RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint

District Court, E.D. Washington·Decided June 8, 2026·No. 2:25-cv-00504·Unknown

Opinion

RS TITAN, LLC, No. 2:25-cv-00504-MKD Plaintiff, ORDER GRANTING IN PART AND v. DENYING IN PART PUBLIC UTILITY DISTRICT NO. 2 DISMISS OF GRANT COUNTY; TERRY PYLE; LARRY SCHAAPMAN; JUDY ECF No. 9 WILSON; NELSON COX; TOM FLINT, Defendants. Before the Court is Defendants’ Motion to Dismiss. ECF No. 9. The Court held a hearing on May 26, 2026. ECF No. 14. David Steele and Jonathan Hawley represented Plaintiff. John Cadagan and Mark Wilner represented Defendants. The Court has reviewed the motion and record, heard from counsel, and is fully informed. For the reasons explained below, the Court GRANTS in part and DENIES in part the motion. Plaintiff operates a data center at the Randolph Road facility in Moses Lake, Washington. ECF No. 7 at 2 ¶ 1. The facility’s electrical service is supplied by Defendant Grant County PUD, a municipal public utility district. Id. at 6 ¶ 13.

Plaintiff alleges that, for more than two decades, Plaintiff, its predecessors, and affiliates worked with Grant County PUD to expand Defendants’ facilities and increase the electrical capacity available to the Randolph Road facility. Id. at 7 ¶

19. Beginning in 2000, Plaintiff’s predecessors and affiliates entered a series of agreements with Grant County PUD related to increased electrical service at the Randolph Road facility. Id. at 7-9 ¶¶ 20-24. In July 2000, Plaintiff’s predecessor

executed a Letter of Commitment agreeing to reimburse Defendants up to $1 million for design and procurement work needed to expand power to the facility. Id. at 7-8 ¶ 20. In December 2002, Plaintiff’s predecessor and Grant County PUD

entered a Use of Facilities and Service Agreement under which Grant County PUD agreed to install and modify electrical infrastructure and Plaintiff’s predecessor agreed to pay a monthly charge for use of the PUD’s facilities. Id. at 8 ¶ 21. Between 2005 and 2007, Plaintiff or its affiliates made additional facilities-cost

payments to the PUD, including payments associated with additional increments of electrical service. Id. at 8-9 ¶¶ 22-23. Plaintiff alleges that, by the end of 2007, these payments totaled more than $1.9 million. Id. at 9 ¶ 24.

On January 31, 2008, the parties entered a New Customer Agreement. Id. at 9 ¶ 26. Plaintiff alleges that the 2008 Agreement consolidated and superseded the prior agreements. Id. Under the agreement, Grant PUD agreed to continue actions

to expand or modify its electrical facilities and to use reasonable efforts to complete those actions so that it would be able to serve up to a maximum of 34.4 MVA of electrical service to the Randolph Road facility. Id. at 9-10 ¶ 27. Plaintiff

was responsible for charges relating to the PUD’s furnishing of electricity to the facility, as well as a monthly minimum payment. Id. Plaintiff alleges that it relied on the 2008 Agreement and the PUD’s prior commitments in acquiring and investing in the Randolph Road facility. Id. at 10 ¶

28. Plaintiff further alleges that, in 2009, it deeded land to Grant County PUD to facilitate construction of substations and related infrastructure needed to serve increased load at the facility. Id. at 10-11 ¶ 29. Plaintiff also alleges that Grant

County PUD later confirmed the anticipated capacity: in 2009, it allegedly stated that it intended to provide Plaintiff adequate capacity as Plaintiff’s need developed “up to what has been paid for,” and in 2019, it allegedly confirmed that it had the capability to meet approximately 34 MVA at the Randolph Road facility. Id. at 11

¶¶ 30-32. In late 2024 and 2025, Defendants adopted and applied new load-limit policies. Plaintiff alleges that Defendants adopted Resolution 9074 in December

2024, giving the PUD authority to set and enforce load limits, and later adopted Resolution 9098 in August 2025 as part of its Customer Service Policies. During that same period, Defendants sent Plaintiff letters stating that Plaintiff’s allowable

load at the Randolph Road facility would be limited to 9.2 MW. Plaintiff alleges that it demanded Defendants honor the 34.4 MVA level of service, but Defendants did not do so. Id. at 12 ¶¶ 35-38.

Separately, in August 2023, Plaintiff submitted a large-power application to Defendants seeking an additional 41 MVA of electrical service for the Randolph Road facility, beyond the 34.4 MVA Plaintiff alleges it was already entitled to receive. Id. at 13 ¶ 41. Plaintiff paid the then-required $21,000 nonrefundable

application fee. Id. Plaintiff alleges that this payment placed its application in Defendants’ large electric service queue. Id. at 13-14 ¶ 42. After submitting the application, Plaintiff followed up with Defendants about timing and alleges it was

told that there were long delays, that no action was required from Plaintiff, and that Plaintiff could continue checking in. Id. at 14 ¶ 43. In September 2025, the PUD informed Plaintiff that it had updated its large- power application fee schedule effective September 1, 2025, and that existing

applications in the queue without a Facilities Construction Agreement would be subject to the updated fee structure. Id. at 14-15 ¶ 44. For Plaintiff’s 41 MVA request, the PUD assessed a total application fee of $1,640,000. Id. at 15 ¶ 45.

After crediting Plaintiff’s prior $21,000 payment, the PUD required Plaintiff to pay an additional $1,619,000. Id. The PUD’s communication stated that if Plaintiff did not timely respond or pay, its application would be deemed forfeited and

cancelled, and reapplication would require starting at the end of the queue. Id. at 16 ¶ 48. Plaintiff responded that it wished to remain in the queue with no change to its requested load and was later billed the outstanding balance. Id. at 16 ¶¶ 49-

50. “To survive a [Fed. R. Civ. P. 12(b)(6)] motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is

plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not

suffice.” Id. In considering a motion to dismiss for failure to state a claim, the Court must accept as true the well-pleaded factual allegations and any reasonable inference to be drawn from them, but legal conclusions are not entitled to the same assumption of truth. Id. A complaint must contain either direct or inferential

allegations respecting all the material elements necessary to sustain recovery under some viable legal theory. Twombly, 550 U.S. at 562. “Factual allegations must be enough to raise a right to relief above the speculative level.” Id. at 555.

Defendants move to dismiss all claims asserted in Plaintiff’s First Amended

Complaint. As discussed below, the Court dismisses the official capacity claims against the individual Commissioners as redundant, dismisses Plaintiff’s federal and state due process claims, and otherwise denies the motion.

A. Official Capacity Claims Defendants move to dismiss the claims against the Commissioners as redundant because Grant County PUD itself is named as a defendant. An official capacity claim is treated as a claim against the entity itself. Kentucky v. Graham,

Free access — add to your briefcase to read the full text and ask questions with AI

RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint, (E.D. Wash. 2026).

RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint (RS Titan, LLC v. Public Utility District No. 2 of Grant County; Terry Pyle; Larry Schaapman; Judy Wilson; Nelson Cox; Tom Flint) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
United States Trust Co. of NY v. New Jersey
431 U.S. 1 (Supreme Court, 1977)
Kentucky v. Graham
473 U.S. 159 (Supreme Court, 1985)
Alden v. Maine
527 U.S. 706 (Supreme Court, 1999)
Lujan v. G & G Fire Sprinklers, Inc.
532 U.S. 189 (Supreme Court, 2001)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Shanks v. Dressel
540 F.3d 1082 (Ninth Circuit, 2008)
In Re the Marriage of MacDonald
709 P.2d 1196 (Washington Supreme Court, 1985)
Hite v. Public Utility District No. 2
772 P.2d 481 (Washington Supreme Court, 1989)
Nishikawa v. US EAGLE HIGH, LLC
158 P.3d 1265 (Court of Appeals of Washington, 2007)
Young v. Young
191 P.3d 1258 (Washington Supreme Court, 2008)
State v. Paul
12 P.3d 1036 (Court of Appeals of Washington, 2000)
Donovan Lee v. Intelius Inc
737 F.3d 1254 (Ninth Circuit, 2013)
Messick v. Johnson
1931 OK 736 (Supreme Court of Oklahoma, 1931)
Lager v. Berggren
60 P.2d 99 (Washington Supreme Court, 1936)
Pure Wafer Inc. v. City of Prescott
845 F.3d 943 (Ninth Circuit, 2017)