COURT OF APPEALS OF VIRGINIA
Present: Judges Beales, Causey and White UNPUBLISHED
Argued by videoconference
RONALD VILLARROEL MEMORANDUM OPINION* BY v. Record No. 1572-24-4 JUDGE KIMBERLEY SLAYTON WHITE FEBRUARY 3, 2026 RAILING SYSTEMS, LLC
FROM THE CIRCUIT COURT OF ARLINGTON COUNTY Daniel S. Fiore, II, Judge
Tara L. Umbrino (Jennifer Porter; TLT Legal Services, PLLC; Jennifer Porter Law, PLLC, on briefs), for appellant.
Nicholas J. Phillips (Thomas, Thomas & Hafer, LLP, on brief), for appellee.
Ronald Villarroel appeals the circuit court’s judgment to sustain Railing Systems, LLC’s
(Railing Systems) plea in bar to his personal injury complaint. The circuit court determined that
the Workers’ Compensation Act (Act), Code §§ 65.2-300 through -307, precluded Villarroel’s
claim because Railing Systems and Villarroel were statutory co-employees of third-party
defendants BCN Design Build, LLC and BCN Enterprises, LLC (collectively BCN).1 Finding
no error, we affirm.
BACKGROUND
Villarroel worked at a residential construction project in Arlington in December 2021.
While working, he stepped on a window well egress grate and sustained serious injuries.
* This opinion is not designated for publication. See Code § 17.1-413(A). 1 BCN Enterprises, LLC oversees construction of projects, and BCN Design Build, LLC is a licensed general contractor. According to Villarroel, the grate gave way, causing him to fall down the window well.
Villarroel sued Railing Systems, arguing that it created a dangerous condition by failing to
properly install the grate.2 Villarroel’s complaint alleged four counts: (1) creation of a dangerous
condition; (2) failure to maintain; (3) failure to warn; and (4) negligent construction.
Railing Systems moved to file a third-party complaint for indemnification and
contribution against BCN. Over Villarroel’s objection, the circuit court granted the motion.
According to the third-party complaint, BCN provided installation instructions for the grate;
Railing Systems fabricated and installed the grate as specified and required by BCN; BCN
oversaw and controlled the construction project and construction safety; and BCN hired
Villarroel’s company and directed Villarroel’s work.
Railing Systems then filed a plea in bar, contending that Railing Systems and Villarroel
were both statutory employees of BCN under the Act, Code §§ 65.2-300 through -307. At the
plea in bar hearing, testimony indicated that BCN was the general contractor for the construction
project, and BCN’s contract required it to install the grate and complete the punchout work.
BCN subcontracted with Railing Systems to install the grate. BCN subcontracted with
Villarroel’s employer, Pristine Home Services (Pristine), to complete the punchout work, and
Villarroel performed Pristine’s work. Punchout work included details like installing doorknobs or
shower rods and applying touchup paint. BCN paid both Railing Systems and Pristine to work on
the project.
Railing Systems’ managing member and corporate designee, Mary Skelley, testified that
she field-measured the window-well opening for the grate, which had a ladder and a hatch door.
2 Villarroel had already “filed a suit against BCN in Richmond City Circuit Court.” However, based on the record, the case was dismissed with prejudice “upon agreement of the parties.” There is nothing in the record indicating any further action by Villarroel against BCN directly. -2- Then Railing Systems ordered the raw materials, cut them to the measurements taken, welded
them together, and primed them with a rustproof coating. As a non-expert witness, Skelley
testified that cutting and welding required specialized equipment and skills that she thought were
generally outside the skill set of an average general contractor.3 She added that Railing Systems
installed the grate at the property by drilling holes to install mounting brackets for the ladder,
bolting the brackets to the foundation or wall, bolting shelf angles, and mounting the grate on the
shelf angle.
From the evidence at the plea in bar hearing, the circuit court found among other things
that: (a) BCN contracted to build a residential dwelling at the property; (b) BCN engaged various
subcontractors to perform its contractual obligations, and BCN did not maintain employees to
perform the construction; (c) BCN subcontracted with Pristine, and Pristine performed BCN’s
trade; (d) Pristine employed Villarroel, who performed Pristine’s trade; (e) BCN subcontracted
with Railing Systems to fabricate and install the grate; (f) Railing Systems fabricated and
installed the grate “based on its own pre-inspection of the window well area”; and (g) Villarroel
fell through the grate’s window well while he worked. The circuit court found that Railing
Systems was “not a delivery service of material”; rather, it installed the grate. Railing Systems’
installation of the grate was necessary to fulfill BCN’s contractual obligation, and it therefore
constituted the trade, business, or occupation of BCN.
The circuit court considered Skelley’s lay testimony that welding was outside the skill set
of an average general contractor to be only “an opinion” without authority or expert support.
The circuit court found Skelley’s testimony unconvincing and unsupported by authority. The
circuit court stated: “There’s nothing that says a general contractor can’t perform welding.
3 Asked whether “for the average general contractor, the ironwork and welding work that you described for the Court is outside of the skill set of a general contractor,” Skelley answered, “Generally, yes.” -3- There’s no statutory provision. There’s no ordinance against it. The—you know, this is a
burden that the plaintiff assumed. And this Court is not persuaded.”
The circuit court held that the Act applied because Villarroel and Railing Systems were
statutory co-employees, and BCN was the statutory employer. Finding that the Act provided the
exclusive remedy for Villarroel’s claim, the circuit court sustained the plea in bar and dismissed
the complaint with prejudice. Villarroel appeals, arguing that the circuit court misapplied the
Act, misapplied the burden of proof, and disregarded Skelley’s testimony.
ANALYSIS
When an appellate court reviews a ruling on a plea in bar on which the parties have
presented evidence “ore tenus, the circuit court’s factual findings ‘are accorded the weight of a jury
finding and will not be disturbed on appeal unless they are plainly wrong or without evidentiary
support.’” Cornell v. Benedict, 301 Va. 342, 349 (2022) (quoting Massenburg v. City of Petersburg,
298 Va. 212, 216 (2019)). To the extent the review rests on legal questions, including statutory
construction, we review de novo. Id.
There are two main ways in which a court can establish evidentiary support for a plea in bar:
“based on a discrete body of facts identified by the parties through their pleadings, or developed
through the presentation of evidence supporting or opposing the plea.” Hawthorne v. VanMarter,
279 Va. 566, 577 (2010). On the latter, “if the facts are disputed and no demand for a jury is made,
the ‘whole matter of law and fact’ may be decided by the court.” Ferguson Enters., Inc. v. F.H.
Furr Plumbing, Heating & Air Conditioning, Inc., 297 Va. 539, 549 (2019) (quoting Hawthorne,
279 Va. at 578).
To enable parties to present supporting evidence for a plea in bar, a trial court may hold an
evidentiary hearing and this Court may rely on that evidence even in the absence of any other
evidence. See Fines v. Rappahannock Area Cmty. Servs. Bd., 301 Va. 305, 312 (2022). Indeed,
-4- precedent indicates that in some circumstances the trial court must hold an evidentiary hearing to
establish evidentiary support when presentation of evidence is necessary. See Montalla, LLC v.
Commonwealth, 303 Va. 150, 173 (2024) (“In making this factual finding . . . the Court of Appeals
strayed from its proper role . . . . [T]he circuit court conducted no evidentiary hearing on the
Commonwealth’s plea of accord and satisfaction, and thus, made no formal factual finding based on
the evidence . . . .” (emphasis omitted)); Kole v. City of Chesapeake, 247 Va. 51, 57 (1994) (“We
also conclude that the trial court erred in refusing to conduct an evidentiary hearing as requested by
the [plaintiffs].”).
This case is distinguishable from those in which the trial court failed to establish evidentiary
support before ruling on a plea in bar. Here, there was an in-person evidentiary hearing. In the
hearing, two witnesses, called by BCN and Railing Systems separately, testified as to the facts
relating to BCN’s contract to build the home, Villarroel’s role as a subcontractor in that work, and
Railing Systems’ role as a subcontractor in that work. As noted above, the trial court made
numerous findings of fact and law based on evidence from this hearing. Pertaining to evidentiary
support specifically, it found that Railing Systems was contracted to fabricate and install the grate,
that “Railing Systems was not a delivery service of material,” that the installation was “part of the
construction of the residential structure,” and, thus, that “Virginia Code [§] 65.2-302(b) and
[§] 65.2-307 apply.” The evidentiary hearing and the findings of fact indicate that the trial court
sought and found evidentiary support for the judgment on the plea in bar.
I. The circuit court correctly applied the Workers’ Compensation Bar.
a. The Scope of the Contracts
Workers’ compensation benefits generally provide the “exclusive remedy for a workplace
injury falling within the Act.” Hartford Underwriters Ins. Co. v. Allstate Ins. Co., 301 Va. 460, 469
(2022). Code § 65.2-307(A) prevents a covered employee or his administrator from seeking “any
-5- other remedy against the employer or his fellow employees.” Jones v. Commonwealth, 267 Va.
218, 222 (2004).
The Act applies when “an employment relationship of some kind” exists between the
claimant and the defendant. Jeffreys v. Uninsured Emp.’s Fund, 297 Va. 82, 90 (2019). In addition
to basic employer/employee relationships, the Act recognizes an additional “category of
employment relationship called ‘[s]tatutory employer.’” Id. (citing Code § 65.2-302). These
classifications of the employer-employee relationship—“true” and “statutory”—govern who is
entitled to workers’ compensation coverage and, conversely, who, because of a lack of coverage, is
entitled to maintain an independent civil suit.4 See id.; accord Pfeifer v. Krauss Constr. Co. of Va.,
Inc., 262 Va. 262, 266-67 (2001) (citing Code § 65.2-307(A)). Like employers and employees in a
true employment relationship, statutory employers and employees are bound by the exclusivity
provisions of Code § 65.2-307(A), which limit a covered employee to the “rights and remedies”
under the Act. See Jones, 267 Va. at 222.
Whether a particular person or entity was the statutory employer of an injured employee
presents a “mixed question of law and fact that must be determined under the facts of each case.”
Moore v. Va. Int’l Terminals, Inc., 283 Va. 232, 235 (2012) (quoting Bosley v. Shepherd, 262 Va.
641, 648 (2001)). As a result, the Court reviews the factual components of that determination for
plain error and considers application of the relevant law de novo. See Cornell, 301 Va. at 349.
A company or individual may be a statutory employer of the employees of certain
subcontractors. See Jeffreys, 297 Va. at 90-92 & 92 nn.3-4. Code § 65.2-302 provides that the
person or business is liable for workers’ compensation benefits as a statutory employer under
4 If we were to follow the dissent’s lead, the rule for statutory employment would be dramatically underinclusive. The dissent asserts that relevant to the analysis of this rule is the degree of supervision and control exercised over the task being performed – virtually the same test undertaken in reviewing a basic employer/employee relationship. Clearly, precedent dictates otherwise. -6- specified circumstances. See Princess Anne Builders, Inc. v. Faucette, 37 Va. App. 102, 109-12
(2001). Code § 65.2-302(A) and (B) set out two tests for coverage of an employee under the Act by
a statutory employer. Id. at 109-11 (citing Cinnamon v. Int’l Bus. Machs. Corp., 238 Va. 471, 476
(1989)) (noting that subsection (C) augments those tests); see Jeffreys, 297 Va. at 90-92 & 92
nn.3-4. Subsection (A) establishes the “normal-work test,” and subsection (B), treated as an
exception, sets out the “subcontracted-fraction test.” Princess Anne Builders, 37 Va. App. at 110-11
(quoting Cinnamon, 238 Va. at 476). If either test applies, the worker is a statutory employee
covered by the Act, preventing him from suing his statutory employer or any of his statutory
co-employees. Jeffreys, 297 Va. at 90-92; Pfeifer, 262 Va. at 266-67.
The normal-work test provides coverage under the Act to “all persons engaged in any work
that is a part of the trade, business or occupation of the original party who undertakes as owner, or
contracts as contractor, to perform that work.” Jeffreys, 297 Va. at 92 n.5 (quoting Cinnamon, 238
Va. at 475 n.1). So, “every such owner, or contractor, and subcontractor” who is higher in the chain
above an employee is liable as a statutory employer for injury to the employee. See id. (quoting
Cinnamon, 238 Va. at 475 n.1).
The “subcontracted-fraction test” relates to determining statutory-employer status under
Code § 65.2-302(B) and (C). Princess Anne Builders, 37 Va. App. at 110. When the owner’s trade,
occupation, or business is different from the general contractor’s, courts look to see whether the
work that caused the accident is “obviously a subcontracted fraction of [that] contract.” Cinnamon,
238 Va. at 476 (alteration in original). If the subcontractor’s work is a fraction of the general
contractor’s contract, then the general contractor “is the statutory employer of the injured worker,
whether directly employed by the primary subcontractor or by a secondary subcontractor.” Princess
Anne Builders, 37 Va. App. at 111. For example, in Princess Anne Builders, the general contractor
-7- was a statutory employer of the tree removal company because tree removal was a
subcontracted-fraction of the main sales contract for the home. Id. at 112.
Here, BCN subcontracted a fraction of the construction project to both Pristine and Railing
Systems. Pristine’s punchout work and Railing Systems’ installation of the grate were elements of
the construction project that were critical to fulfilling BCN’s contract. Both Railing Systems and
Pristine, and their employees, undertook a portion of BCN’s home-construction project, and
therefore they were engaged in BCN’s work.
The dissent makes much of the fact that the parties did not include the contract in the record.
According to the dissent, Railing Systems “failed to meet its burden to show that . . . [the]
subcontracted fraction test applied.” The dissent supports this claim by asserting that “the contract
was never produced or introduced into evidence,” and consequently, “we do not know what was in
it.” Further, “[t]he circuit court received into evidence no document dictating the scope or contents
of the contract.”
Yet, in this case the content of the contract is an issue of fact that was resolved by the trial
court. “[W]hen an issue is raised whether . . . other evidence of contents correctly reflects the
contents, the issue is for the trier of fact to determine.” Rule 2:1008. It is undisputed that BCN was
under contract to complete a residential construction project and that both Villarroel’s employer and
Railing Systems were under contract with BCN. Here, the trial court took testimonial evidence as
sufficient to establish the scope of BCN’s construction contract as well. The testimony of BCN’s
owner, Brian Normile, indicates that BCN was under a “general contract for construction of a
property” at the address and “was contracted to build this home.” More explicitly, “[t]he work that
Railing Systems completed for BCN Design Build was work that was required under BCN Design
Build’s contract to build the home.” Counsel for Villarroel agreed that this last fact is
-8- “undisputed.”5 Accordingly, the subcontracted-fraction test is satisfied in this case. See Whalen v.
Dean Steel Erection Co., 229 Va. 164, 169 (1985) (Act barred tort claim of subcontractor
performing a fraction of the construction work for which general contractor had overall
responsibility).
The dissent would have this Court serve as the factfinder in this case, when that is the job of
the trial court and one already completed here. “[T]he reviewing court is not permitted to
substitute its judgment, even if its view of the evidence might differ from the conclusions
reached by the finder of fact at the trial.” Linnon v. Commonwealth, 287 Va. 92, 98 (2014)
(quoting Lawlor v. Commonwealth, 285 Va. 187, 224 (2013)). The argument presented by the
dissent is that the record is incomplete in this case because, without the actual contract included, the
trial court had insufficient evidence to determine the scope of the agreements between BCN, Railing
Systems, and Villarroel (via Pristine).6 Yet, it is unclear what we, as an appellate court, would gain
by having the written contract on the record without thereby playing the role of factfinder. We rely
on the undisputed facts of the record presented through witness testimony before the trial court.
According to the dissent we need the written contract because Railing Systems “failed to
show the scope of the construction contract between BCN and Railing Systems.” This
5 The following colloquy occurred between the trial court, counsel for BCN, and counsel for Villarroel:
[Feinstein, counsel for BCN:] BCN Design Build was required to complete [the work done by Railing Systems and Pristine Home Services] under its contract to build the home. [Court:] Is that in dispute? [Porter, counsel for Villarroel:] That issue is not in dispute, your Honor. 6 The dissent appears to draw from our Supreme Court’s analysis in Bosher v. Jamerson, 207 Va. 539 (1966). Contained in the Bosher record was the actual contract relied upon, apparently. The dissent points to the Bosher Court’s language that the case “relied solely on the parties’ contract.” See id. at 542-43. -9- misrepresents the record and obfuscates the issue on appeal. The facts in the record upon which we
rely, none of which are plainly wrong or without evidentiary support, are sufficient for this Court to
move on to answering the legal issues—whether Railing Systems and Villarroel were statutory
co-employees of BCN. The trial court relied on testimony regarding the scope of both the BCN
residential construction contract and BCN’s contract with Railing Systems—the BCN contract
required the work of both the subcontractors in question, and the Railing Systems contract included
only work that was required for BCN to fulfill its residential construction contract. The dissent is
incorrect, since Railing Systems provided enough factual information about the scope of the
contract to decide on the subcontracted-fraction test.
As the facts on record are sufficient for the legal finding we advance here, requiring a
contract can only be relevant if it’s inclusion would raise new evidence that contradicts those
established facts. But that is a factfinding power this Court is not entitled to exercise. The dissent
again misconstrues this opinion, saying that “[t]he majority argues that we must ignore all that we
do not know about the contract.” To the contrary, this opinion asserts that we must not ignore all
that we do know about the contract, especially when, as here, what we know is sufficient to form
the basis of an answer to the legal question at hand.
Again, in requiring the actual contract the dissent can only be looking to find evidence
that contradicts the undisputed facts found by the trial court. It is the trial court’s responsibility
and authority to weigh such evidence to determine the facts and our job to differ only where the
findings are plainly wrong or without evidentiary support, which we do not see here.
The dissent essentially admits the foregoing point. According to the dissent “[p]arties need
not present a physical copy of a contract in order for this Court to find sufficient evidence in the
record. Witness testimony can suffice.” But that witness testimony must show “whether the
installation requirements fell into the subject matter of the contract.” What is clearly established
- 10 - in this case is that “[t]he work that Railing Systems completed for BCN Design Build was work
that was required under BCN Design Build’s contract to build the home.” In other words, the
installation completed for BCN Design Build “fell into the subject matter of the contract [to build
the home].” The dissent hopes for evidence that BCN controlled, supervised, or oversaw the
work by Railing Systems, but fails to establish that any of these features is necessary to meet the
subcontracted-fraction test.
Finally, the dissent cites several Supreme Court cases purporting to show that “our Supreme
Court has not settled for mere evidence of an agreement and instead has looked to the terms of
the contract provided in evidence.” We do not rely on “mere evidence of an agreement” or “the
mere existence of an agreement,” but rather the scope of the contract. None of the cited cases
discuss the necessity of a contract on the record. More importantly, none of them stand for the
proposition that submitting a contract to the record is necessary when testimony provides enough
information to decide the legal question.7 We agree that the contents and scope of the contract
are relevant to the determination of the subcontracted-fraction test, and the testimony on record
here is sufficient to conclude that Railing Systems’ contract with BCN was a subcontracted
fraction of BCN’s contract to build a home.
b. Mere Delivery
Villarroel’s argument that Railing Systems merely delivered the grate is also unsupported by
the evidence. The evidence showed that Railing Systems installed the grate by drilling, bolting,
7 Indeed, except for one of the cases the dissent cites in the paragraph in question, none of them even mention whether there was a contract on record. See Se. Tidewater Area Manpower Auth. v. Coley, 221 Va. 859 (1981); Cooke v. Skyline Swannanoa, Inc., 226 Va. 154 (1983); Rodriguez v. Leesburg Bus. Park, LLC, 287 Va. 187 (2014); Napper v. ABM Janitorial Servs. - Mid Atl., 284 Va. 55 (2012); Cinnamon, 238 Va. 471. The only case that does mention it discusses a photocopy of the agreement to address an issue with the best evidence rule. Carmody v. F.W. Woolworth Co., 234 Va. 198 (1987); see also Myrick v. Commonwealth, 13 Va. App. 333, 339 (1991) (quoting the relevant section of Carmody as instructive for a decision on the best evidence rule). - 11 - measuring, and mounting it. Thus, Railing Systems performed more than delivery, and the cases
limited to delivery are inapposite. See Hipp v. Sadler Materials Corp., 211 Va. 710, 711 (1971)
(holding that Act did not apply because a concrete company was only required to deliver the
concrete—not to spread or finish the concrete); Burroughs v. Walmont, Inc., 210 Va. 98, 100 (1969)
(stacking of sheetrock was not an act of construction, so it was not in the trade or business of the
general contractor).
The dissent mischaracterizes our analysis on this point also, saying “case law does not
mandate that a subcontractor show it is a delivery system to escape the normal-work or sub-
contracted fraction tests.” Neither do we mandate any such thing. However, if the plaintiff argues
that the defendant’s work falls under mere delivery, then the plaintiff is required to show that the
defendant’s work is mere delivery. Villarroel makes exactly that argument. Thus, it was necessary
for this Court to address the argument, concluding Villarroel did not show that Railing Systems
merely delivered the grate in question.
To be statutory co-employees, workers must have an employer or statutory employer in
common somewhere in the chain of employment. See Fowler v. Int’l Cleaning Servs., 260 Va. 421,
426, 428-29 (2000) (holding that a worker employed by an owner was a statutory fellow employee
of a contractor engaged to perform work on the owner’s premises). Here, BCN subcontracted and
paid both Pristine and Railing Systems for work on the construction project, and Pristine paid its
employee Villarroel to complete Pristine’s work. Thus, Villarroel and Railing Systems were
statutory co-employees “entitled to the exclusivity protections of the Act.” David White Crane
Serv. v. Howell, 282 Va. 323, 328 (2011).
II. The circuit court did not shift the burden of proof for the plea in bar to Villarroel.
“Absent clear evidence to the contrary in the record, the judgment of a trial court comes
to us on appeal with a presumption that the law was correctly applied to the facts.” Yarborough
- 12 - v. Commonwealth, 217 Va. 971, 978 (1977). Under that standard, “we will not fix upon isolated
statements of the trial judge taken out of the full context in which they were made, and use them
as a predicate for holding the law has been misapplied.” Id. Reviewing courts consider the
entire record in context. Suffolk City Sch. Bd. v. Wahlstrom, 302 Va. 188, 217 (2023); Coward v.
Wellmont Health Sys., 295 Va. 351, 363 n.11 (2018) (same).
Villarroel argues that the circuit court’s statement from the bench that “this is a burden
that the plaintiff assumed” shows misapplication of the overall burden of proof.8 But in context,
the statement’s focus was that Villarroel failed to establish that Skelley knew welding was
outside a general contractor’s scope of work. Other evidence had suggested general contractors’
work may include welding, and the circuit court was not persuaded that BCN could not perform
welding. The isolated comment did not pertain to all the testimony and evidence, and it did not
impact the trial court’s conclusion. Rather, the circuit court’s ruling, considered in its context,
shows that the circuit court did not place the burden on Villarroel to prove that the Workers’
Compensation Act did not bar Villarroel’s personal injury complaint. Instead, Railing Systems
met its burden to show that the subcontracted-fraction test applied and Villarroel and Railing
Systems were statutory co-employees under the Act.
The dissent states that our analysis “focus[es] on isolated statements”—just what we have
accused Villarroel of doing therein. The claim is that by making much of the idea that BCN
“could weld,” we have ignored the more important question of whether they “do weld.” But this
is irrelevant. Whether BCN could or does weld bears no importance for the question of whether
Railing Systems carried out a sub-contracted fraction of BCN’s work, even if it would bear some
8 Railing Systems was a third-party plaintiff to BCN, and Railing Systems had the burden of proof for its plea in bar. See Baker v. Poolside, 272 Va. 677, 688 (2006). - 13 - importance for the normal-work test. We have been clear that our decision here, as well as the
decision of the trial court, is based on the former, not the latter.
The importance of whether BCN could or does weld is merely in reference to the burden
of proof argument made by Villarroel. Since Villarroel argues that the trial court shifted the
burden of proof, it is incumbent upon us to address the context of the statement he uses to make
the argument. The context includes a discussion of whether a contractor’s being able to perform
work that Railing Systems performed affects the conclusion that Railing Systems was engaged in
the normal work of BCN. Thus, not only is the dissent’s analysis of our treatment of that
statement yet another mischaracterization of our analysis, it is not pertinent to the substance of
the analysis at all.
III. The circuit court did not err in weighing Skelley’s testimony.
We “view the facts in the light most favorable to the party prevailing before the trial
court”—Railing Systems. Bottoms v. Bottoms, 249 Va. 410, 414 (1995). “The credibility of the
witnesses and the weight accorded the evidence are matters solely for the fact finder who has the
opportunity to see and hear that evidence as it is presented.” Elliot v. Commonwealth, 277 Va.
457, 462 (2009). “We give deference to the fact finder who, having seen and heard the
witnesses, assesses their credibility and weighs their testimony.” Id. And where evidence is
conflicting, “it is for the jury to say which witness . . . they will believe and what testimony they
will accept.” Diggs v. Lail, 201 Va. 871, 877 (1960).
Under the Massie doctrine, a litigant’s “statements of fact and the necessary inferences
therefrom are binding upon him.” Massie v. Firmstone, 134 Va. 450, 462 (1922). The Massie
doctrine “is not to be read as a rule of thumb, categorical, absolute, and universally applicable.”
Baines v. Parker, 217 Va. 100, 104 (1976). It “applies only to ‘statements of fact’ made by the
litigant, to statements of facts ‘within his own knowledge’, and to ‘the necessary inferences
- 14 - therefrom.’” Id. The Massie doctrine “does not apply to a litigant’s statement of opinion.”
Beeton v. Beeton, 263 Va. 329, 337 (2002).
Here, Skelley testified that she generally agreed that welding was outside of the skill set
of an average general contractor. She offered this as a lay opinion, and there was no showing
that she had personal knowledge of an average general contractor’s work. Thus, the Massie
doctrine does not apply. See Beeton, 263 Va. at 337 (Massie doctrine did not apply to statement
of opinion). And even if Railing Systems’ corporate designee’s testimony would not have
independently sufficed to show applicability of the Act, the circuit court was permitted to
consider all the testimony and evidence. Nat’l Union Fire Ins. Co. v. Bruce, 208 Va. 595, 600
(1968). Here, there was sufficient record evidence overall to find the subcontracted-fraction test
was met. Thus, we find no error in the circuit court’s weighing of the evidence.
CONCLUSION
We hold that the circuit court did not err by granting Railing Systems’ plea in bar. The
record supports the determination that Villarroel was a statutory co-employee with Railing
Systems and that his claim was consequently barred by the Workers’ Compensation Act’s
exclusivity provisions. We therefore affirm the circuit court’s dismissal of Villarroel’s personal
injury suit.
Affirmed.
- 15 - Causey, J., dissenting.
Whether Railing Systems is the statutory employer of Mr. Villarroel presents a “mixed
question of law and fact that must be determined under the facts of each case.” Moore v. Va. Int’l
Terminals, Inc., 283 Va. 232, 235 (2012) (quoting Bosley v. Shepherd, 262 Va. 641, 648 (2001)).
Here, both the circuit court and the majority incorrectly apply the facts of the present case to the law
at hand.9 Mr. Villarroel cannot be Railing Systems’ statutory co-employee, as Railing Systems
failed to meet its burden to show that either the normal-work or sub-contracted fraction test applied.
See Jeffreys v. Uninsured Emp.’s Fund, 297 Va. 82, 90-92 (2019).
Under the normal-work test, based on the evidence found by the circuit court, BCN and
Railing Systems were not “engaged in any work that is a part of the trade, business or occupation of
the original party who . . . contracts as contractor, to perform that work.” Id. at 92 n.5 (quoting
Cinnamon v. Int’l Bus. Mach. Corp., 238 Va. 471, 475 n.1 (1989)). It is undisputed that, from the
evidence at the plea in bar hearing, the circuit court found that, “based on its own pre-inspection of
the window well area,” Railing Systems ordered the raw materials, cut them to the measurements
taken, welded them together, and primed them with a rustproof coating before installing the grate.
Railing Systems then completed specialized, highly-technical installation work—work that was
performed by certified welders who, using specialized equipment, drilled holes to install mounting
brackets for the ladder, bolted the brackets to the foundation or wall, bolted shelf angles, and
mounted the grate on the shelf angle. BCN could not have performed any of these tasks as part of
its trade, business, or occupation, as BCN did not itself maintain employees. Even BCN’s corporate
designee, Mr. Normile, testified that “BCN wasn’t hired to fabricate anything.”
9 The majority hides behind Yarborough v. Commonwealth, 217 Va. 971, 978 (1977), which notes the presumption that the law was correctly applied to the facts. However, this is a presumption that can be rebutted with “clear evidence to the contrary in the record,” as is the case here. - 16 - Railing Systems never came under the control or supervision of BCN. In this way, BCN is
different from the respondent-corporation in Bosher v. Jamerson, 207 Va. 539, 542-44 (1966), a
case upon which Railing Systems relied to show that specialized subcontractors can be co-
employees of general contractors. In Bosher, the subcontractor worked “as directed by the [general
contractor’s] supervisor.” Id. at 542-43. The Court found that it was only after the subcontractor
came under the supervision and control of the general contractor that it was performing work that
was part of the trade, business, or occupation of the general contractor. Id. Here, there is no
evidence in the record that BCN was actively supervising or controlling the installation of the
custom ironwork. BCN itself maintained no employees; instead, it could be likened to a
headhunter: it merely found subcontractors it could then employ to finish the component jobs. And
even if it did have employees, unlike the general contractor’s supervisors actively working
alongside the subcontracted employees in Bosher, there is no evidence of a BCN supervisor on the
jobsite directing the subcontractors’ activities. See also Bassett Furniture Indus., Inc. v.
McReynolds, 216 Va. 897, 900 (1976) (finding the injured worker was not a statutory co-employee
because the general contractor “had no control over [the subcontractor’s] employees and never
required any ‘specific changes’”).
As a result, Railing Systems, as the movant on the plea in bar, did not present sufficient
evidence to show that manufacturing and fabricating custom-fit ironwork is part of the trade,
business, or occupation of BCN. See Cornell v. Benedict, 301 Va. 342, 349 (2022) (noting the
movant bears the burden of proof on a plea in bar heard ore tenus).
Under the sub-contracted fraction test, likewise, there is no evidence that Villarroel and
Railing Systems are co-employees. Because Railing Systems’ trade, occupation, or business is
different from BCN’s, we must look to see whether the work that caused the accident is “obviously
a subcontracted fraction of [the parties’] contract.” Cinnamon, 238 Va. at 476. If Railing Systems’
- 17 - work is a sub-contracted fraction of BCN’s contract, then BCN “is the statutory employer of the
injured worker, whether directly employed by the primary subcontractor or by a secondary
subcontractor.” Princess Anne Builders, Inc. v. Faucette, 37 Va. App. 102, 111 (2001). In Bosher,
where they found that the general contractor was the statutory employer of the subcontractor, the
Court relied solely on the parties’ contract—that was presented as evidence, unlike the case at bar—
which stipulated that the subcontractor was “obligated” to perform “in such [a] manner as directed
by [the general contractor]” and its subcontractors were instructed to perform their duties “as
directed by the [general contractor’s] supervisor.” 207 Va. at 542-43. Likewise, in Whalen v. Dean
Steel Erection Co., 229 Va. 164 (1985), upon which the majority relies, there was a subcontract
presented into evidence which provided that the subcontractor was to do “a complete job of steel
erection.” Id. at 166 (quoting contract language).
Here, the majority claims that “Pristine’s punchout work and Railing Systems’ installation
of the grate were elements of the construction project that were critical to fulfilling BCN’s
contract.” The majority needlessly spills much ink noting that witness testimony can and did
establish the existence of a contract. Agreed, there is no dispute that a contract existed. Both parties
acknowledged that there was a contract; however, the contract was never produced or introduced
into evidence. Herein lies the problem: we do not know what was in it.
The majority misunderstands the arguments made in this dissent. Parties need not present
a physical copy of a contract in order for this Court to find sufficient evidence in the record.
Witness testimony can suffice. However, that testimony should include the performance
required by both parties to, in fact, show whether one party’s actions are indeed a sub-contracted
fraction of the other’s. Noting only that there was a contract for certain subject matter—here, to
build a home—is not enough to show the terms of that contract, specifically whether the
installation requirements fell into the subject matter of the contract. Here, all we know is that
- 18 - BCN contracted with Railing Systems for custom ironwork. We do not know whether Railing
Systems’ installation of that ironwork was indeed a sub-contracted fraction of the main contract
with BCN because we do not know the price term, the performance terms—including method of
payment, whether BCN was supposed to oversee that installation, or whether they were to
supervise or control it. Nor do we know what was to happen if one of the parties failed to
perform under the contract. For all we know, the contract could have noted that the scope of
BCN’s performance was merely to pay upon delivery of the grates.
Other than vague witness testimony establishing the mere existence of an agreement
between the parties—that Railing Systems would install the custom iron grates—there is no
evidence of the contract in the record. No witness in circuit court testified to its scope or contents.10
The circuit court received into evidence no document dictating the scope or contents of the contract.
As a result, we do not know which party held which role or responsibility. We do not know the
10 The majority seems to think that the witness testimony we have in the record is enough to highlight the terms of the contract between the parties, noting “[t]he work that Railing Systems completed for BCN Design Build was work that was required under BCN Design Build’s contract to build the home.” However, this is merely the explanation of the contract’s subject matter. Our Supreme Court has noted that essential contract terms include price, performance, and definiteness. See, e.g., Wilburn v. Mangano, 299 Va. 348, 353-54 (2020) (“Price is a material term, and it must be either ‘fixed by the agreement itself’ or the agreement must provide a mode ‘for ascertaining it with certainty,’ in order for a court to enforce specific performance.” (quoting Parker v. Murphy, 152 Va. 173, 184 (1929))); Rolfs v. Mason, 202 Va. 690, 692 (1961) (noting the importance of performance terms); Smith v. Farrell, 199 Va. 121, 127-28 (1957) (“Another essential element of a valid contract is certainty and completeness. The element of completeness denotes that the contract embraces all the material terms; that of certainty denotes that each one of those terms is expressed in a sufficiently exact and definite manner. An incomplete contract, therefore, is one from which one or more material terms have been entirely omitted.”). We must then have proof that the parties assented to each of these elements. See Moorman v. Blackstock, Inc., 276 Va. 64, 75 (2008) (“[In all contracts of sale,] mutuality of assent[, which is] the meeting of the minds of the parties[,] is an essential element.”). Railing Systems has not met its burden by providing us with the scope and terms of the contract, as we do not know the materials terms of the contract. See Smith, 199 Va. at 127 (“An uncertain contract is one which may, indeed, embrace all the material terms, but one of them is expressed in so inexact, indefinite or obscure language that the intent of the parties cannot be sufficiently ascertained to enable the court to carry it into effect.”). - 19 - performance required by both parties. We do not know whether BCN would supervise the project
or merely pay upon completion of the service, as was the situation in the many delivery cases noted
by the majority. See, e.g., Hipp v. Sadler Materials Corp., 211 Va. 710, 710-11 (1971). The
majority rightly notes that “we must not ignore all that we do know about the contract.” I contend
that we only know the subject matter.
Without a better understanding of the material terms of the parties’ contractual agreement,
we cannot say that there is enough evidence to establish BCN contracted or was hired to
manufacture and install custom ironwork under its ultimate residential construction contract.
Railing Systems had an opportunity to cross-examine the witness but did not ask any questions
about the contract or the scope of the project. As a result, Railing Systems, as the movant on the
plea in bar, did not present sufficient evidence to show that manufacturing and fabricating custom-
fit ironwork is “obviously” performing a sub-contracted fraction of the main contract. See Cornell,
301 Va. at 349 (noting the movant bears the burden of proof on a plea in bar heard ore tenus).
The majority argues that we must ignore all that we do not know about the contract
because we have limited “fact-finding power” as an appellate court. However, our authorized
appellate review is, by definition, to determine whether a reasonable factfinder could conclude
that the evidence was enough to show Railing Systems’ custom ironwork was a sub-contracted
fraction of the main contract. Because we have no evidence of the performance that was dictated
by the contract, the record cannot support what was dictated by a sub-contracted fraction.
Mathematically, we cannot calculate a fraction without knowing the whole. We do no fact-
finding by merely highlighting what the record contains and—in turn—what it does not.
In fact, in its precedent cases that turned on the sub-contracted fraction test, our Supreme
Court has not settled for mere evidence of an agreement and instead has looked to the terms of
the contract provided in evidence. See, e.g., Se. Tidewater Area Manpower Auth. v. Coley, 221
- 20 - Va. 859, 861-62 (1981) (noting that the contract dictated the subcontractor’s specific duties to
effectuate performance of “public service employment programs,” including to receive federal
funds, render monthly service reports, and furnish data as part of their performance, and request
written permission from the general contractor if the subcontractor diverged from these
stipulated terms); Cooke v. Skyline Swannanoa, Inc., 226 Va. 154, 156 (1983) (noting the
controlling term of a license agreement “provides that a substantial and material violation of any
of its terms gives [the general contractor] the right to terminate the license”); Rodriguez v.
Leesburg Bus. Park, LLC, 287 Va. 187, 191 (2014) (quoting the contract, which stipulated that
the subcontractor was “‘solely responsible for doing all of the components to build the building’”
and “‘fully in charge’” of construction, and “was not responsible for obtaining building permits,
paying utility fees, ‘[m]oving . . . the power lines,’ or providing ‘signage for the project’”
(alterations in original)); Napper v. ABM Janitorial Servs. - Mid Atl., 284 Va. 55, 59-60 (2012)
(listing the specificities of performance in a cleaning contract, including which rooms were to be
cleaned on which days and even ensuring certain listed products like “Windex, Clorox, toilet
paper and paper towel[s]” were in each room (alteration in original)); Cinnamon, 238 Va. at 473
(noting, under the “conditions to the contract,” in part, that the general contractor reserved the
rights to “prepare plans and specifications, to approve any changes [the subcontractor] might
make in its project manager and general superintendent, to control access to the job site and the
amount of dust generated by traffic, to issue and approve change orders, to review job progress
reports, and to approve material suppliers and subcontractors”); Carmody v. F.W. Woolworth
Co., 234 Va. 198, 200 (1987) (noting the general contractor “offered as evidence a photocopy of
a license agreement in which [it] granted to [a subcontractor] a license to operate a portrait
photography department in Woolworth’s stores, and a photocopy of that portion of an employee
- 21 - manual describing procedures to be followed by Woolworth employees in regard to
[subcontractor] operations in Woolworth’s stores”).11
The majority also notes that, because Railing Systems installed the grate by drilling,
bolting, measuring, and mounting it, Railing Systems “performed more than delivery, and the cases
limited to delivery are inapposite.” However, Railing Systems failed to show the scope of the
construction contract between BCN and Railing Systems. As an appellate court with limited “fact-
finding power,” we cannot say affirmatively whether the contract was for more than mere delivery.
Assuming without deciding if we could find there was no more than delivery, the delivery cases
show only one avenue that a court can use to find a subcontractor is not in the trade, occupation, or
business of the general contractor. Importantly, case law does not mandate that a subcontractor
show it is a delivery system to escape the normal-work or sub-contracted fraction tests.
The majority finally notes that the circuit court was not persuaded that BCN could not
perform welding. In so doing, it has accused Mr. Villarroel of focusing on isolated statements.
And yet this is what the majority has done. The fact that BCN could weld does not mean they do
weld. See Bassett Furniture, 216 Va. at 903 (“Mere capacity to perform, standing alone, is not
determinative” of what is “normally carried on” by the general contractor.). And the record, by
way of Mr. Normile’s undisputed testimony, shows that—as part of its regular trade, occupation,
or business—BCN does not weld custom ironwork. Instead, BCN hires specialized welders to
perform that task.
11 The majority states that “except for one of the cases the dissent cites in the paragraph in question, none of them even mention whether there was a contract on record.” First, the joint appendices and records of the cases cited after 1990 confirms that there were physical contracts in the record. Second, the majority’s analysis again misses the point: the Court’s analysis in all of the cases noted in this dissent reveals that the Court was presented with evidence of specific, material contractual terms, many of which were discussed in granular detail. - 22 - Railing Systems did not meet its burden to show that either the normal-work or sub-
contracted fraction test applied, so it did it show that Villarroel and Railing Systems were
statutory co-employees under the Workers’ Compensation Act. Therefore, Mr. Villarroel should
recover for a painful accident that occurred on the jobsite at no fault of his own. For this reason, I
respectfully dissent.
- 23 -