RSF Associates, LLC v. Nieto CA4/1

CourtCalifornia Court of Appeal
DecidedFebruary 18, 2021
DocketD076227
StatusUnpublished

This text of RSF Associates, LLC v. Nieto CA4/1 (RSF Associates, LLC v. Nieto CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RSF Associates, LLC v. Nieto CA4/1, (Cal. Ct. App. 2021).

Opinion

Filed 2/18/21 RSF Associates, LLC v. Nieto CA4/1 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

RSF ASSOCIATES, LLC, D076227

Plaintiff, Cross-defendant, and Respondent, (Super. Ct. No. 37-2018- v. 00001161-CU-BC-NC)

NATHANIEL NIETO,

Defendant, Cross-complainant, and Appellant.

APPEAL from a judgment of the Superior Court of San Diego County, Robert P. Dahlquist, Judge. Affirmed.

Nathaniel Joseph Nieto, in pro. per., for Defendant, Cross-complainant and Appellant. Law Offices of Darren J. Quinn and Darren J. Quinn, for Plaintiff, Cross-defendant and Respondent. In this contract action, the court issued a detailed ruling after a bench trial, finding in favor of plaintiff and cross-defendant RSF Associates, LLC (RSF) on the complaint and on the cross-complaint. Defendant and cross- complainant Nathaniel Nieto, doing business as Dave Heyden Landscaping (Heyden Landscaping), challenges the court’s ruling. We affirm. BACKGROUND Facts RSF is a general contractor that built two new buildings on land it owned in the City of San Marcos (City). RSF and Heyden Landscaping entered into a written contract for Heyden Landscaping to provide all landscaping for the property, including underground irrigation, for a fixed cost of $52,500. This dispute arises out of the landscaping to be installed on a strip of land between the sidewalk and the developed property, known as the Community Facility District (CFD). In its contract with Heyden Landscaping, RSF required that the landscaping on the CFD had to be approved by the City, using plans and materials approved by the City in advance, and with inspection and approval by the City of the installation and materials in the trenches for underground irrigation before the trenches were closed. Nieto and his crew started work on the project in April 2017. On September 18, 2017, RSF’s superintendent had an argument with Nieto at the site. The superintendent told Nieto that the work was progressing too slowly. RSF wanted to open the site by October 10, 2017. Nieto knew of this deadline. The landscaping work at that point “was not close to being completed.” Nieto left the site with his crew after the argument and never returned to complete the work.

2 The work that Heyden Landscaping had completed up until September 18 was not approved by the City. A city inspector subsequently inspected the irrigation pipes that Heyden Landscaping had laid, and told RSF that the materials and the entire plan for irrigation layout had not been approved, and it would not be approved due to conflicts with trees, depth, and possible hydraulics issues. An employee of RSF talked with Nieto about returning and completing the job. Nieto would not agree to return unless certain conditions were met. He also said he did not have a sufficient work crew to return to the job until October. RSF hired another landscaper. After conferring with the City inspector, the second landscaper concluded that most of Heyden Landscaping’s work on the CFD was “useless.” It had to be torn out and redone. The new landscaper finished the work by early December. Procedure RSF filed a complaint against Nieto, doing business as Heyden Landscaping, for breach of contract. Nieto cross-complained for breach of contract, goods and services rendered, and foreclosure of two mechanic’s liens he had filed. The court heard evidence over four days. At the conclusion, the court found that “Nieto failed to perform as required by the contract. The work performed by Nieto did not satisfy the City’s standards, as required by the contract. Nieto did not supply sufficient resources to complete the contract in a timely manner.” The court found that Nieto left the job without valid justification, causing RSF to hire another landscaping company to complete the contract work.

3 The court entered judgment on June 28, 2019, awarding RSF a net amount of $37,222.61. The court ruled against Nieto on his cross-complaint. Nieto appealed. RSF later obtained an award of costs and of attorney fees of more than $125,000.00. The court issued an amended judgment in the total amount of $171,322.51 on September 18, 2019. Nieto did not appeal from the amended judgment. DISCUSSION Nieto challenges the judgment of the trial court on three grounds: (1) RSF breached the contract by failing to pay Nieto pursuant to the terms of the contract; (2) RSF breached the contract by requiring Nieto to hire unlicensed day laborers; and (3) the court erred in awarding attorney fees to RSF. I. Standard of Review The three fundamental principles of appellate review are: “(1) a judgment is presumed correct; (2) all intendments and presumptions are indulged in favor of correctness; and (3) the appellant bears the burden of providing an adequate record affirmatively proving error. [Citations.]” (Fladeboe v. American Isuzu Motors Inc. (2007) 150 Cal.App.4th 42, 58–62 (Fladeboe).) In determining whether substantial evidence supports the court's judgment, we view the evidence in the light most favorable to the judgment. (Phillips v. Campbell (2016) 2 Cal.App.5th 844, 849–850.) We do not reweigh the evidence or second-guess the credibility of a witness. (In re Marriage of Balcof (2006) 141 Cal.App.4th 1509, 1531 (Balcof).) II. Contract Issues A. Failure to Pay Nieto claims that RSF breached the contract first by failing to pay Heyden Landscaping after July 2017.

4 1. Applicable Law Nieto was entitled to be paid for substantial performance, but RSF could reduce the amount owed to compensate for defects in performance. (Magic Carpet Ride LLC v. Rugger Investment Group, L.L.C. (2019) 41 Cal.App.5th 357, 364; Kossler v. Palm Springs Developments, Ltd. (1980) 101 Cal.App.3d 88, 102 [party to a contract entitled to reduction in contract price to compensate for deficiencies].) Substantial performance of the terms of the contract requires “ ‘that the defects be such as may be easily remedied or compensated, so that the promisee may get practically what the contract calls for.’ ” (Magic Carpet Ride, at p. 364.) Whether Nieto substantially performed in accordance with the terms of the contract is a question of fact that is left to the factfinder. (Ibid.) We affirm the court’s ruling on deficiencies in substantial performance if the court’s findings were supported by substantial evidence. (Schellinger Brothers v. Cotter (2016) 2 Cal.App.5th 984, 1002 (Schellinger).) 2. Background Nieto’s cross-complaint sought about $9,400 from RSF for work completed for which it was not paid. The court found that Nieto was not entitled to recover any money from RSF because Nieto failed to perform as required by the contract. As a preliminary matter, RSF contends that no money was owed to Nieto because the contract attached to the cross-complaint stated that payment would be due upon completion of the project. Nieto counters that an attachment to the contract, page 15, provided for monthly payments as work progressed. The court granted leave to admit page 15 as an exhibit, but stated that the outcome was the same even with that page included as part of

5 the contract.1 The court stated its “decision on the merits of the case does not turn on whether the parties’ contract contained ‘page 15.’ ” We assume there was a provision for monthly payments, as RSF paid Heyden Landscaping monthly from June through July, but, like the trial court, our review does not depend on the existence of the payment schedule. 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kossler v. Palm Springs Developments, Ltd.
101 Cal. App. 3d 88 (California Court of Appeal, 1980)
Fladeboe v. American Isuzu Motors Inc.
58 Cal. Rptr. 3d 225 (California Court of Appeal, 2007)
In Re Marriage of Balcof
47 Cal. Rptr. 3d 183 (California Court of Appeal, 2006)
Phillips v. Campbell
2 Cal. App. 5th 844 (California Court of Appeal, 2016)
Schellinger Brothers v. Cotter
2 Cal. App. 5th 984 (California Court of Appeal, 2016)
Nellie Gail Ranch Owners Ass'n v. McMullin
4 Cal. App. 5th 982 (California Court of Appeal, 2016)
Jameson v. Desta
420 P.3d 746 (California Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
RSF Associates, LLC v. Nieto CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rsf-associates-llc-v-nieto-ca41-calctapp-2021.