Ross v. City of Cedarvale

255 P. 43, 123 Kan. 344, 1927 Kan. LEXIS 135
CourtSupreme Court of Kansas
DecidedApril 9, 1927
DocketNo. 27,307
StatusPublished

This text of 255 P. 43 (Ross v. City of Cedarvale) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ross v. City of Cedarvale, 255 P. 43, 123 Kan. 344, 1927 Kan. LEXIS 135 (kan 1927).

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

Wilbur Ross sued the city of Cedarvale to recover for his services in operating a light plant of the city and also for damages for being wrongfully excluded from his position as an [345]*345employee of the city. The court sustained a demurrer to plaintiff’s evidence and he appeals.

It appears that plaintiff had been- an employee of the city prior to March 24, 1923, when he entered into an agreement with defendant whereby plaintiff was to receive $125 per month until January 1, 1924. The contractual employment expired on the latter date but he continued his services thereafter and was paid thé wage of $125 per month up to the first of April, 1924. In February of that year the city determined to change its system and asked for bids for the operation of the plant, and in pursuance of a notice given by the city, Ross and others joined in making a bid in which Ross agreed to do the work for $110 per month. Other bids were received and the bid of another party was accepted on March 19, 1924. After-wards, and on April 19, the successful bidders went to the plant accompanied by the city marshal and demanded possession and an opportunity to operate the plant, but the plaintiff refused to surrender it, claiming the city had no right to place it in charge of others or to discontinue his service. There was no attempt to oust plaintiff by force, and he continued to operate until September, 1924, and once a month presented a bill for his services in which he asked for $110 per month. The city council refused to recognize him as an employee of the city after the time of the demand, and disallowed the bills presented. He surrendered the control of the plant and left the service of the city on September 15, 1924, and the persons previously employed for the service took charge of the plant. Plaintiff then brought this action asking for $125 per month and damages for discontinuing his services.

The court held against his contention upon a demurrer to his evidence. Unquestionably the city council had control of the plant and had the right to select employees to operate it. Plaintiff had a contract with the city which by its terms terminated on January 1, 1924. The contract for employment was not renewed or extended by the council, and plaintiff recognized the purpose and right of the city to control employment and change employees when he submitted a bid on a different basis for future operation. The city council had paid him for services up to April 1, which was after the letting of the contract to others and after the notice to quit had been served upon him, but he stubbornly held possession of the plant and insisted that the city council could not change its employees. The fact that the officers did not use more robust means to eject [346]*346plaintiff from the plant, did not vest him with any new rights as against the city.

It is said that the demurrer should not have been sustained inasmuch as the notice to quit fixed the time at April 19, and that the city thus recognized that his services should be continued until that time. Payment was made as we have seen to April 1, but no payment was made after that time because of the attitude of the plaintiff that the city had no authority to employ others and because of his- demand for an indefinite continuance of his employment. He was entitled to compensation up to the time fixed by the notice to quit, but there was no real dispute as to that feature of the case, and this was recognized by the court when it allowed plaintiff judgment for $78.09 for the nineteen days of work in April. That was all the compensation that was due to plaintiff and that he received. Not being a contested question, there is no merit in the objection upon that ground to the sustaining of the demurrer.

As the defendant was successful on the real dispute in the case the awarding of costs against the plaintiff cannot be regarded as material error.

The judgment is affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
255 P. 43, 123 Kan. 344, 1927 Kan. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ross-v-city-of-cedarvale-kan-1927.