Routt v. Dils

40 Colo. 50
CourtSupreme Court of Colorado
DecidedApril 15, 1907
DocketNo. 5178; No. 2782 C. A.
StatusPublished
Cited by1 cases

This text of 40 Colo. 50 (Routt v. Dils) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Routt v. Dils, 40 Colo. 50 (Colo. 1907).

Opinion

Mr. Justice Maxwell

delivered the opinion of the court:

Appellant Boutt entered into a written contract with appellee, Dils, to furnish stone ¿nd other materials, and to do the stone work in the erection of a dwelling house, for the stipuláted sum of $2,500.00, of which amount $1,000.00 was to be paid 'and was paid in advance; the balance to be paid from time to time as the work progressed. ’ .

To insure the performance of the contract, a bond was executed with Boutt as principal, The National Surety Company as surety, and Dils as obligee.

The.work was to be completed November 17th, and in default thereof Boutt was to pay Dils $2.00 per day as liquidated damages.

November 17, 1900, the dwelling being far from completion, through the inability of Boutt to secure the- stone required by the contract, he proposed 'to Dils to substitute granite for the stone required by the contract, and with such material complete 'the dwelling.

[52]*52November 19, 1900, tbe resident manager of tbe surety company was informed by Dils that Routt had failed to complete his contract within'the stipulated time, and he was requested to notify the company of that fact, and also to submit to the company the proposed change in the stone to be used for its assent to such change,, such assent being required by one of the provisions of the bond limiting the liability of the surety company. By letter dated November 21, 1900, the resident manager advised the home office of the surety company of Routt’s failure to°complete the contract within the stipulated time, and also of the proposed change in the contract, which letter was received at the home office of the company November 24,1900. The company assented to the proposed change, and negotiations between Routt and Dils progressed towards a consummation of the change until December 1, 1900, when Routt abandoned the contract and notified Dils, who on the same day, by registered mail addressed to the surety company at its home office, notified the company of Routt’s abandonment of the contract, and requested it, in accordance with the terms of the bond, to complete the contract. This notice was received at the home office of the company December 4, 1900. The company declined to complete the contract, repudiated any obligation upon its part under the bond, upon the ground that notice to it of Routt’s abandonment of the contract came too late. January 5, 1901, appellee, as plaintiff, filed his complaint in the court .below against appellants, wherein, by apt averments, he alleged a breach of the conditions of the bond, and laid his damages by reason thereof at the sum of $1,900.00.'

The evidence introduced by appellee established the facts above set forth, and the further fact that the value of the work and materials furnished by [53]*53Routt under the contract amounted to $500.00 or $600.00. It also appeared from the testimony of appellee, that after the institution of this suit he adopted other plans and specifications and completed the dwelling upon the foundation erected by Routt.

Appellants introduced no evidence.

The court instructed the jury to return a verdict in favor of plaintiff, and against both of the defendants, and to assess plaintiff’s damages in such sum as they should find from the evidence to be the difference between the sum of $1,000.00, the amount paid by Dils upon the contract, and the value of the work done by the defendant Routt upon the premises under the terms of his contract.

The verdict and judgment were ’for $500.00.

The argument of defendants is divided into two heads: 1st, the liability of Routt; 2nd, the liability of the surety company.

1. The argument as to the liability of Routt proceeds upon the erroneous assumption, that the action is based upon an express contract between appellee and Routt to build a stone house, and seeks to recover damages by reason of the breach of such contract; that the evidence shows an abandonment by appellee of the contract alleged in the complaint, and the completion of the dwelling according to different plans and specifications; that by the instruction to the jury appellee was allowed to recover upon an implied promise by Routt to return to appellee whatever balance of the money may have been in his hands belonging to appellee when the contract was mutually abandoned by both parties, and it is insisted that under the pleadings and proof, no liability against Routt was established except possibly for nominal damages, from which it follows that if Routt is not liable the surety company is discharged.

The argument and numerous authorities cited [54]*54in support thereof, are disposed of by the simple statement that the action is not against' Routt for breach of his contract to build a stone dwelling, but it is against both appellants, Routt as principal, and the surety company, as surety, upon a bond, the only difference between the liability of appellants arising by reason of certain conditions in the bond, usual in such instruments, limiting the liability of the surety.

It is true that appellee by pleading and proof undertook to recover the difference between what it would have cost to complete the dwelling according to the contract and the balance remaining unpaid the contractor, but the trial court correctly rejected this theory of the measure of damages, and limited the amount to he recovered by the instruction given to the jury.

2. As to the liability of the surety company, it is insisted that there was a failure upon the part of appellee to show such a compliance with the terms of the bond, as to the manner and time of giving notice of the default of Routt, as relieved the surety company of liability; that in any event the question was one for the jury to determine, and that there was error in arbitrarily instructing the jury to- return a verdict against the surety company.

The conditions of the bond material to a decision of this branch of the argument are:

‘ ‘ Whereas, the above bounden principal has entered into a certain contract with the above named obligee, copy of which contract is hereto attached and hereby referred to and- made a part hereof; and

“Whereas, by the terms of said contract, the above bounden principal covenants, undertakes and agrees,' among other things, to perform certain labor, to furnish certain materials and to protect and save the obligee and the property in said contract mentioned and described, free, clear, and harmless of. [55]*55and from all claims and liens on account of-any such labor and material:

“Now, therefore, if the above bounden principal shall well and truly perform such labor and furnish such materials, and shall protect and save the obligee and the property in said contract mentioned and described, free, clear, and harmless of and from all claims and liens on account of any such labor and material, then this obligation shall be null and void; otherwise, to be and remain in full force and effect. ’ ’

Then follow fifteen provisions limiting and defining the liability of the surety company, pertinent portions of which are as follows:

“3. If, at any time, the above named principal shall, in any manner, fail, neglect or refuse to keep, do or perform any matter or thing at the time and in the manner in said contract set forth and specified, to be by said principal kept, done or performed, the obligee shall immediately notify the.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diana Oil Co. v. Cayton
20 S.W.2d 108 (Court of Appeals of Texas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
40 Colo. 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/routt-v-dils-colo-1907.