Roswell Drainage Dist. v. Dickey

292 F. 29, 1923 U.S. App. LEXIS 2937
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 1, 1923
DocketNo. 6190
StatusPublished
Cited by6 cases

This text of 292 F. 29 (Roswell Drainage Dist. v. Dickey) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roswell Drainage Dist. v. Dickey, 292 F. 29, 1923 U.S. App. LEXIS 2937 (8th Cir. 1923).

Opinion

FARIS, District Judge.

Appellee Walter S. Dickey (impleaded for the purpose of a counterclaim filed by appellants', with his surety, Maryland Casualty Company), who was the plaintiff below, brought this action in equity to cancel a contract made by him with appellant Roswell drainage district, and for an accounting, and to recover, on a quantum meruit, money alleged to be due said appellee for work and materials done and furnished by him, pursuant to such contract and before an alleged breach thereof by the drainage district.

[1] In limine, appellees move to dismiss this appeal, for that, as they allege, appellants, both upon the record and in their brief, have failed to comply with the provisions of rules 11 and 24 of the Rules of this Court (188 Fed ix, xvi, 109 C. C. A. ix, xvi). In a strictly technical sense this motion may have merit; but it is clear that appellants have endeavored to comply with these rules, and their failure if any, has been due to an effort to be more specific even than required by the rules invoked. In the zeal of counsel minutely and meticulously to set out the precise nature of the errors relied on, they have overlooked the intrinsic nature of these alleged errors, which they could have stated better if they had stated them more broadly. In such a situation, we are of opinion that appellants ought not to be penalized by a dismissal of their appeal, and the motion to dismiss the appeal is accordingly overruled.

Cfoming now to the merits: Upon the trial below each of the parties contended that the contract had been breached by the other— plaintiff, Dickey, for that he had not been paid the money due him for work, labor, and materials, as and at the times provided in the contract; and defendant1 drainage district, for that Dickey had used certain materials in the work, to wit, iron for manholes, of less thickness than was prescribed by the specifications, and for that he had not vigorously and continuously prosecuted the work, as in the contract provided. Upon these contentions, the drainage district bottomed its counterclaim for damages accruing to it from the alleged breach of the contract by Dickey.

Briefly stated, and so far as is pertinent, the contract sought to be canceled provided for the digging of about 100 miles, of trenches, the laying of sewer tile therein, the backfilling of such trenches, the excavating of rock and quicksand incidental thereto, the straightening of a river, called Southsprings river,'and the construction of manholes; all labor, machinery, and materials to be furnished by Dickey. The [31]*31contract involved the definite payment of $200,000 to Dickey, with an indefinite sum for extra work and materials, not specified in the plans and specifications, which were to be paid for at the actual reasonable cost thereof, plus 20 per cent. Dickey was to be paid 90 per cent, of the contract price of all work completed, on the 5th and the 20th of each month; of the balance, 7% per cent, was to be paid on the completion of any given section, and the remainder, of 2% per cent., on final completion and acceptance of -all of the work. Dickey contracted to commence work on the 31st day of August, 1915, and, as forecast, to prosecute it vigorously and continuously to completion. Save this provision, no time was fixed for its completion.

The trial court dismissed the counterclaim and found for Dickey, canceling the contract, because of a breach thereof by the drainage district in the matter of making payments due Dickey, as and when such payments fell due, and entered judgment for him for the sum of $21,-276.65. From this decree this appeal was taken by the. drainage district in the conventional mode.

The errors urged for reversal are: (a) That the trial court erred in holding that Dickey’s use of iron, in constructing manholes of a thickness less than called for in and by the specifications, was not a breach of the contract; (b) in holding that Dickey’s alleged failure to prosecute the work vigorously and continuously was not a breach of the contract; (c) in holding that Dickey was entitled to recover $14,711.28, for extra work in excavating rock and quicksand; and (d) in finding against the drainage district upon its counterclaim.

[2] The fact is conceded that Dickey," in constructing the manholes, used iron of 16-gauge, instead of 14-gauge, or x/fa of an inch less in thickness than was called for by the specifications. But Dickey in excuse therefor pleads waiver by the drainage district, mutual mistake in the specifications, and the consent of the engineer in charge for such use, as permitted by the contract. Upon these defenses much evidence was offered upon the trial by both sides. By the preponderance of that evidence it is shown that, while 14-gauge iron was specified for use in constructing manholes, it was by all parties understood that 16-gauge iron should be used for reasons of economy; that the prices for these manholes was fixed upon the basis of the use of 16-gauge iron; that the engineer in charge had the authority under the terms of the contract to permit such use, and that he did permit it, and that the district itself, by its acts, waived this departure from the letter of the specifications. We are of opinion, as already said, that these defenses against the conceded fact were proven by the great weight of the evidence. But, even if this view be wrong, there was evidence enough upon these defenses to put in motion the rule that, where a chancellor has considered conflicting evidence and has based his findings thereon, such findings are to be deemed presumptively correct, and these findings will not be reversed, save in the presence of an obvious error of law, or a serious mistake of fact. United States v. Marshall, 210 Fed. 595, 127 C. C. A. 231; Brookheim v. Greenbaum, 225 Fed. 763, 141 C. C. A. 89. It follows that this contention of appellants should be disallowed.

[32]*32[3] The contract, it will have been noted, fixed no definite time within which completion should be had, save that connoted by the broad stipulation that the work should “be prosecuted vigorously and continuously.” In such situation Dickey was only bound to complete the work in a reasonable time, the existing conditions, situation, and circumstances regarded. The agreement to prosecute the work vigorously and continuously is therefore to be interpreted in the light of the time contemplated for completion, to wit, a reasonable time, and he •was required to exercise only such vigor and continuousness of prosecution as would insure completion in such time, the situation, and existing conditions regarded. The work was in hand during the Great War, and it was being prosecuted before, during, and after this country became involved in that war. The evidence discloses a great scarcity of labor, great incompetency of the laborers secured, and great difficulties in procuring materials for the work and parts for repairs to machinery.

If there had been, as there was not, a fixed and definite time’ agreed on for completion, and no exceptions written into the contract for delays incident to circumstances, then, of course, the scarcity of labor and the incompetency thereof, and the difficulty of getting materials and repairs, would have afforded no legal excuse for a failure to complete within the period provided. But when, by implication of law, completion is required only in a reasonable time, that time which is reasonable will be determined by a reference to the situation existing at and pending performance. 13 C. J. 685.

[4]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allsop Lumber Co. v. Continental Casualty Co.
385 P.2d 625 (New Mexico Supreme Court, 1963)
Bowmaster v. Carroll
23 F.2d 825 (Eighth Circuit, 1928)
Simmons v. Utah Copper Co.
15 F.2d 780 (Eighth Circuit, 1926)
United States v. Bucher
15 F.2d 783 (Eighth Circuit, 1926)
Empire Gas & Fuel Co. v. Stern
15 F.2d 323 (Eighth Circuit, 1926)
Savage v. Shields
293 F. 863 (Eighth Circuit, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
292 F. 29, 1923 U.S. App. LEXIS 2937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roswell-drainage-dist-v-dickey-ca8-1923.