RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint

CourtDistrict Court, E.D. Washington
DecidedJune 8, 2026
Docket2:25-cv-00504
StatusUnknown

This text of RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint (RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint) is published on Counsel Stack Legal Research, covering District Court, E.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint, (E.D. Wash. 2026).

Opinion

1 2

3 4 5 UNITED STATES DISTRICT COURT

6 EASTERN DISTRICT OF WASHINGTON 7 RS TITAN, LLC, No. 2:25-cv-00504-MKD Plaintiff, 8 ORDER GRANTING IN PART AND v. DENYING IN PART 9 DEFENDANTS’ MOTION TO PUBLIC UTILITY DISTRICT NO. 2 DISMISS 10 OF GRANT COUNTY; TERRY PYLE; LARRY SCHAAPMAN; JUDY ECF No. 9 11 WILSON; NELSON COX; TOM FLINT, 12 Defendants. 13 Before the Court is Defendants’ Motion to Dismiss. ECF No. 9. The Court 14 held a hearing on May 26, 2026. ECF No. 14. David Steele and Jonathan Hawley 15 represented Plaintiff. John Cadagan and Mark Wilner represented Defendants. 16 The Court has reviewed the motion and record, heard from counsel, and is fully 17 informed. For the reasons explained below, the Court GRANTS in part and 18 DENIES in part the motion. 19 BACKGROUND 20 Plaintiff operates a data center at the Randolph Road facility in Moses Lake, 1 Washington. ECF No. 7 at 2 ¶ 1. The facility’s electrical service is supplied by 2 Defendant Grant County PUD, a municipal public utility district. Id. at 6 ¶ 13.

3 Plaintiff alleges that, for more than two decades, Plaintiff, its predecessors, and 4 affiliates worked with Grant County PUD to expand Defendants’ facilities and 5 increase the electrical capacity available to the Randolph Road facility. Id. at 7 ¶

6 19. 7 Beginning in 2000, Plaintiff’s predecessors and affiliates entered a series of 8 agreements with Grant County PUD related to increased electrical service at the 9 Randolph Road facility. Id. at 7-9 ¶¶ 20-24. In July 2000, Plaintiff’s predecessor

10 executed a Letter of Commitment agreeing to reimburse Defendants up to $1 11 million for design and procurement work needed to expand power to the facility. 12 Id. at 7-8 ¶ 20. In December 2002, Plaintiff’s predecessor and Grant County PUD

13 entered a Use of Facilities and Service Agreement under which Grant County PUD 14 agreed to install and modify electrical infrastructure and Plaintiff’s predecessor 15 agreed to pay a monthly charge for use of the PUD’s facilities. Id. at 8 ¶ 21. 16 Between 2005 and 2007, Plaintiff or its affiliates made additional facilities-cost

17 payments to the PUD, including payments associated with additional increments of 18 electrical service. Id. at 8-9 ¶¶ 22-23. Plaintiff alleges that, by the end of 2007, 19 these payments totaled more than $1.9 million. Id. at 9 ¶ 24.

20 On January 31, 2008, the parties entered a New Customer Agreement. Id. at 1 9 ¶ 26. Plaintiff alleges that the 2008 Agreement consolidated and superseded the 2 prior agreements. Id. Under the agreement, Grant PUD agreed to continue actions

3 to expand or modify its electrical facilities and to use reasonable efforts to 4 complete those actions so that it would be able to serve up to a maximum of 34.4 5 MVA of electrical service to the Randolph Road facility. Id. at 9-10 ¶ 27. Plaintiff

6 was responsible for charges relating to the PUD’s furnishing of electricity to the 7 facility, as well as a monthly minimum payment. Id. 8 Plaintiff alleges that it relied on the 2008 Agreement and the PUD’s prior 9 commitments in acquiring and investing in the Randolph Road facility. Id. at 10 ¶

10 28. Plaintiff further alleges that, in 2009, it deeded land to Grant County PUD to 11 facilitate construction of substations and related infrastructure needed to serve 12 increased load at the facility. Id. at 10-11 ¶ 29. Plaintiff also alleges that Grant

13 County PUD later confirmed the anticipated capacity: in 2009, it allegedly stated 14 that it intended to provide Plaintiff adequate capacity as Plaintiff’s need developed 15 “up to what has been paid for,” and in 2019, it allegedly confirmed that it had the 16 capability to meet approximately 34 MVA at the Randolph Road facility. Id. at 11

17 ¶¶ 30-32. 18 In late 2024 and 2025, Defendants adopted and applied new load-limit 19 policies. Plaintiff alleges that Defendants adopted Resolution 9074 in December

20 2024, giving the PUD authority to set and enforce load limits, and later adopted 1 Resolution 9098 in August 2025 as part of its Customer Service Policies. During 2 that same period, Defendants sent Plaintiff letters stating that Plaintiff’s allowable

3 load at the Randolph Road facility would be limited to 9.2 MW. Plaintiff alleges 4 that it demanded Defendants honor the 34.4 MVA level of service, but Defendants 5 did not do so. Id. at 12 ¶¶ 35-38.

6 Separately, in August 2023, Plaintiff submitted a large-power application to 7 Defendants seeking an additional 41 MVA of electrical service for the Randolph 8 Road facility, beyond the 34.4 MVA Plaintiff alleges it was already entitled to 9 receive. Id. at 13 ¶ 41. Plaintiff paid the then-required $21,000 nonrefundable

10 application fee. Id. Plaintiff alleges that this payment placed its application in 11 Defendants’ large electric service queue. Id. at 13-14 ¶ 42. After submitting the 12 application, Plaintiff followed up with Defendants about timing and alleges it was

13 told that there were long delays, that no action was required from Plaintiff, and that 14 Plaintiff could continue checking in. Id. at 14 ¶ 43. 15 In September 2025, the PUD informed Plaintiff that it had updated its large- 16 power application fee schedule effective September 1, 2025, and that existing

17 applications in the queue without a Facilities Construction Agreement would be 18 subject to the updated fee structure. Id. at 14-15 ¶ 44. For Plaintiff’s 41 MVA 19 request, the PUD assessed a total application fee of $1,640,000. Id. at 15 ¶ 45.

20 After crediting Plaintiff’s prior $21,000 payment, the PUD required Plaintiff to pay 1 an additional $1,619,000. Id. The PUD’s communication stated that if Plaintiff 2 did not timely respond or pay, its application would be deemed forfeited and

3 cancelled, and reapplication would require starting at the end of the queue. Id. at 4 16 ¶ 48. Plaintiff responded that it wished to remain in the queue with no change 5 to its requested load and was later billed the outstanding balance. Id. at 16 ¶¶ 49-

6 50. 7 LEGAL STANDARD 8 “To survive a [Fed. R. Civ. P. 12(b)(6)] motion to dismiss, a complaint must 9 contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is

10 plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell 11 Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “Threadbare recitals of the 12 elements of a cause of action, supported by mere conclusory statements, do not

13 suffice.” Id. In considering a motion to dismiss for failure to state a claim, the 14 Court must accept as true the well-pleaded factual allegations and any reasonable 15 inference to be drawn from them, but legal conclusions are not entitled to the same 16 assumption of truth. Id. A complaint must contain either direct or inferential

17 allegations respecting all the material elements necessary to sustain recovery under 18 some viable legal theory. Twombly, 550 U.S. at 562. “Factual allegations must be 19 enough to raise a right to relief above the speculative level.” Id. at 555.

20 1 DISCUSSION 2 Defendants move to dismiss all claims asserted in Plaintiff’s First Amended

3 Complaint. As discussed below, the Court dismisses the official capacity claims 4 against the individual Commissioners as redundant, dismisses Plaintiff’s federal 5 and state due process claims, and otherwise denies the motion.

6 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
United States Trust Co. of NY v. New Jersey
431 U.S. 1 (Supreme Court, 1977)
Kentucky v. Graham
473 U.S. 159 (Supreme Court, 1985)
Alden v. Maine
527 U.S. 706 (Supreme Court, 1999)
Lujan v. G & G Fire Sprinklers, Inc.
532 U.S. 189 (Supreme Court, 2001)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Shanks v. Dressel
540 F.3d 1082 (Ninth Circuit, 2008)
In Re the Marriage of MacDonald
709 P.2d 1196 (Washington Supreme Court, 1985)
Hite v. Public Utility District No. 2
772 P.2d 481 (Washington Supreme Court, 1989)
Nishikawa v. US EAGLE HIGH, LLC
158 P.3d 1265 (Court of Appeals of Washington, 2007)
Young v. Young
191 P.3d 1258 (Washington Supreme Court, 2008)
State v. Paul
12 P.3d 1036 (Court of Appeals of Washington, 2000)
Donovan Lee v. Intelius Inc
737 F.3d 1254 (Ninth Circuit, 2013)
Messick v. Johnson
1931 OK 736 (Supreme Court of Oklahoma, 1931)
Lager v. Berggren
60 P.2d 99 (Washington Supreme Court, 1936)
Pure Wafer Inc. v. City of Prescott
845 F.3d 943 (Ninth Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rs-titan-llc-v-public-utility-district-no-2-of-grant-county-terry-pyle-waed-2026.