Root Mfg. Co. v. Johnson

219 F. 397, 135 C.C.A. 139, 1914 U.S. App. LEXIS 1663
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 6, 1914
DocketNo. 2097
StatusPublished
Cited by15 cases

This text of 219 F. 397 (Root Mfg. Co. v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Root Mfg. Co. v. Johnson, 219 F. 397, 135 C.C.A. 139, 1914 U.S. App. LEXIS 1663 (7th Cir. 1914).

Opinion

SEAMAN, Circuit Judge

(after stating the facts as above). [1 '• The judgment against the plaintiff in error rests entirely on the proposition, that the payment of $6,447.67, accepted by it in settlement of its claim of lien, constitutes a preferential payment obtained from the bankrupt in violation of section 60 of the Bankruptcy Act. It was received by the claimant within four months prior to the proceedings in bankruptcy against the debtor (Warren Construction Company) and with knowledge of the fact of the bankrupt’s insolvency, so that the plaintiff in error cannot escape liability therefor to the trustee as adjudged — notwithstanding the undisputed bona fides of the transaction otherwise — if the nature and circumstances of the claim and) settlement thus made do not exclude the transaction from the well-defined meaning of the provision referred to. On the other hand, it is unquestionable that the statute does not denounce-as preferential all payments so obtained by a creditor within the four-months period; that payment may lawfully be accepted for discharge of a valid lien, either legal or equitable; that payments or benefits obtained in various other transactions, as exemplified in recent decisions (Western Tie & Timber Co. v. Brown, 196 U. S. 502, 25 Sup. Ct. 339, 49 L. Ed. 571; Newport Bank v. Herkimer Bank, 225 U. S. 178, 32 Sup. Ct. 633, 56 L. Ed. 1042; Continental Trust Co. v. Chicago T. & T. Co., 229 U. S. 435, 33 Sup. Ct. 829, 57 L. Ed. 1268), are not within the meaning of the statute; and that a transaction is not an unlawful preference (Id.) unless “the estate of the bankrupt was thereby diminished.” While payment of such exceptional claims is preferential in the sense of receiving a benefit not authorized in favor of general creditors (not “of the same class”), it is not an unlawful preference. So the facts in evidence must establish a case clearly within the narrow range of these exceptions to defeat recovery.

[2] In the “special findings of fact” filed below the evidential facts (all undisputed) are set forth at considerable length, and they are epitomized in the foregoing statement, together with copies of the two agreements (of January 12 and April 10, 1912) on which the controversy hinges, mainly, if not entirely. Mention, therefore, of these contract relations and pertinent circumstances will suffice for understanding of the ultimate issue as presented: In 1910 the [402]*402Warren Construction Company (bankrupt) entered into a contract with the Cleveland, Cincinnati, Chicago & St. Louis Railway Company to construct buildings and works, at times and prices fixed, aggregating about $300,000; and bonds were executed by National Surety Company and Bankers’ Surety Company, as sureties, for performance of the work and covenants. For carrying out this work the contractor sublet various portions to numerous subcontractors; and the plaintiff ini error was one of the subcontractors, under'two contracts, amounting to $5,400 and $24,100, respectively, each containing a provision for waiver of liens for the work. During operations under the general contract in 1911, difficulties and delays arose, resulting in dissatisfaction both of the Railway Company and various subcontractors, filing of suits and liens by the latter, and disagreement between the Railway Company and its contractor over liabilities. The plaintiff in error had notified the Railway Company of nonpayment by the contractor for work performed under its subcontract, and completed its work under promises on the part of the Railway Company “to see that it was paid.” On November 25, 1911, the plaintiff in error had completed its subcontract, and $12,895.34 thereof was unpaid and undisputed; and it then filed and recorded its claim for a mechanic’s lien against the property of the Railway Company in conformity with the Indiana statute. In December, 1911, meetings were held attended by representatives of the Railway Company, the bankrupt, and both surety companies, and by various subcontractors, inclusive of the plaintiff in error, for settlement of differences between the parties, resulting in an undisputed written agreement, dated January 12, 1912, and executed by (a) the Railway Company, (b) the bankrupt, and (c) both surety companies. This agreement was completed and the entire fund thereby provided for payment of claims was deposited more than six months prior to the commencement of bankruptcy proceedings. Settlement of the claim of plaintiff in error for payment out of such funds was concluded April 10, 1912, under the further agreement of that date,, signed by all parties to the agreement of January 12, together with the plaintiff in error, and it thus falls within the inhibited four-months period, if the statute is applicable to such payment.

One of the contentions for reversal is that the plaintiff in error had a valid and enforceable mechanic’s lien for this unpaid claim, notwithstanding its so-called waiver thereof, and much of the argument on this appeal is directed for and against the dual propositions on which it rests, namely: (a) That the stipulation of waiver is not an independent one, but dependent on the ensuing stipulation for final payment to be made “within forty days after the contract is fulfilled”; and (b) that such waiver in an executory contract of the lien provided by the Indiana statute “is contrary to public policy and void.” We have not been impressed with either of these theories as tenable, either on the oral argument or upon examination of the authorities cited in the briefs, and they appear to be met and overruled by ‘a decision of the Appellate Court of Indiana (since the hearing of this appeal, called to attention by supplemental brief) in the suit of Carson-Payson Co. v. C., C., C. & St. L. Ry. Co. — for enforcement of [403]*403the statutory lien by one of the above-mentioned, subcontractors, under an analogous stipulation of waiver — reported 105 N. E. 503. Proceeding, therefore, on the assumption that the lien filed by the plaintiff in error on November 25, 1911, was not enforceable at law, in a suit founded alone on the contract for the work, the issue is limited to the force and effect of the above-mentioned agreement of January 12th and the segregation of fund thereby provided to entitle the plaintiff in error to receive payment of its claim thereunder, irrespective of bankruptcy proceedings against the debtor.

The agreement thus relied upon (in connection with the undisputed facts in reference to the claim) to render the payment lawful is entirely free from doubt as to its bona fides and purposes. It plainly provides a fund which was completely segregated from the estate of the bankrupt so long as any claim within its purview remained unsettled. It is free from ambiguity in any of its terms, except as to the meaning with which the term “lienable claims” was used .therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ricotta v. Burns Coal & Building Supply Co.
162 F. Supp. 214 (W.D. New York, 1958)
In Re Webb
160 F. Supp. 544 (S.D. Indiana, 1958)
Dinkelspiel v. Weaver
116 F. Supp. 455 (W.D. Arkansas, 1953)
Troyer v. Mundy
60 F.2d 818 (Eighth Circuit, 1932)
CITIZENS'NAT. BANK OF GASTONIA, NC v. Lineberger
45 F.2d 522 (Fourth Circuit, 1930)
Hough v. Atchison, T. & S. F. Ry. Co.
34 F.2d 238 (Tenth Circuit, 1929)
Beacon Trust Co. v. Dolan
27 F.2d 247 (First Circuit, 1928)
Reeves v. McWilliams Co.
280 F. 100 (Eighth Circuit, 1922)
In re K. G. Whitfield & Bro.
290 F. 596 (W.D. Tennessee, 1921)
Lewin v. Telluride Iron Works Co.
272 F. 590 (Eighth Circuit, 1921)
Mergenthaler Linotype Co. v. Hull
239 F. 26 (First Circuit, 1916)
Johnson v. Root Manufacturing Co.
241 U.S. 160 (Supreme Court, 1916)
In re Floyd-Scott Co.
224 F. 987 (D. Massachusetts, 1915)
Butterfield v. Woodman
223 F. 956 (First Circuit, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
219 F. 397, 135 C.C.A. 139, 1914 U.S. App. LEXIS 1663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/root-mfg-co-v-johnson-ca7-1914.