Rowan Companies v. Transco Exploration Co.

679 S.W.2d 660, 1984 Tex. App. LEXIS 6292
CourtCourt of Appeals of Texas
DecidedSeptember 20, 1984
Docket01-84-0082-CV
StatusPublished
Cited by9 cases

This text of 679 S.W.2d 660 (Rowan Companies v. Transco Exploration Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowan Companies v. Transco Exploration Co., 679 S.W.2d 660, 1984 Tex. App. LEXIS 6292 (Tex. Ct. App. 1984).

Opinion

OPINION

COHEN, Justice.

This is a breach of contract suit brought by Rowan against Transco, which resulted in a take nothing judgment for the defendant, Transco.

In 1976, Rowan agreed to furnish an offshore oil rig and crew to Transco to drill two oil wells in the Gulf of Mexico. On *662 September 20, 1977, a blowout and fire occurred on the rig, the Rowan-Odessa, during drilling of the second well. The fire burned until October 6, 1977, and the rig remained at the site and was used to plug and abandon the second well until November 24, 1977, when it was towed away for repairs, which continued until June 26, 1978. On January 26, 1978, Transco gave written notice to Rowan claiming a right to terminate the contract as of January 31, 1978, pursuant to the force majeure clause of the contract.

Rowan then brought this suit claiming more than $3.8 million for Transco’s failure to pay amounts due under the repair rate clause of the contract between November 24, 1977, and June 26, 1978, plus contractual pre-judgment interest at 12% per year and attorney’s fees.

Transco answered with a general denial and affirmative defenses of abandonment of the contract, recission of the contract, novation, and estoppel. Transco specifically denied that the repair rate of $17,865 per day was applicable. It alleged that the force majeure rate of $17,865 per day applied only up to the date of termination, and that Rowan could not recover even that, according to Transco’s pleadings, because Rowan never gave written notice of the force majeure to Transco, as required in the force majeure clause.

The jury found that the cause of the blowout and fire was beyond Transco’s reasonable control; that Transco was not negligent in failing to place a 5½" liner through the 14,600' gas sand; and that Transco’s decision to continue drilling to 15,500' was not negligent, thus exonerating Transco from all accusations of negligence.

The jury found against Transco on all of its affirmative defenses.

The jury found that it was reasonable to repair the Rowan-Odessa and that Rowan used reasonable diligence in completing repairs by June 26, 1978.

The jury further found that the parties did not intend, when they executed the contract, that, in the event of any one instance of repair, the operating rate ($18,-365 per day) would be payable for the first twelve hours and the repair rate ($17,865 per day) would be payable for the rest of the time required for repairs. Rowan had argued that the contract unambiguously provided, as a matter of law, that the repair rate should apply during the entire period, but, if the repair rate clause was ambiguous, then the parties intended that the higher operating rate apply for the first twelve hours and the repair rate thereafter. The jury’s answer to this issue was, therefore, adverse to Rowan.

Rowan’s points of error 1, 2 and 3 contend that the contract unambiguously provided, as a matter of law, that Rowan was entitled to collect the repair rate of $17,865 per day from November 24, 1977, until June 26, 1978; and, even if the repair rate clause was ambiguous, the evidence established, as a matter of law, that the parties intended for the repair rate to be payable during this period, and that the jury’s finding that the parties did not so intend was against the great weight and preponderance of the evidence.

The first issue for decision is which of several daily contract rates in the contract applies and for what period of time. Rowan contends that the “repair rate” of $17,-865 a day should be payable throughout the entire period of November 24, 1977, to June 26, 1978. Rowan specifically denied in its pleadings that an event of force maj-eure had occurred; consequently, according to Rowan, the force majeure clause did not apply. The force majeure daily rate was the same as the daily repair rate, $17,-865; however, the vital difference between the two clauses affecting the amount of damages was that the force majeure clause, quoted below, provided for termination upon five days notice, unlike the repair rate clause, which had no termination provision.

Transco asserted that a force majeure event had occurred and that, pursuant to its notice of January 26, 1978, any liability it may have had thereunder ended five days later on January 31, 1978.

*663 The repair rate clause, which was relied upon by the plaintiff, Rowan, provided:

The repair rate will be payable in the event operations are suspended on account of breakdown, maintenance or repair of contractor’s equipment (as distinguished from routine inspection, lubrication, change of pump liners, repacking swivel, slipping of drilling line, etc.) during the period in excess of twelve (12) continuous hours in any one instance, up to a maximum of seventy-two (72) hours accumulated repair time at the operating rate during any thirty (30) day period.

The force majeure clause, upon which the defendant, Transco, relied, provided:

14. Neither party hereto shall be liable, other than to make payments due hereunder, including Force Majeure rate provided for in schedule “A” (6) which shall be applicable during periods of Force Majeure for failure to perform the terms of this agreement when performance is hindered or prevented by strikes, lockouts, riots, war (declared or undeclared), acts of God, insurrections, fire, storm, interference of any governmental authority, inability to obtain critical materials including drill pipe and bits, or other cause beyond a reasonable control of such party, whether or not similar to the causes herein specified. In case either party hereto shall be unable, wholly or in part, because of such cause of Force Majeure, to carry out its obligations under this agreement, it shall promptly give written notice to that effect to the other party, stating the particulars of such Force Majeure, and such party shall also give written notice to the other party of the termination of such conditions. The performance of any obligation or obligations suspended while Force Majeure is operative, shall be resumed as soon as reasonably possible after the termination thereof, and the time of such suspension shall not be considered as time expended for the performance of any obligations under the provisions of this agreement. Should any act of Force Majeure causing the suspension of operations hereunder continue for a period of thirty days or more, either party shall have the right to terminate this agreement by giving the other party written notice five (5) days in advance of the date of termination subject to payments due .... (emphasis added)

Schedule A to the contract was entitled “Rates of Payment to Contractor”, Rowan, and its paragraph 6, entitled “Force Maj-eure Rate”, provided:

The Force Majeure rate, ($17,865 per day) will be payable during periods when conditions defined in Articles 10 and 14 occur. 1 If during such periods less than full crews are utilized, appropriate costs of such reduced labor and payroll burden shall be deducted from the daily rate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TEC Olmos, LLC v. ConocoPhillips Co.
555 S.W.3d 176 (Court of Appeals of Texas, 2018)
Bowen v. Robinson
227 S.W.3d 86 (Court of Appeals of Texas, 2006)
GT & MC, INC. v. Texas City Refining, Inc.
822 S.W.2d 252 (Court of Appeals of Texas, 1991)
Ppg Industries, Inc. v. Shell Oil Company
919 F.2d 17 (Fifth Circuit, 1990)
Kodiak 1981 Drill v. Delhi Gas Pipeline
736 S.W.2d 715 (Court of Appeals of Texas, 1987)
Kodiak 1981 Drilling Partnership v. Delhi Gas Pipeline Corp.
736 S.W.2d 711 (Court of Appeals of Texas, 1987)
Gulftide Gas Corp. v. Cox
699 S.W.2d 239 (Court of Appeals of Texas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
679 S.W.2d 660, 1984 Tex. App. LEXIS 6292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowan-companies-v-transco-exploration-co-texapp-1984.