Roos v. Lassiter

188 F.2d 427
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 20, 1951
Docket13360_1
StatusPublished
Cited by3 cases

This text of 188 F.2d 427 (Roos v. Lassiter) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roos v. Lassiter, 188 F.2d 427 (5th Cir. 1951).

Opinion

HOLMES, Circuit Judge.

The appellees (plaintiffs below) recovered a judgment against the appellants (defendants below) for a balance claimed by appellees as due them for grubbing and clearing approximately 1600 acres of land, owned by appellants in Cameron County, Texas. A jury was waived, and the trial before the court below resulted in a judgment for appellees for the entire balance of $26,977.72, with interest from May 10, 1948. A contractor’s lien to secure its payment was fixed and decreed upon said land, with an appropriate foreclosure provision if payment as adjudged should not be made.

*428 The trial court found that, after a personal conference with defendant Edward Roos, the plaintiff Lassiter submitted to him a written proposal, with reference to said land, to knock and rack the brush, pick up the top ground, burn the brush, plow the ground not less than 16 to 18 inches, pick up the roots, burn them, float the ground, then rake both ways, pick up the roots, then float the ground. The proposal continued: “I will start in two days to work on the job. The dozers will start first, then in about two days I will start racks and burn the brush then plow right after the fire goes out.” (Signed) Ralph-Lassiter, Phone 108, Edinburg, Texas.

In January, 1948, the agreement was consummated in writing by a letter addressed to plaintiff Lassiter, signed in behalf of defendant by his agent (at that time) McLeod. The -letter reads as follows:

“Mr. Ralph Lassiter

Edinburg, Texas.

“Under -authority given me by the owner, Edward Roos, of approximately 1900 acres of land to San Pedro Grant, Cameron County, Texas, it is understood and agreed that you are to have the clearing contract on this tract of land and to be paid a price of $41.50 per acre according to the attached statement given Mr. Roos by yourself.

“It is further understood that you are to be paid on each 100 acres of land that is completed and ready for cultivation as it is finished.

“It is further understood that all of the contract will be completed and the land ready for cotton planting by March 1st, 1948, unless unavoidable circumstances prevent the completion of the clearing.

“I believe this constitutes the entire agreement, and if this is satisfactory you may sign a copy of this letter as acceptable to you.

“Yours very truly,

Wimberly McLeod

“Accepted

“ (s) Ralph Lassiter

WMc:lad.”

Appellees, for the purposes of this trial, construed the contract as follows, R. 96: “The land was to be cleared at -a price of $41.50 per acre and the writing was brief; in effect, it required him to knock the brush with a root plow and, float the ground. * * * To knock the brush with a bulldozer and to root plow the ground and clear up the roots and burn them and then float the ground. Floating, as I understand meaning sort of harrowing. And the contract was made in December, 1947, and was to be performed in January, February, and March, perhaps, but was to be completed, except for conditions not under the control of the Plaintiff, Mr. Lassiter, in time for the planting of cotton crop in 1948. That is the substance of the contract. * * * ”

Under date of March 4, 1948, appellee Lassiter wrote appellant John A. Roos, R. 223:

“Mr. John Roos

Erie Engine & Manufacturing Co.

Erie, Pennsylvaia.

“Dear Mr. Roos:

“Herewith enclosed is bill approved by Mr. Wimberly McLeod, and will thank you for a check for the amount listed on the. bill.

“Fully expect to have the -entire acreage ready for planting barring weather conditions.

“Enel. Ralph Lassiter.”

But the court held, R. 389: “I find that, as construed by the parties, time was not of the essence of the contract and that defendants, although complaining and dissatisfied, acquiesced in the delay and accepted the benefit of plaintiffs’ services. A balance of $26,977.72 is due plaintiffs from defendants.”

Appellants sought to reconcile this conflict between the court’s findings and appellees’ interpretation of the contract by moving to amend the findings to read, R. 380:

“(1) There is no real controversy but that all parties construed that portion of the letter contract between Plaintiffs and Defendants, which provided that ‘It is further understood that all of the contract will be completed and the land ready for *429 cotton planting by March 1st, 1948, unless unavoidable circumstances prevent the completion of the clearing.’ to mean that Defendants’ land should be cleared, grubbed and ready for cotton planting not later than April 1st, 1948; which was the time limit under the Federal Pink Bollworm Quarantine for planting cotton in the area in which the Defendants’ land is situated; and that, as so construed by the parties, time of performance was of the essence of the contract on which Plaintiffs sue.”

Appellants’ motion was overruled, and they contend that the learned trial judge fell into error on this and other points, because he concluded too early in the trial that appellants had waived their rights to proper and timely performance of the contract by making payments on account of appellees’ partial performance, with knowledge that the contract had not been completed prior to March 1, 1948 (R. 172-173; 201-202), in literal compliance with its terms, and that this too-quick conclusion influenced all subsequent rulings of the court below.

The district court found that appellants, knowing that the contract had not been completed prior to March 1, 1948, and that appellees were undertaking to complete it prior to March 31st, made two payments of $20,000 on account of the contract during the month of March, 1948; the first was made “without prejudice to our rights” (R. 229) on March 10, 1948, and the second made on account (R. 77), March 24, 1948.

As to the two payments, appellant Edward Roos testified as follows (R. 357, 358, 359) : “The manner in which Lassiter proceeded to clear the land did not lend itself to payment in 100 acre blocks. That is, it was not cleared 100 acres at a time. The process of clearing the land consisted of about five different operations and Lassiter’s plan of work was to complete one operation on the entire tract to be cleared and then proceeded with the next operation. I knew, as he did, that he would have to exercise real energy to accomplish the essential purpose of my contract with him, which was to put the land in condition for farming in time to plant a cotton crop in 1948. I was not informed as to Lassiter’s financial situation and did not want him handicapped in the performance of his contract by lack of funds. When he sent me his first estimate, in excess of $18,000.-00, I did not. know whether, he had completed the clearing of any portion of the land; but I had been informed by McLeod, and, about March 12 by telephone conversation with Lassiter, that his job of clearing was being completed. I, therefore, directed my son, Mr. John A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
188 F.2d 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roos-v-lassiter-ca5-1951.