Rosen Construction Ventures, Inc. v. Mintz, Levin, Cohn, Ferris, Glovsky & Popeo, P.C.

364 F.3d 399, 2004 U.S. App. LEXIS 7372, 2004 WL 817140
CourtCourt of Appeals for the First Circuit
DecidedApril 16, 2004
Docket03-1758
StatusPublished
Cited by15 cases

This text of 364 F.3d 399 (Rosen Construction Ventures, Inc. v. Mintz, Levin, Cohn, Ferris, Glovsky & Popeo, P.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rosen Construction Ventures, Inc. v. Mintz, Levin, Cohn, Ferris, Glovsky & Popeo, P.C., 364 F.3d 399, 2004 U.S. App. LEXIS 7372, 2004 WL 817140 (1st Cir. 2004).

Opinion

LIPEZ, Circuit Judge.

Plaintiffs Rosen Construction Ventures, Inc. and Acropolis Ventures, Inc., owned by Clifford Rosen, (collectively, “Rosen”) filed a legal malpractice action against Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C., and two members of that firm, Stephen Leonard and Stephen Lan-ger (collectively, “Mintz Levin”). Rosen alleges that Mintz Levin was negligent in drafting a contract between Rosen and O’Donnell Sand & Gravel, owned by Mary O’Donnell (collectively, “O’Donnell” or “ODSG”), and in failing to properly advise Rosen about certain easements it required on the O’Donnell property.

Mintz Levin moved for summary judgment in August 2000, arguing that Rosen’s claims were barred by the three-year statute of limitations for legal malpractice actions. Mass.G.L. ch. 260, § 4 (2003). In March 2001, the district court denied that motion, holding that there was a disputed issue of fact about the duration of Mintz Levin’s representation of Rosen. One *402 year later,-while discovery was ongoing, the Massachusetts Supreme Judicial Court decided Lyons v. Nutt, 436 Mass. 244, 763 N.E.2d 1065 (2002), a case that clarified the continuing representation doctrine applicable to legal malpractice actions.

In February 2002, Mintz Levin again moved for summary judgment, citing the Lyons decision and evidence procured during discovery. In response, the district court held that “[t]he issue is not ... when Rosen thought that it might have a malpractice claim against Mintz Levin, but rather when it knew it was harmed as a result of Mintz Levin’s conduct.” The district court then granted Mintz Levin’s second summary judgment motion, holding that Rosen actually knew that its harm was the result of Mintz Levin’s conduct more than three years before it filed its malpractice action against Mintz Levin.

In evaluating Rosen’s appeal from this summary judgment ruling, we must determine whether there is a genuine issue of fact regarding when Rosen’s malpractice claim accrued — that is, when Rosen knew, or should have known, that Mintz Levin’s alleged malpractice was the source of Ro-sen’s injuries. After reviewing the summary judgment record, we affirm in part and vacate in part the district court’s decision.

I.

We set forth the background facts here, reserving some of the details until the discussion of the issues on appeal. In August of 1994, Rosen Associates, a non-party to this case and a separate entity controlled by Clifford Rosen, the owner of Rosen Construction Ventures, Inc., agreed to purchase a parcel of land in Everett, Massachusetts from Monsanto Chemical Company and another related entity. Ro-sen intended to build a shopping center on this site, referenced by the parties as the “Development Site.” The Development Site was contaminated, and the remediation plan called for a six-foot deep layer of clean fill to be spread over the property. Because Rosen contracted for this remediation responsibility, it needed to obtain and store clean fill until it could be used on the Development Site.

O’Donnell, who had access to significant quantities of clean fill, owned land close to the Development Site. It had purchased this property from Boston Edison Co. (the “Edison Site”) for $100,000 in cash and a $1.9 million note (the “Edison Note”). In early 1995, Rosen and O’Donnell negotiated an agreement relating to both the fill and certain aspects of the Edison Site. Rosen retained Mintz Levin to draft a contract that memorialized the arrangement between Rosen and O’Donnell. That written contract, which came to be known as the Fill Agreement, was dated April 19, 1995.

Among other things, the Fill Agreement provided that (1) O’Donnell would grant Rosen a three year 51% interest in the Edison Site as tenants in common, (2) Rosen could convert that temporary 51% interest into a maximum 50% permanent partial interest, depending on the extent to which Rosen negotiated a reduction in the principal of the Edison Note, and (3) O’Donnell would grant to Rosen, upon Ro-sen’s request, a perpetual easement on the Edison Site to allow Rosen to construct road access to the Development Site. The portion of the Fill Agreement relevant to Rosen’s rights to secure a permanent interest in the Edison Site — Section 6(b)— reads as follows:

[I]f Rosen, in its sole discretion, is able to negotiate with Edison a forgiveness of, or a reduction in, the principal amount due in order to obtain a discharge of the Edison Mortgage, below $1,900,000, then Rosen may retain, and shall not be required to reconvey to *403 [O’Donnell], that undivided percentage interest (not to exceed 50%) in the Edison Site which is equal to (x) the amount of such principal forgiveness or reduction, divided by (y) Two Million Dollars ($2,000,000). For example, if Rosen were to negotiate a principal reduction of $250,000, then Rosen would be able to retain a 12.5% undivided interest, and if Rosen were to negotiate a principal reduction of $1,250,000, then Rosen would be entitled to retain a 50% undivided interest.

After signing the Fill Agreement in April, Rosen began negotiating with Boston Edison for a reduction in the principal amount of the Edison Note. At that time, the principal payment schedule for the Edison Note called for $100,000 monthly payments from May to September 1995, $200,000 payments in December 1995 and March and June 1996, and a final $800,000 payment in March 1998. Rosen attempted to secure at least partial forgiveness of the Edison Note in exchange for agreeing to purchase the electricity for the planned shopping center on the Development Site from Boston Edison. At one point, Boston Edison offered a $640,000 reduction in the Edison Note, which Rosen did not accept. In the end, Rosen and Boston Edison never finalized a reduction in the outstanding Edison Note balance.

On April 2, 1996, almost one year after the Fill Agreement was signed, O’Donnell paid off the outstanding balance of the Edison Note and obtained a discharge of the mortgage on the Edison Site. The next day, O’Donnell verbally informed Rosen of its actions. During the following week, O’Donnell advised Rosen that, in its view, the full payment of the note terminated Rosen’s right to acquire a permanent interest in the Edison Site under the Fill Agreement.

Rosen disagreed with O’Donnell’s interpretation of the Fill Agreement, claiming that its right to obtain a permanent interest in the Edison Site had not been terminated and that O’Donnell’s prepayment of the note and its position on the issue were “calculated to interfere with a right [Ro-sen] had bargained for in good faith.” O’Donnell responded that Rosen’s position was “preposterous” and that O’Donnell’s decision to satisfy its obligations on the Edison Note at that time was permitted by the Fill Agreement. O’Donnell also wrote that “[n]owhere is it stated that O’Donnell is prohibited from early satisfaction of our financial obligations.” During April and June of 1996, Rosen and O’Donnell exchanged increasingly heated letters setting forth their respective positions, and eventually they reached an impasse.

In June 1996, Rosen asked Mintz Levin to draft a complaint for use in an impending civil action against O’Donnell, and Mintz Levin complied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mary Serafine v. Tim Branaman
810 F.3d 354 (Fifth Circuit, 2016)
Hutchins v. Shatz, Schwartz & Fentin, P.C.
494 B.R. 108 (D. Massachusetts, 2013)
Mendes v. Factor
41 A.3d 994 (Supreme Court of Rhode Island, 2012)
Frankston v. Denniston
907 N.E.2d 244 (Massachusetts Appeals Court, 2009)
Feddersen v. Garvey
427 F.3d 108 (First Circuit, 2005)
Feddersen v. Garvey, et al.
D. New Hampshire, 2005
Feddersen v. Garvey
352 F. Supp. 2d 145 (D. New Hampshire, 2005)
Union Products Inc. v. Warner 7 Stackpole, L.L.P.
18 Mass. L. Rptr. 624 (Massachusetts Superior Court, 2004)
Bourdeau v. Wall
111 F. App'x 28 (First Circuit, 2004)
CHESWELL, INC. v. Premier Homes and Land Corp.
319 F. Supp. 2d 144 (D. Massachusetts, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
364 F.3d 399, 2004 U.S. App. LEXIS 7372, 2004 WL 817140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rosen-construction-ventures-inc-v-mintz-levin-cohn-ferris-glovsky-ca1-2004.