Rowan v. Harris

532 F. Supp. 969, 1982 U.S. Dist. LEXIS 10853
CourtDistrict Court, E.D. Louisiana
DecidedFebruary 26, 1982
DocketCiv. A. No. 78-1602
StatusPublished

This text of 532 F. Supp. 969 (Rowan v. Harris) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowan v. Harris, 532 F. Supp. 969, 1982 U.S. Dist. LEXIS 10853 (E.D. La. 1982).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

BEER, District Judge.

To the extent any of the following findings of fact constitute conclusions of law, they are adopted as such. To the extent any conclusions of law constitute findings of fact, they are so adopted.

Findings of Fact

1. Plaintiffs in this action are A. L. Rowan and Robert L. Rowan, individually and as partners in A. L. Rowan & Son, General Contractors, a Louisiana partnership.

2. Defendant in this action is the Department of Housing and Urban Development (hereinafter referred to as “HUD”), an agency of the United States Government.

3. A. L. Rowan & Son (hereinafter referred to as “Rowan”) was the general contractor for the Pontchartrain Union Apartments, a 56-unit housing project located in Gretna, Louisiana. Rowan’s contract was with Pontchartrain Union, a non-profit organization, as owner. Charles E. Curry Company, Inc. was the mortgagee for the construction project, and HUD insured the mortgage under the National Housing Act, 12 U.S.C. §§ 1701-1750g. Although HUD was not a party to the building contract, under the provisions of the Act, HUD controlled the payment of contract funds through its inspections and supervision of the project. HUD became further involved in the construction project when Pontchartrain Union defaulted on the mortgage. Curry exercised its option under the National Housing Act and assigned the note and the mortgage securing the note to HUD.

4. The construction contract between Rowan and Pontchartrain Union was signed on April 29, 1971, and the contemplated date of completion of the project was April 1, 1972. The project, however, was not substantially completed until June 18, 1973, at which time HUD approved the issuance of a certificate of substantial completion.

5. Upon issuance of the certificate of substantial completion, plaintiffs demanded from HUD the retainage withheld on the construction contract. HUD refused to pay the retainage, however, because there was no cost certification by the original mortgagor, Pontchartrain Union, as required by the contract. In a previously filed action, Rowan sued HUD to recover this retainage of more than $92,000. In summary judgment proceedings, the court awarded Rowan $94,092.29, representing the retainage plus interest. A. L. Rowan & Son, General Contractors, Inc., et al. v. Charles F. Curry Company, Inc., et al, Civil Action No. 75-3807 (E.D.La. Sept. 27, 1977).

6. Prior to the signing of the building contract in April 1971, Rowan met with various HUD employees. In spite of Rowan’s alleged request for assurances that all payments would be promptly made before the tenth of each month and that cost overruns would be paid, the contract includes none of these provisions. Nevertheless, the contract was executed and Rowan commenced work on the project.

7. As evidenced by HUD inspection reports, inspections were performed beginning in mid-May 1971, and continued through May 1973. These inspections were performed almost entirely by one HUD em[971]*971ployee, Charles M. Rodi. Mr. Rodi, a HUD witness, testified that he had no recollection of these inspections independent from the reports. The visits to the project site were consistent and frequent; a total of 37 inspections were performed during this two-year period.

8. Prom the very beginning Rowan encountered problems with the Pontchartrain project. Just about two months into the project, in mid-August, 1971, progress on the job was reported as slow. A city-wide concrete strike, which was to last about forty-five days, forced a work stoppage on the project. Several days work was lost due to unusually heavy rains.

9. At the same time, however, Rowan encountered problems that resulted, either directly or indirectly, from Rowan’s own actions. One such recurring problem was HUD’s rejection of Rowan’s requests for monetary draws due to Rowan’s repeated failure to justify the amount of money requested on the basis of completed work. Although HUD advised Rowan that proper substantiation of the requests was critical to the payment of construction funds, in one instance, Rowan’s unjustified requests resulted in a delay in payment of almost three months.

10. The inspection reports also reveal that corrections were required in many cases to bring work already completed on the project up to HUD standards.

11. In August 1972, the HUD inspection revealed a lack of supervision on the job. Later that month, a shortage of workers resulted in an unsatisfactory slow rate of progress. This shortage of workers continued through October.

12. In November 1972, although plumbers and metalworkers were at work on the project, other crafts left the job and refused to return until they were paid. Later, in December 1972, the job was closed down after a period of virtually no activity since the beginning of November.

13. In an attempt to get the project moving and completed, Carl Geyer, HUD’s Assistant Director of Technical Services, met with Rowan and the various subcontractors. As a result of the meeting, the mortgage on the project was increased by $66,000, the time for completion of the project was extended, and reserve funds necessary for completion were restored. A. L. Rowan testified that the only reason he resumed work on the project was because he had been assured by Geyer at this meeting that the cost overruns incurred by Rowan would be paid at the completion of the project. Carl Geyer testified that he did not make any representations to Rowan that cost overruns would be approved. Geyer further testified that he was not authorized to make such representations because he was subject to a HUD policy directive that prohibited payment of cost overruns. No written agreement was ever entered into concerning the cost overruns. I do not find that HUD, through Geyer, approved cost overruns.

14. Because Rowan lacked the funds to complete the project, Rowan obtained a loan from the Ouachita Bank in Monroe, Louisiana, using the project as security. Because some of the subcontractors would not return to work until they received payment for completed work, Rowan used the loan funds to pay these subcontractors.

15. In March 1973, there was once again a reported problem with the request for payment submitted to HUD. Intermittent periods of no work activity occurred throughout the remainder of the project.

16. The worker shortages and the slow progress on the Pontchartrain project noted during the frequent HUD inspections were the symptoms of much more pervasive troubles affecting Rowan’s business. When Rowan first started the Pontchartrain project, the partnership was still heavily financially committed to the completion of a large turnkey project in Breaux Bridge, Louisiana. The contract price of the 100-unit Breaux Bridge project was $1.2 million and was much larger than any of the small home and church construction projects Rowan had undertaken previously. By undertaking the 56-unit, $833,000 Pontchartrain project while still committed to the [972]*972Breaux Bridge project, Rowan overextended its capabilities.

17. James F. Pinner, a C.P.A. called by plaintiff as a financial expert, testified that the Rowan partnership was very thinly capitalized. Rowan’s capital remained approximately $50,000 to $60,000 while the partnership continued to take on more and more jobs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liberto v. Villard
386 So. 2d 930 (Louisiana Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
532 F. Supp. 969, 1982 U.S. Dist. LEXIS 10853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowan-v-harris-laed-1982.