Royal Ridge Construction, LLC v. Jo Lynn Spradlin
This text of 2025 Ark. App. 528 (Royal Ridge Construction, LLC v. Jo Lynn Spradlin) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Cite as 2025 Ark. App. 528 ARKANSAS COURT OF APPEALS DIVISION II No. CV-24-556
ROYAL RIDGE CONSTRUCTION, LLC Opinion Delivered November 5, 2025 APPELLANT APPEAL FROM THE SEBASTIAN V. COUNTY CIRCUIT COURT, FORT SMITH DISTRICT [NO. 66FCV-24-398] JO LYNN SPRADLIN HONORABLE GREG MAGNESS, APPELLEE JUDGE
AFFIRMED
N. MARK KLAPPENBACH, Chief Judge
Royal Ridge Construction, LLC, appeals the circuit court order denying its motion
to compel arbitration in a lawsuit filed by Jo Lynn Spradlin. We affirm.
In December 2020, Spradlin signed a contract for Royal Ridge to construct a home
in Fort Smith. The contract, drafted by Royal Ridge, has nine pages with a total of twenty-
one paragraphs that include provisions for the scope of the work, the compensation,
cancellation and work-suspension rights, the commencement (January 2021) and completion
(October 2021) dates, insurance and risk of loss, and site visits, among other topics.
Paragraph sixteen on page seven is titled “Mediation and Arbitration – Small Claims.” It
provides that either party may request mediation or pursue a small claims action; if those
two methods of dispute resolution do not work, then the final alternative is to pursue mandatory arbitration. Paragraph sixteen has its own internal signature lines for both
parties:
THIS ARBITRATION CLAUSE WAS SEEN AND AGREED TO:
___________ _____________ ______________ (Owner) (Owner) (Contractor)
Only Spradlin signed this paragraph’s signature lines.
The nineteenth paragraph is titled “Severability,” and it recites that if any provision
of the contract is determined by a court to be invalid or unenforceable, then the remainder
of the contract will remain in full force and effect. On page nine, there are signature and
date lines for both partes:
SEEN AND AGREED TO:
____________________ __________________________ Owner Date Contractor Date
____________________ By________________________ Owner Date Signature Title
Only Spradlin signed and dated it.
Ultimately, Spradlin was dissatisfied with Royal Ridge’s construction. Spradlin
initiated arbitration, and the parties had an initial arbitration conference call in February
2024. Spradlin withdrew from arbitration when Royal Ridge could not produce a contract
that it signed.
In April 2024, Spradlin filed a lawsuit in circuit court. She appended the contract
she signed. Royal Ridge filed a motion to compel arbitration. At the hearing on the motion,
2 Jonathan Griffin (an owner of Royal Ridge) testified that the company would typically sign
the contract and he would be surprised if it had not, but a signed copy could not be found.
Griffin said Royal Ridge had never before tried to enforce arbitration under a contract like
this. Spradlin testified that she began with arbitration because she had signed the contract,
but when she realized that Royal Ridge had not signed the contract, she pursued the lawsuit.
The circuit court denied the motion to arbitrate, focusing on whether there was
mutual agreement and assent. The circuit court found it significant that there was a separate
signature block for paragraph sixteen within the construction contract. Absent mutual
assent, Royal Ridge could not demand arbitration nor would the court compel it. This
appeal followed.
An order denying a motion to compel arbitration is immediately appealable. Ark. R.
App. P.–Civ. 2(a)(12) (2025). We review a circuit court’s denial of a motion to compel
arbitration de novo on the record. Heather Manor Care Ctr., Inc. v. Marshall by Ellis, 2024
Ark. App. 596, 704 S.W.3d 134. While we are not bound by the circuit court’s decision, in
the absence of a showing that the circuit court erred in its interpretation of the law, we will
accept its decision as correct on appeal. Id. When a court is asked to compel arbitration, it
is limited to deciding two threshold questions: (1) whether there is a valid agreement to
arbitrate between the parties and, (2) if such an agreement exists, whether the dispute falls
within its scope. Id.
Was there a valid arbitration agreement between the parties? The parties agree that
this is the dispositive issue. We are guided here by the legal principle that contractual
3 agreements are construed against the drafter. Heather Manor, supra. We look to state contract
law to determine whether the parties’ agreement is valid. Id. In Arkansas, the essential
elements for an enforceable arbitration agreement are (1) competent parties, (2) subject
matter, (3) legal consideration, (4) mutual agreement, and (5) mutual obligation. Id. Royal
Ridge, as the proponent of the arbitration agreement, has the burden of proving these
essential elements. Id. The reviewing court employs an objective test for determining mutual
assent, looking for objective indicators of agreement and not subjective opinions. Pine Hills
Health & Rehab., LLC v. Matthews, 2014 Ark. 109, 431 S.W.3d 910; STAP, Inc. v. Sutterfield,
2020 Ark. App. 18, 592 S.W.3d 249.
This construction contract, drafted by Royal Ridge, contains the paragraph on
arbitration that has its own signature lines for both parties. What would be the purpose of
the signature lines related solely to the arbitration provision if not to manifest mutual assent
to arbitration? The construction contract also contains a severability clause that provides
that if any paragraph’s provisions are deemed invalid, then the remainder of the contract
provisions remain in effect. Royal Ridge agreed to construct the house for Spradlin and was
paid for its services. Royal Ridge did not, however, manifest its assent to the arbitration
provision, the only provision embedded within the contract that had signature lines for both
parties. Construing this contract against the drafter, Royal Ridge fails to convince us that
the circuit court committed reversible error.
Affirmed.
HARRISON and BROWN, JJ., agree.
4 Bradley D. Hull, for appellant.
Robertson, Beasley, Shipley & Robinson, PLLC, by: Christopher J. Hooks, for appellee.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2025 Ark. App. 528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-ridge-construction-llc-v-jo-lynn-spradlin-arkctapp-2025.