Romono Oolitic Stone Co. v. Missouri Valley Bridge & Iron Co.

173 Ill. App. 534, 1912 Ill. App. LEXIS 450
Appellate Court of Illinois·Decided October 7, 1912·Published·Cited by 1 cases

Opinion

Mr. Justice Shirley

delivered the opinion of the court.

This was an action in assumpsit by appellant to recover from appellee damages resulting from an alleged breach of contract. The declaration contained three special counts also the common counts. The first special count alleged a completion of the contract, and claimed the sum of $4,043.67 as the balance due which was the amount retained by appellant until the contract was completed, and as the court found for appellant on that count and rendered a judgment for the sum claimed, it is unnecessary to set it forth.

The second special count among other things averred that appellant agreed to furnish appellee all Bed-ford stone required for the four main piers of the Municipal Bridge which was being constructed by the City of St. Louis across the Mississippi Eiver, cut and dressed according to the plans and specifications of the engineers of said bridge; that prior to entering into said agreement appellee furnished appellant specifications of the engineer of said bridge for appellant’s examination in order that it might make a bid upon the stone which was to be furnished for the stonework of the bridge; that of said specifications clause 26 provided :

“The general form, character and details for the masonry of the piers are shown upon the drawings. In general it will consist of first class rock faced Ashlar facing, with concrete hearting, coping, pedestal blocks, and special corners and shapes will be made to detail drawings furnished by the president; the balance of the Ashlar to be coursed to suit the convenience of the quarry, but subject to the approval of the President. Preference is hereby expressed for two foot courses.”

It was further averred that appellant in making its bid for the stone and for which said contract was after-wards made based it upon said clause 26 of the specifications ; that relying upon such specifications that the Ashlar which was the courses of layers of stone with which the piers were veneered would be coursed to suit the convenience of the quarry, appellant agreed to furnish said Ashlar stone for the sum of $9.10 per cubic yard f. o. b. cars East St. Louis; that after making said contract appellee elected to change the terms of said contract in this, that instead of appellant furnishing the Ashlar to suit the convenience of the quarry appellee ordered appellant to furnish Ashlar in courses of two feet; that appellant when so ordered informed appellee that furnishing the Ashlar that way would make an extra cost of $1.50 per cubic foot above the contract price; that appellant forwarded the Ashlar as so required and which appellee accepted and used and which amounted to the extra sum of $5,421.72.

The court (a jury being waived) found the issues raised by the second count and plea thereto in favor of appellee, and found there was nothing due appellant on that count. Error is assigned on the finding on the second count and that will be first considered.

The clauses of the contract which are material were, that the stone should be cut and dressed in accordance with the plans and specifications of the engineers and subject to the inspection, approval and acceptance of the engineers of the Municipal Bridge, and for all rock faced stone appellant should be paid $9.10 per cubic yard f. o. b. cars East St. Louis. It was further provided that the stone should be furnished in accordance with the course plans furnished by appellee and approved by the engineers.

Appellant insists that requiring it to furnish the stone in two-foot courses was not according to the written contract, which it is claimed included clause 26 of the specifications, hut a departure therefrom, which necessitated the furnishing of additional labor and material for which appellant had a right to recover under the second count and also under the common counts.

Clause 26 of the specifications in evidence standing alone is somewhat ambiguous. There arises some doubt whether it is to be interpreted as providing that the stone should be coursed to suit the convenience of the quarry as claimed by appellant, or should be stone coursed subject to the approval of the president of the Municipal Bridge Company. Assuming that said clause should be regarded as entering into and being a part of the contract between the parties it is' a familiar rule that in a doubtful case the interpretation which the parties themselves have by their conduct practically given the contract will prevail. Bishop on Contracts, 598. “The construction which the parties have by their acts placed on an ambiguous instrument is entitled to great if not controlling weight in determining its proper construction.” Am. & Eng. Ency. 2nd Ed., Vol. 17, p. 24, and cases cited.

At the time said clause 26 of the specifications was furnished appellant, the engineers of the Municipal Bridge had not furnished the plans for the stonework in the piers. They were furnished later and after this contract between appellant and appellee was made. Appellant had clause 26 before it, and says it contracted in view of its provisions. Yet by the terms of the contract it agreed that the stone should be cut and dressed in accordance with the plans and specifiecations of the engineers of the bridge, and should be furnished according to the course plans furnished by appellee and approved by the engineers. It is apparent from these provisions of the contract that appellant and appellee understood and construed clause 26 to mean that the course plans were not fixed by clause 26 but were yet to be fixed by the engineers.

That this was appellant’s construction of the contract at that time is also quite apparent from the correspondence between the parties after the plans of the engineers providing for two-foot courses were furnished. In a letter to appellee’s engineer appellant wrote: “The plans have been received and we note you have 2,0" almost throughout. This makes it rather hard for our work and cutting would be greatly facilitated if you could make your courses, some a little greater and some a little smaller so as to allow it some leeway on the bed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Romono Oolitic Stone Co. v. Missouri Valley Bridge & Iron Co., 173 Ill. App. 534, 1912 Ill. App. LEXIS 450 (Ill. Ct. App. 1912).

173 Ill. App. 534 (Romono Oolitic Stone Co. v. Missouri Valley Bridge & Iron Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Marks v. Twohy Bros.
194 P. 675 (Oregon Supreme Court, 1921)