Ross v. Columbus Mining Co.

264 S.W. 1071, 204 Ky. 474, 1924 Ky. LEXIS 491
CourtCourt of Appeals of Kentucky
DecidedSeptember 26, 1924
StatusPublished
Cited by12 cases

This text of 264 S.W. 1071 (Ross v. Columbus Mining Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ross v. Columbus Mining Co., 264 S.W. 1071, 204 Ky. 474, 1924 Ky. LEXIS 491 (Ky. Ct. App. 1924).

Opinion

¡Opinion of the Court by

Judge 0 ’Neal —

-Reversing.

Tbe appellants, George Ross and J. B. Rayner, as plaintiffs in a joint petition, sought to recover damages from the appellee, Columbus Mining Company, for its breach of an oral contract which they claim it entered into with them.

They allege in their petition “that on the 16th day of August, 1916, they entered into an oral contract with this defendant company ... to take up and continue to drive a certain entry in the defendant’s mine, and pursuant- to that (sic) terms of said oral contract the plaintiffs agreed to drive said entry and air courses, and to turn off cross entries; side rooms and dog entries, and to fix up all places, curtain up the air, and repair the track and to do any and . . . work necessarily incident to place said mine in condition so successful mining could be done in said first part of said mine, and to do all the work [476]*476preparatory to preparing said mine for successful operation of all coal in the second part of defendant’s mine . . . and in fact they contracted to do and perform any and all work necessarily incident to reaching and mining the coal in the second part of defendant’s mine; . . . they agreed to remove all the coal from the aforesaid entry, cross entries, air courses, side rooms and dog entries, and place same in cars. . . . They were to have complete control of said entry, cross entries, side rooms, dog entries and air courses for a period of one year from the 16th day of August, 1916, until the 16th day of August, 1917, . . . and (defendant) agreed and bound itself to pay these plaintiffs the sum of $0.47 per ton for all coal removed from said coal mine aforesaid . . . $3.00 for each lineal yard made in driving1 said main entry . . . $0.75 per yard for the air courses driven in making said entry.

“Now plaintiffs say pursuant to aforesaid contract they entered into the discharge of their duties on the — day of August, 1916, and by the terms of said contract they were to work and labor in said mine for a period of twelve months therefrom.” They "further allege “that they did and performed each and every stipulation, condition and agreement of said oral contract enjoined upon them by its terms thereof from the date of said contract” for a period of five months, at which time defendant refused to permit them to continue their work, thereby breaking the contract to their damage in the sum of $2,940.00, for which amount they prayed judgment.

Upon the trial at the conclusion of all the evidence the lower court sustained appellee’s motion for a directed verdict and entered a judgment dismissing the petition, and from that judgment appellants prosecute this appeal.

The record fails to disclose upon what grounds the court sustained appellee’s motion for a directed verdict, but it is apparent the court’s ruling is based upon one or more of the grounds argued i±L brief of appellee’s counsel. It is therein contended that the action of the court was correct and the peremptory instruction proper, because, first, the petition failed to state a cause of action and, second, the evidence showed appellee’s superintendent who contracted with the appellants had no authority to make such a contract.

The sufficiency of the petition is attacked upon numerous grounds. It is insisted that the contract as alleged falls within the inhibition of section 470 of the Ken[477]*477tucky Statutes, commonly known as the statute of frauds, and is therefore unenforceable. That statute provides, in substance, that no action shall be brought to enforce any agreement not in writing which is not to be performed within'one year from the making thereof. Appellee argues that since the petition alleges that the oral contract therein declared upon was to run for a period of twelve months from the day it was made, it could not possibly be performed “within one year from the making thereof” and was therefore within the statute and unenforceable. It is further argued that under the rule of construction that a pleading is to be construed most strongly against the pleader, the allegation that appellants “entered into the discharge of their duties on the — day of August, 1916, and by the terms of said contract they were to work and labor in said mine for a period of twelve months therefrom,” must be construed as an allegation of an oral contract for a year’s services to commence in the future and therefore within the statute of frauds.

"We find no merit in either of these contentions. While it is true we have universally held that a pleading must be most strongly construed against the pleader, we have also held that it must be considered as a whole, and when the petition in this action is so construed it is not susceptible of the strained construction placed upon it by appellee’s counsel. It is unnecessarily prolix and therefore confusing, but though unartfully drawn it definitely alleges “that on the 16th day of August, 1916, they entered into an oral contract,” that they were to perform certain work and that “they were to have complete control of said entry . . . for a period of one year from the 16th day of August, 1916, until the 16th day of August, 1917;” that “they entered into the discharge of their duties on the — day of August, 1916, and by the terms of said contract they were to work and labor in said mine for a period of twelve months therefrom; ’ ’ and that “they did and performed each and every stipulation, condition and agreement of said oral contract enjoined upon them by its terms thereof from the date of said contract” until its breach by appellee.

It will be noted that in the next to the concluding phrase just quoted the petition charges that appellants started work on, and the contract was to run twelve months from, “the — day of August, 1916.” Counsel contend that when this is construed most strongly against the pleader the blank day of August must be held to mean [478]*478a, day in August later than the 16th, the date of the contract, and that therefore the contract was to commence in the future, and being oral and for a year it was within the statute of frauds and unenforceable. This argument might be sound if the petition contained no other allegations on the subject, or if there were any doubt as to the date omitted, but neither condition exists here. We might add that the uncontradicted evidence also shows that appellants commenced work under the contract on the day it was entered into. However, the extracts from the petition which we have previously copied herein show beyond cavil that the term of the contract was exactly one year, commencing the day it was made, to-wit, August 16,1916, and ending August 16, 1917. This being true, it was not required to be in writing and was not within the inhibition of the statute of frauds, for, as stated in 25 E. C. L. 453:

“’If the contract period commences running immediately on the making of the contract and is to extend for a year and no longer, it is not within the statute.”

The same principle is thus stated in 27 C. J. 186:

“An oral contract of employment for a year to begin on the day the contract is made ... is not within the statute. So if the contract is made orally for one year to begin in praesenti, although no services are to be performed by the employee until a future day, the contract is operative from the day of the making and is not within the statute.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Island Trashmoval Services, Inc. v. Government of the Virgin Islands
23 V.I. 367 (Supreme Court of The Virgin Islands, 1988)
M & R Contractors & Builders, Inc. v. Michael
138 A.2d 350 (Court of Appeals of Maryland, 1958)
Lively v. Elkhorn Coal Co.
101 F. Supp. 1014 (E.D. Kentucky, 1952)
Elizabethtown Lincoln-Mercury, Inc. v. Tucker
240 S.W.2d 847 (Court of Appeals of Kentucky, 1951)
Boutwell v. Lewis Bros. Lumber Co.
182 S.W.2d 1 (Court of Appeals of Tennessee, 1944)
Blue Diamond Coal Company v. Robertson
31 S.W.2d 701 (Court of Appeals of Kentucky (pre-1976), 1930)
Harmount Wolff Tie Company v. Skinner
24 S.W.2d 263 (Court of Appeals of Kentucky (pre-1976), 1930)
Swain v. Harmount & Woolf Tie Co.
11 S.W.2d 940 (Court of Appeals of Kentucky (pre-1976), 1928)
Ross v. Columbus Mining Company
10 S.W.2d 628 (Court of Appeals of Kentucky (pre-1976), 1928)
Shipp Ex Rel. Fayette County v. Rodes
293 S.W. 543 (Court of Appeals of Kentucky (pre-1976), 1927)
Columbus Mining Company v. Ross
290 S.W. 1052 (Court of Appeals of Kentucky (pre-1976), 1927)
Elkhorn Coal Corporation v. Case
278 S.W. 570 (Court of Appeals of Kentucky (pre-1976), 1925)

Cite This Page — Counsel Stack

Bluebook (online)
264 S.W. 1071, 204 Ky. 474, 1924 Ky. LEXIS 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ross-v-columbus-mining-co-kyctapp-1924.