RONALD ADAMS CONTR. v. Miss. Transp. Com'n

777 So. 2d 649, 2000 WL 1678973
CourtMississippi Supreme Court
DecidedNovember 9, 2000
Docket1999-CA-00255-SCT
StatusPublished

This text of 777 So. 2d 649 (RONALD ADAMS CONTR. v. Miss. Transp. Com'n) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RONALD ADAMS CONTR. v. Miss. Transp. Com'n, 777 So. 2d 649, 2000 WL 1678973 (Mich. 2000).

Opinion

777 So.2d 649 (2000)

RONALD ADAMS CONTRACTOR, INC.
v.
MISSISSIPPI TRANSPORTATION COMMISSION.

No. 1999-CA-00255-SCT.

Supreme Court of Mississippi.

November 9, 2000.
Rehearing Denied March 1, 2001.

*650 Phil B. Abernethy, Richard M. Dye, Jackson, Attorneys for Appellant.

James T. Metz, Grenada, Alan M. Purdie, Ridgeland, Attorneys for Appellee.

BEFORE PRATHER, C.J., McRAE and COBB, JJ.

McRAE, Justice, for the Court:

STATEMENT OF THE CASE

¶ 1. This case comes before the Court on appeal from summary judgment. A contractor had a contract dispute with the Mississippi Transportation Commission ("Commission") over ambiguities regarding payment for additional work. We have held in the past that ambiguities in a contract are to be construed against the drafter. A genuine issue of material fact sufficient to send this matter before a jury does exist. Therefore, the lower court erred in awarding partial summary judgment to the Commission. Accordingly, we reverse the judgment of the trial court and remand the case for further proceedings in accordance with this opinion.

¶ 2. On July 15, 1996, Ronald Adams Contractor, Inc. ("Adams") filed a complaint in the Circuit Court of the First Judicial District of Hinds County, Mississippi, against the Mississippi Transportation Commission for damages arising out of a contract between Adams and the Commission for improvements to a portion of United States Highway 45 known as "the Meridian Bypass." Adams alleged *651 that it encountered site conditions on the Highway 45 Project which were different from the site conditions represented in the contract documents prepared by the Commission, that the Commission directed Adams to perform additional work not included in the contract documents, and that the Commission then refused to compensate Adams fully for the additional work it ordered the construction company to perform. Adams's complaint raised the following causes of action: (1) breach of contract, (2) breach of implied warranty, (3) constructive change to the contract, (4) differing site condition, and (5) material mistake or misrepresentation of fact.

¶ 3. On August 14, 1998, the Commission filed a motion for partial summary judgment and argued that a special provision of the contract required that, when differing site conditions were encountered, Adams was to provide a written notification to the Commission's engineer prior to performing additional work. The Commission claimed that Adams failed to comply with this written notice provision of the contract. The trial court granted the Commission's motion for partial summary judgment. A motion to reconsider and for additional time filed by Adams was denied by the trial court. A final judgment pursuant to M.R.C.P. 54(b) was entered on February 17, 1999. Feeling aggrieved, Adams appealed.

STATEMENT OF THE FACTS

¶ 4. The Commission issued plans and specifications as part of the public bid documents for the U.S. Highway 45 Bypass Project in Meridian, Mississippi. Contractors were invited to submit prices for construction of the project based upon the plans and specifications issued by the Commission. Adams submitted the lowest responsive bid and was awarded a contract by the Commission to construct the project. Adams's contract was for construction of what is known as a "dirt job" or "grading job," requiring Adams to do all grading, drainage, and dirt work necessary to establish the base for the roadway.

¶ 5. The contract required Adams to "cut" hills and other high areas along where the new roadway would be situated, and to "fill" the valleys or low areas. The plans and drawings issued by the Commission were utilized by Adams in preparing its bid price. The plans, which were incorporated into the contract between the Commission and Adams, specified a "grade line," or grade elevation, throughout the length of the new roadway. In high areas, this grade line dictated the depth to which Adams would need to cut, and the grade line also dictated the amount of material which would be filled to get to the appropriate roadway elevation in the "low" areas.

¶ 6. The contract included by reference the Mississippi Standard Specifications for Road and Bridge Construction (standard specifications) (1976 ed.), a Special Provision "Differing Site Conditions" clause (S.P. No. 907-104-10), soil borings, profiles, and other special provisions.

¶ 7. As construction of the project progressed, Adams encountered numerous areas along the proposed roadway where the soil condition at the Commission's designated grade line was unacceptable to the Commission. At each of these locations, the normal operations of Adams would be interrupted and the Commission's engineer would determine how long, wide and deep below the grade line this unacceptable material extended. The engineer would then direct Adams to "undercut" the unsuitable material below the grade line and "backfill" the excavation with suitable material. The Commission recorded these observations and directives in a separate "Field Notebook" specifically documenting the exact length, width, and depth to which the Commission's engineer directed Adams to excavate.

¶ 8. William Ricky May, the Commission's on-site project engineer, conceded that this process of interrupting the construction activities when unsuitable material *652 was encountered at the grade line significantly impacted Adams's efficiency and cost for performing the work. Despite this impact, the Commission only compensated Adams for every cubic yard of dirt excavated and backfilled below the grade line at the original contract unit cost for standard, large quantity dirt movement. The original contract provided for three payment items: muck, excess, and unclassified excavation. All undercutting and backfilling was paid as unclassified excavation.

¶ 9. When the Commission refused to adjust the contract and pay Adams additional compensation for cost and expenses incurred in excavating and backfilling areas below the grade line, Adams filed this lawsuit to recover its additional costs. The Commission moved for partial summary judgment, claiming that it was not required to compensate Adams for the extra work since Adams failed to give a written notice to the Commission prior to performing the extra work not delineated in the contract and since Adams failed to secure a supplemental agreement executed by the full Commission prior to performing the extra work. The Commission's motion was granted by the circuit court.

STATEMENT OF THE ISSUES
I. WHETHER THE TRIAL COURT ERRED IN GRANTING THE COMMISSION'S MOTION FOR PARTIAL SUMMARY JUDGMENT.
II. WHETHER THE TRIAL COURT ERRED IN DENYING RONALD ADAMS'S MOTION TO RECONSIDER AND FOR ADDITIONAL TIME TO CONDUCT DISCOVERY.

DISCUSSION OF LAW

I. WHETHER THE TRIAL COURT ERRED IN GRANTING THE COMMISSION'S MOTION FOR PARTIAL SUMMARY JUDGMENT.

¶ 10. The circuit court's grant of summary judgment is reviewed by this Court de novo. Hernandez v. Vickery Chevrolet-Oldsmobile Co., 652 So.2d 179, 181 (Miss.1995). The Court's review is governed by the same standard used by the circuit court under Rule 56(c) of the Mississippi Rules of Civil Procedure. Brown v. Credit Ctr., Inc., 444 So.2d 358, 362 (Miss.1983). The evidence must be viewed in the light most favorable to the party against whom the motion is made. Id.

¶ 11. The burden of demonstrating that no genuine issue of material fact exists is on the moving party. Id. at 368.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Credit Center, Inc.
444 So. 2d 358 (Mississippi Supreme Court, 1983)
Hernandez v. VICKERY CHEVROLET-OLDS. CO.
652 So. 2d 179 (Mississippi Supreme Court, 1995)
Bruner v. University of Southern Mississippi
501 So. 2d 1113 (Mississippi Supreme Court, 1987)
Estate of Parker v. Dorchak
673 So. 2d 1379 (Mississippi Supreme Court, 1996)
Theobald v. Nosser
752 So. 2d 1036 (Mississippi Supreme Court, 1999)
Churchill v. Pearl River Basin Dev. Dist.
619 So. 2d 900 (Mississippi Supreme Court, 1993)
Pursue Energy Corp. v. Perkins
558 So. 2d 349 (Mississippi Supreme Court, 1990)
Forbes v. COLUMBIA PULP & PAPER COMPANY, INC.
275 So. 2d 92 (Mississippi Supreme Court, 1973)
Miss. Transp. Com'n v. Ronald Adams Cont.
753 So. 2d 1077 (Mississippi Supreme Court, 2000)
Leach v. Tingle
586 So. 2d 799 (Mississippi Supreme Court, 1991)
Thompson v. JONES CTY. COMMUNITY HOSPITAL
352 So. 2d 795 (Mississippi Supreme Court, 1977)
Pearl Realty Co. v. State Highway Commission
154 So. 292 (Mississippi Supreme Court, 1934)
Shell Petroleum Corp. v. Yandell
158 So. 787 (Mississippi Supreme Court, 1935)
Mississippi State Highway Commission v. Sanders
269 So. 2d 350 (Mississippi Supreme Court, 1972)
F. P. Baylot v. Habeeb
147 So. 2d 490 (Mississippi Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
777 So. 2d 649, 2000 WL 1678973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ronald-adams-contr-v-miss-transp-comn-miss-2000.