Rootstown Excavating, Inc. v. Smith

2011 Ohio 6415
Ohio Court of Appeals·Decided December 14, 2011·No. 25457·Published·Cited by 2 cases

Opinion

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

ROOTSTOWN EXCAVATING, INC. C.A. No. 25457 Appellant

v. APPEAL FROM JUDGMENT ENTERED IN THE

KAREN EDWARDS SMITH, TRUSTEE COURT OF COMMON PLEAS OF THE SMITH FAMILY TRUST, et al. COUNTY OF SUMMIT, OHIO CASE No. CV 2007-02-1489 Appellees

DECISION AND JOURNAL ENTRY Dated: December 14, 2011

MOORE, Judge.

{¶1} Appellant, Rootstown Excavating, Inc., appeals from the judgment of the Summit County Court of Common Pleas. This Court affirms.

I.

{¶2} On April 21, 2005, Appellant Rootstown Excavating, Inc., entered into a contract with The Smith Family Trust (the “Trust”) to perform improvements to a 12.5-acre site in the City of Hudson, Summit County, Ohio. The Trust subdivided the site into twenty-two separate parcels, nineteen of which were intended to be sold to builders or individuals as residential lots. Rootstown was to perform certain improvements to the land, such as excavation, clearing, and installation of sewers and waterlines along the planned roads of the subdivision.

{¶3} Rootstown first began working on the site on May 26, 2005. In December 2005, the Trust sold Sublot No. 2 to Appellee Glenmoore Builders, Inc. Glenmoore constructed a model home on the property. Subsequently, a dispute arose between the City of Hudson and the

Trust. As a result, Rootstown’s work was temporarily suspended. It averred that it was unable to complete its work until November 1, 2006.

{¶4} The Trust failed to pay Rootstown in full for services, material and labor furnished to the site, pursuant to the terms of the contract. Consequently, on January 3, 2007, Rootstown executed an affidavit to obtain a mechanic’s lien. The lien was served upon the Trust and Glenmoore. On February 27, 2007, Rootstown filed a motion for partial summary judgment requesting that the trial court determine the validity of the mechanic’s lien, and the right to foreclose upon Sublot No. 2. On that same day, Glenmoore filed a cross-motion for summary judgment asking the trial court to find that Rootstown’s lien was not valid as to Sublot No. 2.

{¶5} On April 10, 2009, the trial court determined that Rootstown’s lien against Sublot No. 2 was not valid because it was not filed within 60 days of Rootstown’s last work on the site. As a result, the trial court denied Rootstown’s motion for partial summary judgment, and granted Glenmoore’s motion for summary judgment. The order did not contain Civ.R. 54(B) language, and the trial court denied Rootstown’s motion for a nunc pro tunc entry with such language. On May 24, 2010, the trial court issued a final order and decree in foreclosure that found Rootstown’s lien to be valid against the remaining sublots.

{¶6} Rootstown timely filed a notice of appeal and raises three assignments of error for our review. We will address them out of order to facilitate our review.

II.

ASSIGNMENT OF ERROR I

“THE TRIAL COURT ERRED IN HOLDING THAT ROOTSTOWN’S LIEN WAS INVALID BECAUSE THE AFFIDAVIT WAS NOT RECORDED WITHIN 60 DAYS OF ROOTSTOWN’S LAST DATE OF WORK ON THE PROPERTY.”

ASSIGNMENT OF ERROR III

“THE TRIAL COURT LIKEWISE ERRED IN GRANTING GLENMOORE’S MOTION FOR SUMMARY JUDGMENT.”

{¶7} In its first assignment of error, Rootstown argues that the trial court erred in holding that its lien was invalid because the affidavit was not recorded within 60 days of its last work on the property. Because of this, it further argues in the third assignment of error that the trial court erred in granting Glenmoore’s motion for summary judgment. We do not agree.

{¶8} We review an award of summary judgment de novo. Grafton v. Ohio Edison Co.

(1996), 77 Ohio St.3d 102, 105. “Pursuant to Civ.R. 56(C), summary judgment is appropriately rendered when ‘(1) [n]o genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing such evidence most strongly in favor of the party against whom the motion for summary judgment is made, that conclusion is adverse to that party.’” Turner v. Turner (1993), 67 Ohio St.3d 337, 339-340, quoting Temple v. Wean United, Inc. (1977), 50 Ohio St.2d 317, 327. On a motion for summary judgment, the moving party has the burden of demonstrating that no genuine issues of material fact exist. Dresher v. Burt (1996), 75 Ohio St.3d 280, 292. The burden then shifts to the nonmoving party to provide evidence showing that a genuine issue of material fact does exist. Id. at 293.

{¶9} Both parties agree that the last date of work in relation to the residential project was November 1, 2006, and that this work did not occur on the Glenmoore property. The affidavit to obtain a mechanic’s lien was filed January 3, 2007, sixty-three days after the last date of work. As such, if the affidavit was required to be filed within 60 days, it would be untimely. In its motion for summary judgment, and its reply to Rootstown’s motion for summary judgment, Glenmoore argued that R.C. 1311.06(B)(1) mandated that Rootstown file its lien

within 60 days of its last day of work. Rootstown argued that the affidavit was subject to the 75- day filing requirement because the work performed was not “in connection with a one- or two- family dwelling[.]” See R.C. 1311.06(B)(1)/(3). It contended that the work “was performed pursuant to a commercial contract with the Trust for site improvements to a one-parcel plot of land[.]” It urged the trial court to look at the “nature of the actual work performed by the lien claimant.” Rootstown offered no case law to support its view, and instead urged the court to look at the plain meaning of the statute and the legislative intent.

{¶10} R.C. 1311.03 provides that every person who, pursuant to a contract with the owner or holder of another legal interest in real property, provides improvements to roads, drains, or sewers, shall have a lien on the property to secure payment for what he is owed. The lien applies to any current legal interests and any that are subsequently obtained. Notice and recording provisions in R.C. 1311.04, 1311.05, 1311.06 and 1311.07 make the lien binding on the current owner and any others who subsequently acquire an interest in the property. Although liberal principles of construction generally apply to effectuate the purpose of a mechanic’s lien, liberal construction does not apply to the procedure for perfecting the lien; all steps set forth in the statute to perfect a lien must be followed and the law must be strictly construed and applied. Internatl. Refractory Serv. Corp. v. Woodmen of the World Life Ins. Society (1990), 68 Ohio App.3d 513, 515-516.

{¶11} R.C. 1311.06(B)(1) provides that a mechanic’s lien that “arises in connection with a one- or two-family dwelling” shall be filed “within sixty days from the date on which the last labor or work was performed or material was furnished by the person claiming the lien[.]” Otherwise, “[i]f the lien is one not described in division (B)(1) or (2) of this section, [it shall be filed] within seventy-five days[.]” R.C. 1311.06(B)(3). Based on the plain language of the

statute, it is evident that if the materials or labor arise in connection with a one- or two-family dwelling, then the 60-day filing requirement applies. If they do not, the 75-day filing requirement applies.

Free access — add to your briefcase to read the full text and ask questions with AI

Rootstown Excavating, Inc. v. Smith, 2011 Ohio 6415 (Ohio Ct. App. 2011).

2011 Ohio 6415 (Rootstown Excavating, Inc. v. Smith) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Buck v. Reminderville
2014 Ohio 1389 (Ohio Court of Appeals, 2014)
Sheperd v. Akron
2012 Ohio 4695 (Ohio Court of Appeals, 2012)