Royal Indemnity Co. v. State Ex Rel. Standard Sanitary Manufacturing Co.

166 N.E. 361, 120 Ohio St. 378, 120 Ohio St. (N.S.) 378, 7 Ohio Law. Abs. 271, 1929 Ohio LEXIS 349
CourtOhio Supreme Court
DecidedApril 24, 1929
Docket21578
StatusPublished
Cited by4 cases

This text of 166 N.E. 361 (Royal Indemnity Co. v. State Ex Rel. Standard Sanitary Manufacturing Co.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royal Indemnity Co. v. State Ex Rel. Standard Sanitary Manufacturing Co., 166 N.E. 361, 120 Ohio St. 378, 120 Ohio St. (N.S.) 378, 7 Ohio Law. Abs. 271, 1929 Ohio LEXIS 349 (Ohio 1929).

Opinion

Marshall, C. J.

The constitutional question presented relates to portions of Sections 2316 and 2365-1, General Code. The former section was enacted March 20, 1917 (107 Ohio Laws, 454), and states: “Such bond shall also be conditioned for the payment of all material and labor furnished for or used in the construction for which such contract is made. The bond may be enforced against the person, persons or company executing such bond, by any claimant for labor and material, and suit may be brought on such bond in the name of the state of Ohio on relation of' the claimant within one year from the date of delivering or furnishing such labor or material, in the court of common pleas of the county wherein such labor or material was furnished or delivered,” etc. That section applies only to public buildings erected by the state.

Section 2365-1 was enacted on March 21, 1917 (107 Ohio Laws, 642), one day later than the former statute,'and in its pertinent parts provides: “With an additional obligation for the payment by the con *382 tractor, and by all sub-contractors, for all labor performed or materials furnished in the construction, erection, alteration or repair of such building, works or improvements.” That section applies to public buildings erected by the state or any political subdivision of the state. Both sections, therefore, apply to the present controversy, and they are so similar in their provisions that either statute would be sufficient for the present case without the other. It is claimed that these laws, in requiring contractors to furnish bond for the payment of claims of sub-contractors, laborers, and materialmen, impair the obligation of contracts, and therefore violate Section 28, Article II of the Ohio Constitution. It is further claimed that they abridge the privileges and immunities of citizens, and are a limitation upon the freedom of contract, and that they therefore violate the provisions of the Fourteenth Amendment to the federal constitution.

Although those statutes have been in existence twelve years, their constitutional validity has never before been argued in this court. Bonds with such conditions have been employed in public construction in a multitude of instances, and they have been enforced in the courts of this state in a very large number of cases. A number of cases have been decided by this court treating those provisions in the statutes as valid, and they have been enforced on that theory without any argument to the contrary.

The first of these cases is Royal Indemnity Co. v. Day & Maddock Co., 114 Ohio St., 58, 150 N. E., 426, 44 A. L. R., 374, decided in 1926. In 1927 the case of Southern Surety Co. v. Schmidt, 117 Ohio St., 29, 158 N. E., 1, was decided. Later in the same *383 year, Southern Surety Co. v. Standard Slag Co., 117 Ohio St., 512, 159 N. E., 559, again enforced a bond in favor of materialmen. Three cases have been decided by this court affirming recovery on the part of materialmen and subcontractors where the statutes were not in all respects complied with. In Southern Surety Co. v. Chambers, 115 Ohio St., 434, 154 N. E., 786, the condition was not written in the sub-contractor’s bond, but the advertisement for bids required a bond to be furnished in full compliance with the statute. It was held in that case that under such circumstances the provisions of the statute will be read into the bond.

In American Guaranty Co. v. Cliff Wood Coal & Supply Co., 115 Ohio St., 524, 155 N. E., 127, it was again held that materialmen and sub-contractors may avail themselves of the security of the bond, although they are not expressly named therein. In that case >the condition of the bond was that the obligee should be indemnified against loss or damage arising from the failure of the principal to perform his contract without any express provision in favor of materialmen. In that case the bid bond fully complied with the statute. The only difficulty was that in executing the contractor’s bond there was a failure to insert the statutory condition. It was held that the bid bond was a part of the contract, and therefore a part of the contractor’s obligation, and therefore a part of the surety company’s obligation.

In American Guaranty Co. v. Cincinnati Iron & Steel Co., 115 Ohio St., 626, 155 N. E., 389, an additional question was argued and decided, viz., the right of a materialman furnishing materials to a *384 sub-contractor and who therefore had no direct contractual relation with the principal contractor. In that respect the case is similar to the instant case.

In the three cases last named the statutory conditions were read into the bonds, although not expressly recited therein, on the principle that, the statute having required such a bond to be given, the contractor and the surety company must have contracted in relation to the statutes, and will be held responsible as though the statute had been fully complied with. This court has, therefore, in seven different cases recognized the validity of these statutes without expressly so declaring.

Similar provisions are found in the statutes of other states of the Union, and, so far as we are able to discover, have been uniformly upheld. If there have been any cases decided in other jurisdictions declaring such provisions to be unconstitutional, they have not been brought to our attention. Certain cases from other jurisdictions have been cited in this case as authorities, placing limitations upon the right of a legislature to hold the owner of property chargeable with mechanics’ liens for labor and materials furnished, where the contract was not made with the owner. It is not necessary to look to other jurisdictions for a decision upon that principle. This was so decided in Palmer & Crawford v. Tingle, 55 Ohio St., 423, 45 N. E., 313. Where an owner contracts with a contractor for the erection of a building at a given price, it becomes an impairment of that contract to permit liens to be established against the property of the owner as the result of a contract to which he was not a party, and where the liens increase the contract cost of the *385 building. On the other hand, when an owner enters into a contract with a builder, and the owner feels a moral responsibility for the payment of all materials and. labor entering into the building, and accordingly stipulates in the contract that the contractor shall pay the entire cost, it places that responsibility upon the contractor himself, and he can only discharge that contract by making full payment. When he gives a bond, he is only assuring the fulfillment of his contract, and the surety company becomes liable for that for which the contractor was already liable. A private owner is fully justified in making such a contract in order to prevent his property from becoming incumbered by liens, whether valid or not. A public owner is justified, because in this state mechanics’ liens cannot attach to public ownership.

The decision in the case of Palmer & Crawford v. Tingle, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carlin v. Reminderville
2025 Ohio 1435 (Ohio Court of Appeals, 2025)
Mountaineer Euclid, Inc. v. Western Casualty & Surety Co.
250 N.E.2d 768 (Ohio Court of Appeals, 1969)
J. T. Weybrecht's Sons Co. v. Hartford Accident & Indemnity Co.
161 Ohio St. (N.S.) 436 (Ohio Supreme Court, 1954)
Manhattan Terrazzo Brass Strip Co. v. A. Benzing & Sons
50 N.E.2d 570 (Ohio Court of Appeals, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
166 N.E. 361, 120 Ohio St. 378, 120 Ohio St. (N.S.) 378, 7 Ohio Law. Abs. 271, 1929 Ohio LEXIS 349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-indemnity-co-v-state-ex-rel-standard-sanitary-manufacturing-co-ohio-1929.