Rothers Construction, Inc. v. Centurion Industries, Inc.

CourtAppellate Court of Illinois
DecidedMarch 20, 2003
Docket4-02-0347 Rel
StatusPublished

This text of Rothers Construction, Inc. v. Centurion Industries, Inc. (Rothers Construction, Inc. v. Centurion Industries, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rothers Construction, Inc. v. Centurion Industries, Inc., (Ill. Ct. App. 2003).

Opinion

NO. 4-02-0347

IN THE APPELLATE COURT

OF ILLINOIS

FOURTH DISTRICT

ROTHERS CONSTRUCTION, INC., ) Appeal from

Plaintiff-Appellant, ) Circuit Court of

v.      ) Piatt County

CENTURION INDUSTRIES, INC., d/b/a ) No. 01CH13

A-LERT CONSTRUCTION SERVICES; O'MALLEY )

GRAIN, INC.; and UNKNOWN OWNERS AND ) Honorable

NON-RECORD CLAIMANTS, ) John P. Shonkwiler,

Defendants-Appellees. ) Judge Presiding.

_______________________________________________________________

JUSTICE KNECHT delivered the opinion of the court:

Plaintiff, Rothers Construction, Inc., a subcontractor, brought an action in the circuit court of Piatt County to foreclose a mechanics lien against defendants, O'Malley Grain, Inc., the owner of a construction project, and Centurion Industries, Inc., d/b/a A-Lert Construction Services (A-Lert), the general contractor.  Defendants filed a motion to dismiss pursuant to section 2-619(a)(9) of the Code of Civil Procedure (Code) (735 ILCS 5/2-619(a)(9) (West 2000)).  The trial court found plaintiff failed to perfect its mechanics lien pursuant to section 24 of the Mechanics Lien Act (Act) (770 ILCS 60/24 (West 2000)).  Plaintiff appeals, contending (1) the trial court erred in dismissing its mechanics lien foreclosure complaint on the grounds it was not properly perfected under section 24 of the Act and (2) the trial court erred when it failed to find defendants were equitably estopped from asserting the failure to perfect the lien under section 24 of the Act.  We affirm.

I. STATUTES AT ISSUE

The Act provides for different ways to perfect a mechanics lien depending on the circumstances.  Section 24 of the Act provides in pertinent part:

"[A] [s]ub[]contractor *** may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra or additional work or material is delivered thereafter, within 90 days after the date of completion of such extra or additional work or final delivery of such extra or additional material, cause a written notice of his or her claim and the amount due *** to be sent by registered or certified mail, with return receipt requested *** or personally served on the owner of record or his agent ***."  770 ILCS 60/24 (West 2000).

Section 25 of the Act provides in pertinent part:

"In all cases where the owner, agent, architect[,] or superintendent cannot, upon reasonable diligence, be found in the county in which said improvement is made, or shall not reside therein, the sub[]contractor *** may give notice by filing in the office of the recorder against the person making the contract and the owner a claim for lien ***."

770 ILCS 60/25 (West 2000).

II. BACKGROUND

A-Lert entered into a contract with defendant O'Malley Grain, Inc., to build grain bins and material handling systems on its property in Piatt County and then, on December 31, 1999, subcontracted some of the work on the project to plaintiff, Rothers Construction, Inc., a corporation headquartered in Minnesota.  On June 8, 2000, plaintiff completed construction services at O'Malley Grain's plant in Piatt County.  On September 5, 2000, plaintiff recorded a mechanics lien on O'Malley Grain's property in Piatt County in the amount of $97,182.50.  

On April 20, 2001, plaintiff filed a complaint against both defendants.  Attached to the complaint as exhibit A was a copy of the recorded mechanics lien.   Attached to the complaint as exhibit B was a notice of mechanics lien claim, addressed to O'Malley Grain, dated April 12, 2001.

On September 25, 2001, plaintiff filed its amended complaint.  Attached to this complaint was only an exhibit A, the recorded mechanics lien.  On October 15, 2001, both defendants filed a joint motion to dismiss the amended complaint pursuant to section 2-619(a)(9) of the Code.  In the portion of the motion addressing count I of the amended complaint, O'Malley Grain contends, among other things, plaintiff failed to allege it filed a notice of mechanics lien pursuant to section 24 of the Act (770 ILCS 60/24 (West 2000)) and its lien was not perfected.

On November 19, 2001, plaintiff filed a written response to the motion to dismiss and contended that section 25 of the Act applied, not section 24, and that it complied with section 25.  In support of this contention, plaintiff provided an exhibit to its response showing O'Malley Grain's registered agent to be located in Cook County.

Alternatively, plaintiff contended if compliance with section 24 of the Act was necessary for perfecting a mechanics lien in this case, O'Malley Grain was equitably estopped from arguing section 25 was improper because the mechanics lien claim was drafted by the attorney for O'Malley Grain, with instructions on how to file it with the recorder.  This contention was supported by the affidavit of James A. Rothers, plaintiff's vice-president, who stated plaintiff was referred to this particular attorney by the president of O'Malley Grain, Robert P. O'Malley.

On November 21, 2001, the trial court heard arguments on defendants' motion to dismiss count I.  The trial court found plaintiff did not meet all of the requirements of equitable estoppel but denied defendants' motion to dismiss as to count I on the grounds that O'Malley Grain was a resident of Cook County for purposes of the Act based on the case cited by plaintiff, Hollembeak v. National Starch & Chemical Corp. , 95 Ill. App. 3d 309, 420 N.E.2d 172 (1981), and, therefore, perfection of the mechanics lien was proper under section 25.

On December 20, 2001, O'Malley Grain filed a motion to reconsider the trial court's ruling.  Attached to the motion was the affidavit of Robert P. O'Malley, chief executive officer of O'Malley Grain, Inc.  In his affidavit, O'Malley stated he was a resident of Piatt County, was the agent in charge of the construction project at issue in Piatt County, and was present at the construction site three to four times per week during construction.

Plaintiff filed a motion to strike O'Malley's affidavit on January 17, 2002, and filed a response to the motion to reconsider on January 29, 2002.  The response did not mention the equitable estoppel arguments it had made in response to the original motion to dismiss.  O'Malley Grain filed a response to the motion to strike its affidavit on January 29, 2002.

On January 30, 2002 the trial court heard arguments on plaintiff's motion to strike and O'Malley Grain's motion to reconsider.  The trial court allowed O'Malley Grain to file O'Malley's affidavit .  During argument, plaintiff raised the equitable estoppel argument and O'Malley Grain asked the court to consider it as untimely raised since more than 30 days had passed since the trial court found the argument unpersuasive at the original motion to dismiss hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archer Daniels Midland Co. v. Barth
470 N.E.2d 290 (Illinois Supreme Court, 1984)
Season Comfort Corp. v. Ben A. Borenstein Co.
655 N.E.2d 1065 (Appellate Court of Illinois, 1995)
Korogluyan v. Chicago Title and Trust Co.
572 N.E.2d 1154 (Appellate Court of Illinois, 1991)
Henrich v. Libertyville High School
712 N.E.2d 298 (Illinois Supreme Court, 1999)
Suddarth v. Rosen
224 N.E.2d 602 (Appellate Court of Illinois, 1967)
Horwitz v. Holabird & Root
726 N.E.2d 632 (Appellate Court of Illinois, 2000)
Geddes v. Mill Creek Country Club, Inc.
751 N.E.2d 1150 (Illinois Supreme Court, 2001)
Hollembeak v. National Starch & Chemical Corp.
420 N.E.2d 172 (Appellate Court of Illinois, 1981)
Caruso v. Kafka
638 N.E.2d 663 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Rothers Construction, Inc. v. Centurion Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rothers-construction-inc-v-centurion-industries-in-illappct-2003.