Romohr v. Frank
This text of 485 N.E.2d 841 (Romohr v. Frank) is published on Counsel Stack Legal Research, covering Clermont County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
A petition for appropriation was filed on April 22, 1982. Defendants, Armin Frank et al., filed their answer and jury demand on July 9, 1982. On June 5, 1984, plaintiffs, Dale F. Romohr et al., filed a motion in limine requesting a pretrial order limiting the testimony and evidence as to a taking as to damages to property beyond the property sought to be appropriated. On June 22, 1984, plaintiffs filed a motion to introduce new evidence consisting of ancient documents purporting to establish the width of the right of way of the turnpike as forty feet wide at the site to be appropriated for sewage pipe installation. Various memoranda have been submitted in support of and in opposition to these motions. The court permitted consideration of the new evidence which did not conclusively prove the grant of a highway easement.
Defendants assert that they are entitled to submit evidence at trial pertaining to damages for the “taking” of the property contiguous to the roadside ditch where plaintiffs installed the sanitary sewer line. Defendants argue that they are so entitled because the installation of sewerage lines for the transmission of effluent and wastewater constitutes an increased burden on their estate, because there is no evidence which demonstrates that the roadway easement is actually forty feet, and because the easement does not extend beyond the roadside ditch by prescription as the county easement has not been continuous for the prescriptive period of twenty-one years.
Plaintiffs assert on the other hand that ancient documents viewed in conjunction with more recent surveys of the roadside easement establish that the easement extends beyond the actual surface of the road approximately eleven feet within which area the county constructed the pipeline, that defendants are estopped to deny the easement’s width, and that the pipeline is no added burden on the fee of defendants. Thus, plaintiffs argue that defendants are not entitled to any compensation for a permanent take but only for compensation for the temporary take which overlapped onto defendants’ land beyond the easement. In any event, no recorded easement for highway purposes has ever been recorded but that the easement has been in existence in part (road plus ditch) for over twenty-one years.
The threshold issue, assuming ar-guendo that a highway easement does exist, is whether the construction or in[5]*5stallation of a sanitary sewerage pipeline for the transmission of effluent, wastewater, or waste material within this public roadway or highway easement constitutes an added burden upon the servient estate in fee of the landowner for which a landowner is entitled to compensation for a permanent take. Based upon pertinent Ohio case law and upon the reasoning of the Supreme Courts of various sister states which have addressed the identical issue herein presented, the court finds that the installation of sewage pipelines is a permissible highway easement purpose, which does not add to the burden upon the servient estate.
Defendants cite the court to Whitney v. Toledo (1906), 19 Ohio C.D. 74, 8 Ohio C.C.(N.S.) 577, for the proposition that a sanitary sewer constitutes an additional compensable burden. Further, they cite McCabe v. Hood (1895), 5 Ohio C.D. 292, 13 Ohio C.C. 621, for the proposition that the right to drain sewage is a material enlargement of the right to drain water.
Plaintiffs cite the court to Ziegler v. Ohio Water Serv. Co. (1969), 18 Ohio St. 2d 101 [47 O.O.2d 244], for its holding that the construction and maintenance of a subsurface water pipeline in the area of an easement for highway purposes, which pipeline is for public purposes, does not constitute an added burden for which compensation must be awarded. The Ziegler court reasoned: “We are unable to discern any substantial burden visited on * * * [the landowner’s] property by the intended construction. A denial of the use of a highway for the purpose of transporting water to areas where it is needed, as in the instant case, would be the rejection of evolutionary change.” Id. at 106. Plaintiffs urge this court to extend the Ziegler holding to the installation of sewage pipelines which are for the public good.
A thorough review and scrutinization of the decisions of various other state Supreme Courts demonstrate that such an extension of Ziegler comports with modern views about highway easements.
In Bentel v. Bannock (1983), 104 Idaho 130, 656 P.2d 1383, the Supreme Court of Idaho determined that an easement in a county road includes the right to install subsurface pipelines for the transmission of effluent and waste material. Citing Yale Univ. v. New Haven (1926), 104 Conn. 610, 134 A. 268, 271, and 11 McQuillan, Municipal Corporations (3 Rev. Ed. 1977), Section 31.18, the Bentel court found that the installation of sewage pipelines in a roadway easement does not increase the burden on a servient estate as the scope of a public road easement is comprehensive enough to include “reasonably foreseeable public uses of such roadways, such as subsurface installations for sewage, runoff, communications and other services necessary to the increased quality of life which generally accompanies the growth of civilization.” Id. at 133, 656 P.2d at 1386.
Additionally, in Bolinger v. Bozeman (1972), 158 Mont. 507, 493 P.2d 1062, the high court of Montana, citing Minneapolis Gas Co. v. Zimmerman (1958), 253 Minn. 164, 91 N.W. 2d 642, 649, found that a roadway easement in a highway includes the usage of sanitary sewer pipelines and that the use of right of ways by utilities is one of the proper and primary purposes for which highways are designed, even though the principal use is for travel and transportation.
The court believes that Ohio should adopt the rationale employed by the Idaho and Montana courts and that this holding is a natural and logical extension of the Ziegler decision. The court would note that but for the manholes accompanying the sewage pipelines, these pipes are no greater a visual impairment than water lines would be. As to defendants’ [6]*6claim that the sewer lines might emit foul or noxious odors constituting an additional impairment of enjoyment, the court would note that a similar argument was advanced in Solon v. Smiley (1967), 12 Ohio Misc. 269 [41 O.O.2d 78], but was found by the court to be speculative and was given no consideration by the court.
The next issue to be addressed is whether plaintiffs may submit to the triers of fact evidence of the width of the prescriptive or actual highway easement. The evidence is undoubtedly relevant, for it tends to demonstrate the boundaries of the alleged easement, the purpose for which its introduction is sought. As a document over twenty years in age, it is authenticated under Evid R. 901, per example (B)(8), as it is in such condition as to arouse no suspicion concerning its authenticity, and was in a location where, if authentic, it would have likely been. Further, it is admissible hearsay under Evid. R. 803(16) as an authenticated ancient document to be considered as attendant to the motion in limine.
The ultimate issues presented by the motion in limine,
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
485 N.E.2d 841, 20 Ohio Misc. 2d 4, 20 Ohio B. 207, 1984 Ohio Misc. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/romohr-v-frank-ohctcomplclermo-1984.