Roy v. Boteler

40 Mo. App. 213, 1890 Mo. App. LEXIS 483
CourtMissouri Court of Appeals
DecidedMarch 31, 1890
StatusPublished
Cited by12 cases

This text of 40 Mo. App. 213 (Roy v. Boteler) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roy v. Boteler, 40 Mo. App. 213, 1890 Mo. App. LEXIS 483 (Mo. Ct. App. 1890).

Opinion

Smith, P. J.

This was a suit, brought on a builder’s contract, to enforce a mechanic’s lien for balance claimed to be due thereon. The petition, amongst other allegations, contained the following, to-wit:

Plaintiff complains of defendant, and for his cause of action states, that defendant is and at all times hereinafter mentioned has been the owner of a tract or parcel of land in the city of St. Joseph, county of Buchanan and state of Missouri, known and designated as lots 1, 2, 3 and 4, in block 3, in Wilson’s addition to. the city of St. Joseph aforesaid ; that about the eighth day of August, 1887, the plaintiff and defendant entered into a contract by written articles of agreement, whereby the plaintiff covenanted, promised and agreed to and with the defendant to make, erect and finish, in a good, substantial and workmanlike manner, on the parcel of ground above described, a large two-story, double-brick tenement dwelling house, which has since its erection been known as Dr. Boteler’s flats, by furnishing all the material and doing all the work therefor, except the brick work, brick material, painting and glazing; that [218]*218is to say, plaintiff was to do all the carpenter work and furnish the materials therefor agreeable to the drawings and specifications provided for said work, to the satisfaction and under the direction of Messrs. Eckel & Mann, or either of them, who were the architects of defendant’s said building, and whose approval of plaintiff’s said work was to be testified by a writing or certificate under the hand of them, or either of them, all of which plaintiff agreed to ,do for the sum of thirty-two hundred dollars ($3,200), which sum the defendant then and there and by 'the contract aforesaid promised and agreed to pay plaintiff, in consideration of the performance of said contract on his part thereafter to be made. And plaintiff further states that he has duly kept and performed all the promises, covenants and agreements in said contract contained, on his part, to the satisfaction and under the direction of said architects.

The answer was a general denial, at the trial, the plaintiff introduced in evidence the builder’s contract, which, amongst others, contained the following provisions, to-wit:

First. The said party of the second part does hereby, for himself, his heirs, executors and administrators, covenant, promise and agree to and with the said party of the first part, or his executors, administrators or assigns, that W. R. Roy, the said party of the second part, or his executors or administrators, shall and will, for the consideration hereinafter mentioned, without any unnecessary delay, and as soon as ordered, so make, erect, build and finish in a good, substantial and workmanlike manner, on the vacant lot situate on northeast corner of Thirteenth and Edmond streets in St. Joseph, Missouri, a certain job of carpenters’ and joiners’ work for a new brick building, containing four flats, to be built by the said party of the first part on the place aforesaid, and all to be agreeable [219]*219to the drawings and specification signed- by the said parties and hereunto annexed, to the satisfaction and under the direction of Eckel & Mann, to be testified by a writing or certificate under the hand of the said .Eckel & Mann, and also shall and will find and provide such good, proper and sufficient materials, of all'kinds whatsoever, as shall be proper and sufficient for the completing and finishing all the carpenter and joiner’s work as specified and mentioned in the specifications, for the sum of thirty-two hundred dollars ($3,200). Payments to be made as the work progresses, every two weeks, on the estimate of the architects, of which eighty-five per cent, is paid to contractor; balance, fifteen per cent., to be paid with final payment when the whole job is 'completed and accepted ; provided that in each of the said cases a certificate shall be first obtained by the said party of the second part, which certificate must be signed by the said architects, Eckel & Mann, and countersigned by the sureties. Sixth. Payments made on work during its .progress, on account of the contract or extra work, shall in no case be construed as an acceptance of the work executed ; but the contractors shall be liable to all the conditions of the contract, until the work is finished, completed and finally accepted by the architects, Eckel •& Mann.

The plaintiff, to show performance, introduced the following statement, to-wit:

“St. Joseph, Mo., January 15, 1888.

“Hr. W. C. Boteler bought of Wm. R. Roy, Contractor and Builder, August 8, 1887:

To contract on flats..........................$3,200.00

To extra on front roof, 6 pieces 2x10-20........................$ 2 50

To 80 feet flooring............... 1 75

To 2} days’ labor, $7.50; nails, 25 cts. 7 75 12 00

[220]*220To extra on main room, 1 door, lock & frame......................$ 7 00

To 1 window frame, sash and casing 7 00

To 72 feet inside base.............. 2 88

To 14 pieces 2x4-16, $2.80; 2 pair door casings, $2.50____■........ 5 30

To 4 days’ work, $3.25, ,$13.00; nails, 50 cts......................... 13 50

To 24 lbs. window weights......... 32. 36 00

To extra work — changing front steps To paneling front vestibule, 90 hours work, at 30 cts................$ 27 00 5 00

To nails and moulding............. 1 00

To 200 feet clear poplar lumber, at $3.50.........................1 7 00 35 00

To 2 closets on back porch, 2 days’ work.........................$ 6 00

To 100 feet lumber, -at $3.00; locks and hinges.....:............. 4 00 10 00

To 80 feet flooring No. 2 bds, $1.60; 7 feet flooring $1.90, used in wood work................... 3 50

$3,301 50

Or.

By cash..........................$2,860 96

Amount paid for inside blinds...... 90 00

Amount paid for picture moulding 13 75

Four drain boards left out of house 4 00

Changing sliding door to folding doors......................... 5 00

Difference in width of back porch.. 3 00 2,976 71

“Balance due $324 79”

[221]*221The plaintiff then introduced, as a witness, the architect Eckel, who testified that the statement was made and certified, in the form presented, at the request of defendant, at the time the work was completed, or about completed; that the work was done under the direction and to the satisfaction of said architects, in accordance with the contract; that eighty-five per cent, was paid by defendant on the work as it progressed, on estimates made by the architects, and at the final wind up, an estimate, already alluded to, was made of the balance due; that after the house was completed it was inspected by the architect.

The defendant objected to this evidence, on the ground, (1) that the contract provided that in every case, when payment was to be made under the contract! including final payment, a certificate should first be obtained by plaintiff, signed by Eckel &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iola Portland Cement Co. v. Ullmann
140 S.W. 620 (Missouri Court of Appeals, 1911)
Heidbrink v. Schaffner
127 S.W. 418 (Missouri Court of Appeals, 1910)
Johnson v. Dalrymple
123 S.W. 1020 (Missouri Court of Appeals, 1909)
W. H. Mullins Co. v. Jacob Freund Roofing Co.
5 Ohio N.P. (n.s.) 1 (Court of Common Pleas of Ohio, Hamilton County, 1907)
Burgess v. Mercantile Town Mutual Insurance
89 S.W. 568 (Missouri Court of Appeals, 1905)
Price v. Patrons' & Farmers' Home Protection Co.
77 Mo. App. 236 (Missouri Court of Appeals, 1898)
Nickell v. Phoenix Insurance
46 S.W. 435 (Supreme Court of Missouri, 1898)
Murphy v. North British & Mercantile Insurance
70 Mo. App. 78 (Missouri Court of Appeals, 1897)
McNees v. Southern Insurance
69 Mo. App. 232 (Missouri Court of Appeals, 1897)
Wilkinson v. Metropolitan Life Insurance
63 Mo. App. 404 (Missouri Court of Appeals, 1895)
McCullough v. Phœnix Insurance
21 S.W. 207 (Supreme Court of Missouri, 1893)
St. Joseph Iron Co. v. H. K. Halverson & Co.
48 Mo. App. 383 (Missouri Court of Appeals, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
40 Mo. App. 213, 1890 Mo. App. LEXIS 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roy-v-boteler-moctapp-1890.