875
StatusPublished
Cited by7 cases

This text of 546 S.W.2d 500 (Ruckman & Hansen, Inc. v. State Highway Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruckman & Hansen, Inc. v. State Highway Commission, 546 S.W.2d 500, 1976 Mo. App. LEXIS 2343 (Mo. Ct. App. 1976).

Opinion

TURNAGE, Presiding Judge.

Ruckman and Hansen, Inc., brought suit against the State Highway Commission for breach of contract. Trial to the court without a jury resulted in a judgment in favor of Ruckman for $904,263.07, plus interest of $434,046.27, or a total of $1,338,309.34.

On this appeal the Commission raises a number of objections which will be treated in sequence. The judgment is modified and as modified, affirmed.

Ruckman was awarded a contract by the Commission for the construction of the concrete deck and incidental hand rail and conduit system for lighting and signs on the Chain of Rocks Bridge over the Mississippi River which carries Interstate 270. The bridge was a dual structure with each structure being 5,411 feet in length. The bridge deck, or driving surface, was supported by piers, girders and beams which were constructed by other contractors. The driving surface was shown on the plans to gradually widen for the east 650 feet in order to accommodate acceleration and deceleration lanes for an interchange at that location. From a point 650 feet east of the west end of the bridge, the deck was to be a constant 30 feet in width.

The plans upon which Ruckman based its bid and which became a part of the contract between Ruckman and the Commission showed the bottom of the deck to be arched or haunched at certain points above the tops of the beams and girders which supported the deck. A haunch is created by constructing the forming for the bottom of the deck in such a manner that the bottom of the deck is elevated above the tops of the beams or girders. A haunch can be fixed or variable in nature. A fixed haunch is one which is of a single dimension along the entire length of the beam or girder and a variable is one which varies along the length of the beam or girder.

The plans also called for reinforcing steel bars to be placed in the concrete of the deck, curbs and parapet walls. There was a median barrier separating the east and westbound lanes which also contained steel bars. Some of the bars to be used in the curbs, walls and median were to be bent into a rectangular shape. The plans specified the dimensions of these bars. In the case of straight bars, the specifications allowed a variation of one inch plus or minus from that specified. In the case of bent bars, a variation of one-half inch more or less was allowed from that stated in the specifications.

Ruckman produced substantial evidence to show that the girders and beams upon which the deck was to be constructed were not constructed as shown by the plans upon which it had based its bid. Further, the Commission required Ruckman to change from a fixed to a variable haunch in constructing the deck. Mr. Ruckman, president of Ruckman, testified his company’s bid was based on the plans which called for a fixed haunch throughout the length of the bridge except for the east 650 feet. Ruckman further testified the change from the fixed to a variable haunch caused a greater amount of labor and material used in making forms. The difference arose from the fact Ruckman had bid the job [502]*502based on reusing the forms once they had been constructed to the dimensions of the fixed haunch. When the variable haunch was required, then it became necessary for the forms to be torn up and new forms constructed about every 20 feet of the length which had been shown on the plans to be a fixed haunch.

The contract set out a procedure known as a force account by which Ruckman was to be compensated for extra work. Ruck-man testified the actual increase in his cost because of the change from a fixed to a variable haunch was $690,455.81. Calculated under the force account method, he testified this extra cost amounted to $601,-686.36.

Ruckman further testified the steel bars were ordered from his supplier based on the variations allowed by the specifications in the contract. He further testified the bars as delivered met the specifications with the allowable variations. However, it soon became apparent when Ruckman began work that only bars which fit the exact dimensions specified with no variation could be used. This meant practically all bars had to be cut or rebent in order to make all of them meet the exact specifications with no variation. The Commission also produced evidence to show that inspectors on the job rigorously enforced all of the clearance measurements called for in the plans. Ruckman’s evidence showed these clearance requirements could not be met by using the steel bars without allowable variations. Only bars meeting the exact measurement would allow for the specified clearance distances.

Ruckman stated his actual extra cost involved in cutting and reshaping the steel bars to make all of them conform to the exact dimensions with no variation was $264,281.30. This amount calculated under the force account method was $243,261.07. The court arrived at the amount of the judgment by taking the total of $844,947.43 as the total of the concrete and steel extra expense. From this the court deducted $5,846.00 paid by the Commission for extra expense, $3,181.68 which Ruckman had claimed for cleaning steel rods, $61.72 which Ruckman had claimed for storm damage, and $594.96 which Ruckman had claimed for flood clean up. After deducting these amounts, the total awarded to Ruckman was $835,263.07. To this the court added $69,000.00 which the Commission had charged against Ruckman for delay in completion of the project. The contract provided a forfeiture by Ruckman of $250.00 for each day completion was delayed beyond the specified date. Adding the $69,000.00 made the total of $904,263.07 which the court awarded to Ruckman. Interest for eight years was added to this amount to make the total judgment of $1,338,309.34.

The Commission lists in its brief eleven points. Of these, three relate to a complaint concerning the admission of a certain exhibit and evidence over its objection and a failure to admit testimony. In a court tried case, “ ‘the appellate court considers such of the evidence as it deems admissible, and excludes from consideration evidence improperly admitted.’ ” Butcher v. McClintock, 373 S.W.2d 917, 922 (Mo.1963); Hunt v. Easley, 495 S.W.2d 703, 707[1] (Mo.App.1973). The challenged evidence related to a letter from the Commission’s engineering firm prior to bids being advertised, and to the admission of a copy of Ruckman’s original bid sheet. The excluded evidence related to testimony showing Ruckman’s employees were not properly supervised.

Without deciding whether or not the evidence of which complaint is made was admissible or not, this court has concluded the judgment is supported by substantial evidence without considering any of the challenged evidence. Under Murphy v. Carron, 536 S.W.2d 30, 32[1, 2] (Mo. banc 1976) the judgment must be affirmed unless there is no substantial evidence to support it or unless it is against the weight of the evidence, or unless it erroneously declares or applies the law. The judgment in this case is supported by substantial evidence and is not against the weight of the evidence and does not erroneously declare or apply the law, with the exceptions hereinafter noted.

[503]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard's Original Long Creek Lodge v. Seymour Inn, Inc.
791 S.W.2d 944 (Missouri Court of Appeals, 1990)
St. Paul Fire & Marine Insurance Co. v. Starr
651 S.W.2d 517 (Missouri Court of Appeals, 1983)
Blair v. Blair
600 S.W.2d 143 (Missouri Court of Appeals, 1980)
King v. Smith
572 S.W.2d 200 (Missouri Court of Appeals, 1978)
In Re Estate of King
572 S.W.2d 200 (Missouri Court of Appeals, 1978)
Merrigan v. Spradling
564 S.W.2d 615 (Missouri Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
546 S.W.2d 500, 1976 Mo. App. LEXIS 2343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruckman-hansen-inc-v-state-highway-commission-moctapp-1976.