Rowe v. Harris

576 S.W.2d 172, 1979 Tex. App. LEXIS 3445
CourtCourt of Appeals of Texas
DecidedJanuary 11, 1979
DocketNo. 5884
StatusPublished
Cited by3 cases

This text of 576 S.W.2d 172 (Rowe v. Harris) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowe v. Harris, 576 S.W.2d 172, 1979 Tex. App. LEXIS 3445 (Tex. Ct. App. 1979).

Opinion

OPINION

JAMES, Justice.

This is an appeal by the plaintiff from an instructed verdict in favor of defendant. We reverse and remand.

Plaintiff-Appellant John D. Rowe brought this suit against Defendant-Appel-lee J. Gordon S. Harris based upon a written construction contract, alleging that Harris had breached said written contract to Plaintiff Rowe’s damage in the amount of $6479.77; and in the alternative that Harris was liable to Rowe under Sections 17.46 and 17.50 of the Business and Commerce Code (commonly called the Texas Deceptive Trade Practices Act) for certain alleged deceptive trade practices and that Harris was thereby liable for treble damages and reasonable attorney’s fees.

Harris pleaded by way of defense that Rowe and Harris had reached an accord and satisfaction concerning the complaints made by Rowe, and in addition that the original contract had merged into the warranty deed executed and delivered by Harris to Rowe on July 7, 1976.

Trial was had to a jury, and after both sides had rested, the Defendant Harris moved for an instructed verdict, which motion was granted. Thereupon the trial court entered judgment that Plaintiff Rowe take nothing, from which judgment Plaintiff Rowe appeals.

On February 25, 1976, Rowe entered into a written contract with Harris wherein Harris agreed to build a home for Rowe in accordance with certain plans and specifications, for which Rowe agreed to pay Harris $96,760.00. Under the contract Harris was allowed 180 days from beginning of construction in which to complete same. Since construction actually began on March 12, 1976, Harris therefore had until on or about September 8, 1976, in which to complete performance, under the terms of the contract.

After construction was under way, Rowe asked Harris if an earlier move-in date [174]*174could be arranged. Harris preferred not to rush completion too much; however, at first Harris told Rowe that he might get the house completed by June 10, 1976. Later on, Harris told him that June 10th would be too early but that Rowe could move into the home by July 10, 1976.

Therefore, the parties set up a closing date for July 7, 1976. At this last-named date there were certain items of construction that had not been completed. Rowe was in a hurry to move into the place because he had already sold his then-existing home and had agreed to give up possession thereof. Harris agreed to go ahead and close, with the understanding that he would finish up the incomplete items within 30 days after closing. On July 7, 1976, the parties entered into a written agreement called “Escrow Agreement,” the pertinent parts of which read as follows:

“ESCROW AGREEMENT
* * * # * *
“It is agreed by the undersigned parties to this transaction that the sum of $775.00 will be held in escrow by said Southwest Land Title Co., and the remainder of the proceeds, if any, are to be disbursed at this time. The funds escrowed hereunder are to be held in the amounts and until the following has been accomplished, to-wit:
$500.00 for items included on the attached list
200.00 for repair of the fireplace mantel
75.00 for repair of front door
$775.00 Total
“Southwest Land Title Co. is authorized to hold said deposit in escrow until the purpose of this agreement has been complied with at which time the deposit will be paid to J. Gordon S. Harris provided said Southwest Land Title Co. has received written approval of such payment from all parties to this agreement.
“In the event said written approval has not been received on or before 30 days from this date, then, a representative of Southwest Land Title Co. shall have access to said property to make inspection of same, and will be authorized to make disbursement after the above mentioned work has been completed.
“No liability or expense shall accrue against Southwest Land Title Co. by virtue of said company acting as escrow agent.”
******
Attached to the “Escrow Agreement” and being a part thereof is a sheet containing Rowe’s handwriting, which sheet was initialled by both Rowe and Harris, and which reads as follows:
“The amount of $500.00 will be put in escrow and remain for 30 days for following work to be completed. At end of 30 days any work not completed to owners satisfaction will be considered not completed and payment allocated for those items will be paid to John D. Rowe.
$150.00 1. Complete all paint, patching, touch-up finishing of cabinets, shelves, cleaning of F/place, brushing all cedar.
$150.00 2. Install vents, replace all cedar stripping under doors, repair facer board over family room, replace ft. door knob, patio knob, replace board on side patio.
$100.00 3. Complete yard work.
$100.00 4. Repair driveway.
$500.00
$200.00 5. Repair or replace mantel.
$ 75.00 6. Repair or replace ft. door trim & paint.
$775.00 Total.
John R.
C. R.
J. H.”

The closing which took place on July 7, 1976, was handled by the Southwest Land Title Co. At said closing Harris executed and delivered a warranty deed of the subject house and lot to Rowe, for which Rowe paid Harris $95,985.00, same being the agreed purchase price of $96,760 less $775.00 held back by the title company in accordance with the “escrow agreement.” The title company has ever since held this money in escrow, and has never released same to either Rowe or Harris.

After the closing and after Rowe moved into the house in question, Harris made some efforts to complete the items set out in the escrow agreement; however, it is [175]*175undisputed that Harris never completed the items listed in said escrow agreement, within the thirty days or at any time thereafter. A few days before the 30 days (after closing) had expired, Rowe contacted the title company and requested that the $775.00 be paid to him (Rowe); however, the title company took no action and did not pay the money to either Rowe or Harris. The title company was never made a party to this suit, and from the record still holds the $775.00 in escrow.

Although Harris admits that he did not complete the items set out in the escrow agreement, Harris never tendered the $775.00 to Rowe, with this possible exception: After such sides had rested, and the testimony had been concluded, the parties entered into the following “stipulation”:

(By Counsel for Defendant Harris):

“Well, further, the Defendant Harris, and the Plaintiff Rowe would stipulate that in the event the Plaintiff Rowe does not recover judgment in this case, the Defendant Harris would stipulate that the funds now on deposit with the Southwest Land Title Co. in escrow in the amount of $775.00 will be refunded to the Plaintiff Rowe, and the Defendant Harris will execute all instruments necessary for the refund.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelton v. Swift Motors, Inc.
674 S.W.2d 337 (Court of Appeals of Texas, 1984)
Harris v. Rowe
593 S.W.2d 303 (Texas Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
576 S.W.2d 172, 1979 Tex. App. LEXIS 3445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowe-v-harris-texapp-1979.