Roussey v. Ernest W. Hahn, Inc.

251 Cal. App. 2d 251, 59 Cal. Rptr. 399, 1967 Cal. App. LEXIS 1966
CourtCalifornia Court of Appeal
DecidedMay 22, 1967
DocketCiv. 29628
StatusPublished
Cited by7 cases

This text of 251 Cal. App. 2d 251 (Roussey v. Ernest W. Hahn, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roussey v. Ernest W. Hahn, Inc., 251 Cal. App. 2d 251, 59 Cal. Rptr. 399, 1967 Cal. App. LEXIS 1966 (Cal. Ct. App. 1967).

Opinion

STEPHENS, J.

In 1959, R. H. Roussey and others were owners of a parcel of land in Oxnard, California. Defendant R. Leon Edgar & Associates, Inc. (Edgar) was engaged by plaintiffs to prepare plans and specifications for a building to be built on plaintiffs’ land. Edgar was to supervise that construction. Defendant Ernest W. Hahn, Ine. (Hahn) by contract was engaged by plaintiffs to construct the building. There was no contractual association between Edgar and *253 Hahn. As part of that construction, The Flintkote Company (Flintkote) furnished to Hahn certain roofing materials to be used by Hahn.

The building was completed by Hahn according to Edgar’s plans. Problems arose concerning the watertight integrity of the roof. Plaintiffs brought this action against Edgar, Flintkote, and Hahn for damages caused by the roofing defects.

The complaint was filed on June 3, 1964, and summons issued. Defendants Edgar and Flintkote were served on June 11, 1964. Flintkote filed its answer and a cross-complaint on July 23, 1964. Hahn did not file an answer though service of complaint had been duly made on June 15, 1964. On July 23, 1964—the same day that codefendant Edgar filed its answer— plaintiffs took Hahn’s default. On July 28, 1964, judgment was entered, as prayed, by minute order.

The service upon Hahn was made upon one Herman Maier, secretary and executive vice president of the corporation. He was the Hahn corporate officer upon whom all legal service normally was made. Following normal procedure, Maier conducted a preliminary investigation of the matter. Within 10 days of service, Maier determined that the complaints of defects and alleged damage were caused by structural design, not workmanship or material. He notified codefendant Edgar of his conclusions. By conversation, Maier informed Edgar that it appeared the liability was due to the Edgar design. Edgar told Maier to send the summons and complaint and Edgar would present them to their insurance company and have them ‘ ‘ take care ’ ’ of the matter.

Maier thus believed Edgar would have his insurance carrier settle the matter or answer the complaint on behalf of Hahn. Maier did not thereafter follow his normal procedure of forwarding the summons and complaint to Hahn’s insurance carrier or attorney, but rather sent them to Edgar. Edgar, however, did not “take care” of this matter on behalf of Hahn, but answered for itself only. On the same day Hahn’s default was entered, Edgar filed its answer denying plaintiffs’ allegations. Edgar also filed a cross-complaint against Hahn and Flintkote. Summons issued on the cross-complaint but was not served upon either cross-defendant. On January 28, 1965, a letter was sent to Hahn by plaintiffs’ attorney informing Hahn of the default judgment entered against them, and demanding payment in the amount of $5,782.70. This was the first notice Hahn had as to the default that had occurred. This letter was mailed six months and five days *254 after the entry of default; hence, the period provided for motion to vacate default judgment (Code Civ. Proc., § 473) had expired.

On February 23, 1965 (26 days after the letter was received and a full month after expiration of time to move for relief from default), Hahn filed a Notice of Motion to Vacate Default and Set Aside Judgment, along with proposed answers to plaintiffs' complaint and Edgar’s cross-complaint, plus cross-complaint against Edgar and others. This motion was denied. Hahn appeals.

In determining Hahn’s right to relief from default, the trial court concluded itself bound by Wattson v. Dillon (1936) 6 Cal.2d 33 [56 P.2d 220], 1 The court concluded facts of the Wattson case were indistinguishable from those before it in this case.

Hahn raises three issues on this appeal:

(1) “Did the Trial Court have discretion of Judgment in applying the facts of this case to the applicable law and fail to exercise that discretion ?
(2) “Are the facts of this ease distinguishable from the facts of ‘Wattson’1
(3) “Should the Appellate Court as a matter of justice and in accordance with the law governing relief from default vacate the default and set aside the default judgment entered?”

The Wattson case involved an action to vacate a final judgment. The trial court vacated the judgment but on appeal was reversed. The facts were: R. A. Wattson was under contract with the City of Los Angeles to construct certain street improvements. He sublet a portion of the work to the Hollywood Granite Company. Hollywood sublet a portion of the work to the Lewis Construction Company. Lewis negligently performed a portion of the work, resulting in injury to the property of the Dillons. The Dillons sued Wattson, Hollywood, and Lewis. Wattson was served on October 8, 1930. He immediately telephoned the agent of the bonding company indemnifying Hollywood, telling that agent that his company was looking to it to take care of the lawsuit. The agent advised that the complaint and summons should be sent to him, and promised that his company “would take care of it.” *255 Wattson, in compliance with this request, sent the complaint and summons to the bonding company. In a letter of transmittal, Wattson reviewed the telephone conversation, and concluded: “Please be advised that we look entirely to you for protection in this matter.”

On October 15, 1930, the bonding company acknowledged receipt of complaint, summons and letter of transmittal from Wattson. It further informed Wattson that the matter had been turned over to their claims department, and that the problem had been taken up with the Union Indemnity Company, the bonding company for Lewis Construction Company, and that “the latter company will handle this matter.” About a week or 10 days after October 8, 1930, Wattson talked with Lewis of the Lewis Construction Company and was informed by him that “the matter had been handled satisfactorily.” Still later, on October 21, 1930, Lewis informed Wattson that the matter had been attended to and that there was nothing further for Wattson to do.

As a result, Wattson made no appearance, and his default was taken in December 1930. Judgment against Wattson was entered in May of 1931 and a writ of execution levied in December of 1931. Upon the levy of execution, Wattson, for the first time, learned what had occurred. He immediately instituted an action to set aside the judgment. The Supreme Court held that under the facts (above set forth) Wattson was guilty of inexcusable neglect as a matter of law. The Supreme Court made it clear that the trial court made no finding indicating the existence of fraud, and that the basis of the motion by Wattson was solely mistake and accident.

The principles in a case such as that before us have been set forth in the case of Weitz v. Yankosky (1966) 63 Cal.2d 849 [48 Cal.Rptr. 620, 409 P.2d 700], 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bae v. T.D. Service Co. of Arizona
245 Cal. App. 4th 89 (California Court of Appeal, 2016)
Cruz v. Fagor America, Inc.
52 Cal. Rptr. 3d 862 (California Court of Appeal, 2007)
In Re Estate of Breard
84 Cal. Rptr. 2d 276 (California Court of Appeal, 1999)
Cables v. Beard
71 Cal. App. 4th 753 (California Court of Appeal, 1999)
Kulchar v. Kulchar
462 P.2d 17 (California Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
251 Cal. App. 2d 251, 59 Cal. Rptr. 399, 1967 Cal. App. LEXIS 1966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roussey-v-ernest-w-hahn-inc-calctapp-1967.