R.T. Builders, Inc. v. Granger, Unpublished Decision (11-9-2005)

2005 Ohio 6043
CourtOhio Court of Appeals
DecidedNovember 9, 2005
DocketNo. 04-MA-147.
StatusUnpublished
Cited by1 cases

This text of 2005 Ohio 6043 (R.T. Builders, Inc. v. Granger, Unpublished Decision (11-9-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.T. Builders, Inc. v. Granger, Unpublished Decision (11-9-2005), 2005 Ohio 6043 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} Defendants-appellants, Ross and Kathleen Granger, appeal from a jury award of $90,000 in favor of plaintiff-appellee, R.T. Builders, Inc., on appellee's claims for breach of contract and conversion and appellants' counterclaim for breach of contract in the Mahoning County Common Pleas Court.

{¶ 2} Appellants entered into a contract with appellee's president, Richard Troiano, for the construction of a home in North Lima, Ohio. The contract price was $374,325. The parties signed a payout schedule that set out the amount appellants would pay appellee based upon various levels of completion of the contract. The schedule provided for five payments of specific amounts upon the completion of certain percentages of completion and specific tasks such as framing with shingles, electric and plumbing work, and interior painting.

{¶ 3} Appellants financed their construction loan through Farmers National Bank. Under the payout schedule, one of the parties had to contact the bank to request a draw on the loan. An appraiser would then inspect the house to ensure the proper work was completed. Upon the appraiser's approval, the bank would then forward the appropriate funds to appellee upon one of appellants' signatures.

{¶ 4} Appellants authorized payments for the first two draws in full. When it came time for the third draw, appellants did not want to pay appellee the full amount because the concrete garage floor had been damaged by Fagan Lumber (Fagan). Appellee repaired the damaged concrete. Nonetheless, due to the concrete damage, appellants authorized the payment of the third draw minus $3,000, which was the amount to replace the concrete.

{¶ 5} Appellee requested the fourth draw on or about November 9, 2000. The appraiser's inspection revealed that, at the time, construction was 88 percent complete. Under the payment schedule, 85 percent completion was required for appellee to receive the fourth draw. The amount of the fourth draw on the payment schedule was $78,608.25. However, appellee requested $82,000. This created a dispute between the parties. Based upon the 88 percent completion, the bank was willing to pay appellee $92,838. However, appellants would not authorize payment.

{¶ 6} One of the items listed on the payment schedule for appellee to receive the fourth draw was that the kitchen cabinets were to be installed. However, as of November 10, appellee had not yet installed the cabinets. The allowance for the cabinets was $14,000. Mr. Granger stated that he would not authorize payment because he believed appellee was not going to complete the construction of the home. However, Mr. Granger also testified that although he and his wife looked at cabinets in the summer, they did not order the cabinets until October 2. Appellee claimed that because of appellants' delay in ordering the cabinets, there was no way they could be installed by November 10.

{¶ 7} Appellants believed that appellee was not going to pay for the cabinets with the fourth draw and had additional concerns about how appellee was financing the job. They requested additional financial information from appellee, but claim none was provided.

{¶ 8} Appellee never did any work on the house after November 10. It filed a suit against appellants alleging breach of contract and conversion. The conversion claim stemmed from the damaged concrete. Apparently, appellee repaired the damage caused by Fagan. Fagan later issued a check to appellants for $3,000 with a release regarding the damage it had caused. Appellants cashed this check but never paid the money to appellee. Additionally, as mentioned above, they withheld $3,000 from the third draw due to the concrete damage. Appellee claimed therefore, that it was entitled to $3,000 on a conversion claim. Appellants subsequently filed a counterclaim for breach of contract alleging appellee failed to complete construction.

{¶ 9} The case proceeded to a jury trial. Appellants moved for a directed verdict, which the court overruled. The jury returned a verdict in favor of appellee for $90,000. The court entered judgment on the verdict on May 21, 2004. Appellants filed a motion for a new trial or a judgment notwithstanding the verdict. The trial court overruled appellants' motions. Appellants subsequently filed a notice of appeal on June 30, 2004.

{¶ 10} Appellants raise three assignments of error, the first of which states:

{¶ 11} "THE JURY FINDING THAT APPELLANTS BREACHED THE CONTRACT WAS CONTRARY TO LAW AND AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE."

{¶ 12} Appellants argue that the jury's verdict on appellee's breach of contract claim was contrary to law and against the weight of the evidence. They contend that this case involved the interpretation of an unambiguous contract and payment schedule. Appellants argue that the payment schedule controlled the payouts. They contend that appellee's entire case is based on the statement by the banker that the bank would have authorized a payment of up to $92,000 based on the percentage of completion as determined by the appraiser. However, appellants argue, appellee did not have a contract with them to be paid in that way. Since appellee had not yet completed all of the requirements for the fourth draw, which included the installation of the kitchen cabinets, appellants contend it was not entitled to the fourth draw pursuant to the terms of the payment schedule.

{¶ 13} Appellants further argue that when they asked for assurances regarding the financing for the remainder of the work, appellee refused. They claim that they were fearful that appellee did not have sufficient funds to finish the contract.

{¶ 14} Thus, appellants contend that when appellee refused to return to work after November 10, it breached the contract, not the other way around.

{¶ 15} A judgment supported by some competent, credible evidence going to all the material elements of the case must not be reversed as being against the manifest weight of the evidence. Willett v. Felger (Mar. 29, 1999), 7th Dist. No. 96C-P-40; Gerijo, Inc. v. Fairfield (1994),70 Ohio St.3d 223, 226, 638 N.E.2d 533. Furthermore, in considering whether a judgment is against the manifest weight of the evidence, it is important that this court be guided by the presumption that the findings of the trier of fact are correct. Seasons Coal Co., Inc. v. Cleveland (1984), 10 Ohio St.3d 77, 80, 461 N.E.2d 1273. If the evidence is susceptible to more than one interpretation, we must construe the evidence consistently with the trial court's judgment. Gerijo,70 Ohio St.3d at 226.

{¶ 16} To prevail in a breach of contract case, the plaintiff must prove the existence of a contract, the plaintiff's performance under the contract, the defendant's breach, and damages. Doner v. Snapp (1994),98 Ohio App.3d 597, 600, 649 N.E.2d 42.

{¶ 17}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toronto City Schools Bd. of Edn. v. Ascent Resources Utica, L.L.C.
2024 Ohio 1436 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 6043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rt-builders-inc-v-granger-unpublished-decision-11-9-2005-ohioctapp-2005.