RPM Plumbing Mechanical, Inc. v. Jim Plunkett, Inc.

46 S.W.3d 60, 2001 Mo. App. LEXIS 601, 2001 WL 339638
CourtMissouri Court of Appeals
DecidedApril 10, 2001
DocketWD 58454
StatusPublished
Cited by12 cases

This text of 46 S.W.3d 60 (RPM Plumbing Mechanical, Inc. v. Jim Plunkett, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RPM Plumbing Mechanical, Inc. v. Jim Plunkett, Inc., 46 S.W.3d 60, 2001 Mo. App. LEXIS 601, 2001 WL 339638 (Mo. Ct. App. 2001).

Opinion

SPINDEN, Chief Judge.

This case involves a dispute between a general contractor, Jim Plunkett, Inc., and its subcontractor, RPM Plumbing Mechanical, Inc., about plumbing work provided by RPM at Crestview Nursing Home in Bethany. In its lawsuit against Plunkett, RPM claimed that Plunkett owed it $18,160. After a bench trial, the circuit court entered judgment of $3160 for RPM against Plunkett and Associated Indemnity Corporation. 1

RPM appeals. It asserts that the circuit court erred in refusing to award the entire amount of its claim because Plunkett did not plead, and was not entitled to, a set-off or recoupment. RPM also claims that the circuit court erred in not awarding prejudgment interest on the $3160. We affirm the circuit court’s award of $3160 but reverse the circuit court’s denial of prejudgment interest and remand for the circuit court to award prejudgment interest on the $3160.

The dispute arose from RPM’s work on the Crestview project. Pursuant to the terms of the contract, RPM agreed to perform all of the project’s plumbing work for $76,000. The contract specified that RPM was to install “Type L” copper plumbing pipe for an above-ground domestic water system.

When the plumbing work was nearly complete, a nursing home representative discovered that RPM had installed “Type M” copper plumbing pipes instead of “Type L.” On March 6, 1997, representatives of RPM and Plunkett met with the project’s architect, engineer and owner to discuss the problem. The nursing home *62 considered two alternatives to resolving the problem: have all of the nonconforming pipes removed at a cost to RPM of at least $40,000 2 or have only exposed pipes removed and replaced on the conditions that shnt-off valves be installed at various points and have RPM secure a 10 year, $50,000 bond to protect the owner from problems resulting from nonconforming plumbing pipes. The owner and RPM agreed to the second alternative. Although RPM removed and replaced the exposed pipes and put in shut-off valves, RPM never provided a bond.

Because RPM did not provide a bond, Plunkett agreed to deduct $15,000 from its contract if the owner accepted the remaining non-conforming pipes. Plunkett informed RPM by letter about the settlement agreement and informed RPM that, pursuant to the terms of its subcontract, Plunkett would deduct $15,000 from the balance owing to RPM.

RPM sued Plunkett on the ground that it was entitled to the entire $18,160 balance due and that it was not bound by Plunkett’s settlement with the project owner. At trial, Plunkett admitted that it owed RPM $3160 even after deducting the $15,000. The circuit court entered judgment of $8160 for RPM and did not order interest on the judgment.

In this appeal, RPM contends that the circuit court erred in not awarding the entire amount of its claim. It asserts that Plunkett was not entitled to a set-off 3 or recoupment of $15,000 because it did not plead it as an affirmative defense. RPM, however, permitted Plunkett to try the issue without objection. We deem the parties to have tried the issue by implied consent pursuant to Rule 55.33(b).

Although the defense of recoupment is “generally embraced in the subject of counterclaim,” it is “still available as a purely defensive matter going only to the reduction or satisfaction of the plaintiffs claim.” Brush v. Miller, 208 S.W.2d 816, 820 (Mo.App.1948). Thus, in a case involving defective performance under a contract, a defendant can elect whether to plead “the defective work in reduction of the plaintiffs damages, or whether to plead his own damage as a eounterclaim[.]” Id. If the defendant elects to assert it as an affirmative defense, the defendant must plead it as an affirmative defense. Dyna Flex Limited v. Charleville, 890 S.W.2d 413, 414 (Mo.App.1995). 4

Rule 55.33(b), however, says, “When issues not raised by the pleadings are tried by express or implied consent of *63 the parties, they shall be treated in all respects as if they had been raised in the pleadings.” This means that, when evidence is admitted without objection, we will deem the pleadings to have been amended to conform to the evidence. Seaton v. Weir, 633 S.W.2d 212, 214 n. 4 (Mo.App.1982); Diversified Metal Fabricators, Inc. v. Blue Skies, Inc., 899 S.W.2d 556, 561 (Mo.App.1995); Stegemann v. Helbig, 625 S.W.2d 677, 679 n. 1 (Mo.App.1981). “[Ejvidence received without objection will give rise to an amendment of the pleadings by implied consent only when it bears solely on the proposed new issue and is not relevant to some other issue already in the case.” Kackley v. Burtrum, 947 S.W.2d 461, 465 n. 3 (Mo.App.1997).

Because RPM did not object to evidence supporting the defense and that evidence was not relevant to any other issue in the case, we deem Plunkett’s affirmative defense of recoupment to have been tried by implied consent. Plunkett presented the testimony of the project’s engineer, Ron Mays, that the pipes installed by RPM were inferior to the pipes specified in contract documents. Dean Thompson, the owner’s representative, testified that the owner deducted $15,000 from its contract with Plunkett because RPM had installed inferior pipe not meeting specifications. He said, “[W]e wanted complete replacement of the pipe, or some type of a cash reserve that would cover the cost of any damage we might have from broken lines.” Jim Plunkett, Plunkett’s owner, testified that, because RPM did not install the specified pipes, the owner withheld $15,000 from its payment to Plunkett, so Plunkett withheld $15,000 from its payment to RPM. The circuit court also heard testimony about the process of negotiating a resolution of the dispute, including the negotiations leading to the $15,000 settlement. This testimony was pertinent to RPM’s deficient performance under the contract and the resulting damages sustained by Plunkett.

RPM counters that, even if the issue was tried by consent, Plunkett was not entitled to recoupment of $15,000 because Plunkett did not demonstrate that it had been damaged. RPM argues that the $15,000 figure resulted from mere speculation. We disagree. The number resulted from negotiations between Plunkett and the owner; however, it was based on the architect’s evidence that a failure resulting from RPM’s installing inferior pipe would cost about $20,000 to repair. Although the owner wanted at least the $20,000 as a cash reserve to cover any failures, it settled for $15,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher Rank, DMD v. Sandra Smith
Missouri Court of Appeals, 2020
Agriservices of Brunswick, LLC v. Jacoby
548 S.W.3d 430 (Missouri Court of Appeals, 2018)
Trokey v. R.D.P. Development Group, L.L.C.
401 S.W.3d 516 (Missouri Court of Appeals, 2013)
Unerstall Foundations, Inc. v. Corley
328 S.W.3d 305 (Missouri Court of Appeals, 2010)
Knox v. Morris
293 S.W.3d 478 (Missouri Court of Appeals, 2009)
Shuler v. Premium Standard Farms, Inc.
148 S.W.3d 1 (Missouri Court of Appeals, 2004)
City of St. Joseph v. St. Joseph Riverboat Partners
141 S.W.3d 513 (Missouri Court of Appeals, 2004)
Citibank (South Dakota), N.A. v. Mincks
135 S.W.3d 545 (Missouri Court of Appeals, 2004)
Hollida v. Hollida
131 S.W.3d 911 (Missouri Court of Appeals, 2004)
Boatright v. Boatright
88 S.W.3d 500 (Missouri Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
46 S.W.3d 60, 2001 Mo. App. LEXIS 601, 2001 WL 339638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rpm-plumbing-mechanical-inc-v-jim-plunkett-inc-moctapp-2001.