Rti, LLC v. Pro Engineering

2025 S.D. 64
CourtSouth Dakota Supreme Court
DecidedNovember 12, 2025
Docket30565
StatusPublished

This text of 2025 S.D. 64 (Rti, LLC v. Pro Engineering) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rti, LLC v. Pro Engineering, 2025 S.D. 64 (S.D. 2025).

Opinion

#30565-aff in pt & rev in pt-JMK 2025 S.D. 64

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

RTI, LLC and RTI HOLDINGS, LLC, Plaintiffs and Appellants,

v.

PRO ENGINEERING, INC.; DESIGNARC GROUP, INC.; F.M. ACOUSTICAL TILE, INC.; TRANE U.S. INC.; and EKERN HOME EQUIPMENT COMPANY, Defendants and Appellees,

and

RE COM, INC. Defendant.

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT BROOKINGS COUNTY, SOUTH DAKOTA

THE HONORABLE DAWN M. ELSHERE Judge

SHAWN M. NICHOLS ANDREW S. HURD CLAIRE E. WILKA of Cadwell Sanford Deibert & Garry LLP Sioux Falls, South Dakota Attorneys for plaintiff and appellant RTI, LLC and RTI Holdings, LLC.

CONSIDERED ON BRIEFS AUGUST 27, 2024 OPINION FILED 11/12/25 ****

GREGORY H. WHEELER of Boyce Law Firm, LLP Sioux Falls, South Dakota Attorneys for defendant and appellee designArc Group, Inc.

DANIEL R. FRITZ of Ballard Spahr LLP Sioux Falls, South Dakota

JUAN M. AVILA AARON C. ABELLERIA of Arthur Chapman Kettering Smetak & Pikala, P.A. Minneapolis, Minnesota Attorneys for defendant and appellee Ekern Home Equipment Company.

MARK J. ARNDT RYAN W.W. REDD of Evans, Haigh & Arndt, LLP Sioux Falls, South Dakota Attorneys for defendant and appellee F.M. Acoustical Tile, Inc.

ERIC J. STEINHOFF BRANDON D. MESHBESHER of Lind, Jensen, Sullivan & Peterson, P.A. Minneapolis, Minnesota Attorneys for defendant and appellee Pro Engineering Inc.

COURTNEY R. CLAYBORNE of Clayborne, Loos & Sabers, LLP Rapid City, South Dakota

MARC M. BERG of J. Selmer Law P.A. Minneapolis, Minnesota Attorneys for defendant and appellee Trane U.S. Inc. #30565

KERN, Justice

[¶1.] RTI, LLC, and RTI Holdings, LLC (collectively RTI), sought to build a

clinical research facility (the Facility) in Brookings, South Dakota, to perform

animal health research trials. Due to the nature of the testing, the Facility had

unique requirements for air filtration, air flow, and ventilation. RTI, acting as the

general contractor, hired an architect and various contractors to complete the

project. The Facility was completed in April 2016.

[¶2.] Within months of completion, RTI encountered several issues with the

Facility and sued the architect and contractors, alleging breach of contract and

breach of implied warranties. The defendants all moved for summary judgment and

soon after, RTI sought to amend its second amended complaint to allow it to assert

additional claims against two of the defendants.

[¶3.] The circuit court granted all defendants’ motions for summary

judgment, concluding that RTI’s claims were based on professional negligence and

therefore required expert testimony and that RTI’s CEO, Rolland Nevins, lacked

the necessary qualifications to provide the requisite expert testimony. The circuit

court also denied RTI’s motion to amend the complaint, finding it untimely and the

proposed amendments futile. RTI appeals the dismissal of its claims and the denial

of its motion to amend. We affirm in part and reverse in part.

Factual and Procedural Background

[¶4.] RTI is involved in research in the animal health industry, performing

testing and trials for customers seeking to test various animal products, including

the testing and development of animal vaccines. RTI sought to build a new clinical

-1- #30565

research Facility with individually ventilated rooms. The Facility was to be USDA

BSL-2 certified and therefore had to meet specific requirements, particularly as to

air filtration and flow to prevent cross-contamination.1

[¶5.] RTI acted as the general contractor for the project, with Nevins in

charge of the day-to-day construction details. Through a verbal agreement, RTI

hired designArc as the architect for the project. RTI also hired various contractors

for the project, including Pro Engineering, Inc., to design the HVAC system; Ekern

Home Equipment Co. (Ekern), to install the HVAC and plumbing; and FM

Acoustical Tile (FM) to install the ceiling. Ekern subcontracted with Trane U.S. to

provide and install the HVAC equipment and with ReCom, Inc., to test and balance

the HVAC system.2 RTI later entered into a service agreement with Trane under

1. Biosafety Level 2 (BSL-2) “is suitable for work in clinical, diagnostic, teaching, research or production facilities involving agents of moderate potential hazard to personnel and the environment.” Under BSL-2:

(1) laboratory personnel have specific training in handling pathogenic agents and are directed by competent scientists,

(2) access to the laboratory is limited when work is being conducted, and

(3) certain procedures in which infectious aerosols are created are conducted in biological safety cabinets or other physical containment equipment.

U.S. Dep’t of Health and Human Services et al., Biosafety in Microbiological and Biomedical Laboratories 37 (6th ed. 2020), Biosafety in Microbiological and Biomedical Laboratories (BMBL) 6th Edition | CDC Laboratories.

2. ReCom settled with RTI prior to the summary judgment motions and is not part of the appeal. -2- #30565

which Trane agreed to inspect and provide maintenance for the HVAC system at

the Facility.

[¶6.] RTI alleged that the Facility required an air filtration system that

would filter the air both entering and exiting the testing rooms to capture

contaminants/infectious agents using HEPA filters.3 In particular, the Facility

required clean air to flow from a clean air hallway to the animal testing room, and

then the dirty air was to flow to a dirty air hallway to be filtered out of the Facility.

The air pressure system was key to the desired air flow pattern.

[¶7.] Problems with certain aspects of the Facility arose soon after

construction was completed in April 2016. Contrary to its initial understanding of

the project specifications, RTI claimed it learned that if it adjusted the air pressure

in individual rooms, the entire system would have to be rebalanced, which would

take two to three days each time an adjustment was made. To address this issue,

RTI determined that the Facility required pressurization monitors or sensors, which

were not originally recommended. The pressurization monitors were installed in

November 2016 at an additional cost of approximately $35,000, and the air pressure

system began operating as intended, without rebalancing.

[¶8.] However, RTI then noticed that when the air pressure of individual

rooms was adjusted, the suspended ceiling would move up and down, which

allegedly caused wires to snap and a portion of the ceiling in some of the testing

3. A “HEPA” filter is a high efficiency particulate air filter. According to the Environmental Protection Agency, “This type of air filter can theoretically remove at least 99.97% of dust, pollen, mold, bacteria, and any airborne particles with a size of 0.3 microns (µm).” See https://www.epa.gov/indoor-air- quality-iaq/what-hepa-filter (last visited Nov. 6, 2025). -3- #30565

rooms to collapse. RTI alleged that after the pressure sensors were installed,

additional air ducts and valves had to be installed to connect the main HVAC

system to the clean corridor’s separate HVAC system, at an additional cost to RTI.

[¶9.] After construction was completed, RTI contracted with Pacific GeneTec

(PGT) to develop a poultry salmonella vaccine. Although RTI’s Facility was

designed to eliminate risks of contamination, it became clear while performing the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luther v. City of Winner
2004 SD 1 (South Dakota Supreme Court, 2004)
Kjerstad v. Ravellette Publications, Inc.
517 N.W.2d 419 (South Dakota Supreme Court, 1994)
Guy M. Cooper, Inc. v. East Penn School District
903 A.2d 608 (Commonwealth Court of Pennsylvania, 2006)
Isakson v. Parris
526 N.W.2d 733 (South Dakota Supreme Court, 1995)
Mid-Western Electric, Inc. v. DeWild Grant Reckert & Associates Co.
500 N.W.2d 250 (South Dakota Supreme Court, 1993)
Dahl v. Sittner
429 N.W.2d 458 (South Dakota Supreme Court, 1988)
Noble for Drenker v. Shaver
1998 SD 102 (South Dakota Supreme Court, 1998)
Watson, Watson, Rutland/Architects, Inc. v. BD. OF EDUC.
559 So. 2d 168 (Supreme Court of Alabama, 1990)
First National Bank v. Felt
368 N.W.2d 588 (South Dakota Supreme Court, 1985)
Nemec v. Deering
350 N.W.2d 53 (South Dakota Supreme Court, 1984)
KRANTZ, INC. v. Nissan North America, Inc.
408 F. Supp. 2d 854 (D. South Dakota, 2005)
Zhi Gang Zhang v. Rasmus
932 N.W.2d 153 (South Dakota Supreme Court, 2019)
KOKO Development, LLC v. Phillips & Jordan, Inc.
101 F.4th 544 (Eighth Circuit, 2024)
Zhang v. Rasmus
2019 S.D. 46 (South Dakota Supreme Court, 2019)
Fodness v. City of Sioux Falls
947 N.W.2d 619 (South Dakota Supreme Court, 2020)
Sheard v. Hattum
2021 S.D. 55 (South Dakota Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2025 S.D. 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rti-llc-v-pro-engineering-sd-2025.