Rome Electric Co. v. R. & F. Construction, Inc.

70 Pa. D. & C.2d 168, 1974 Pa. Dist. & Cnty. Dec. LEXIS 105
CourtPennsylvania Court of Common Pleas, Indiana County
DecidedApril 10, 1974
Docketnos. 25, 26
StatusPublished

This text of 70 Pa. D. & C.2d 168 (Rome Electric Co. v. R. & F. Construction, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Indiana County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rome Electric Co. v. R. & F. Construction, Inc., 70 Pa. D. & C.2d 168, 1974 Pa. Dist. & Cnty. Dec. LEXIS 105 (Pa. Super. Ct. 1974).

Opinion

HANDLER, J.,

R & F Construction, Inc. became vested with title to a certain tract of land in the Third Ward of the Borough of Indiana (southwest corner of Eighth and Church Streets) by deed dated April 8, 1971, and recorded July 14, 1971, in the Recorder’s Office of Indiana County in Deed Book volume 624, page 831. Thereafter, R & F Construction Company entered into a contract with H. G. Ward, Inc., as general contractor, to erect an apartment building on the land. R & F as owner and H. G. Ward as contractor executed a waiver of hen which was filed in the office of the Prothonotary of Indiana County on September 21, 1971 to no. 4, December term 1971. R & F encountered insurmountable financial difficulties, and, having delivered certain judgment notes to Rome Electric Co., Inc., and James Banda, Inc., subcontractors of H. G. Ward, the sheriff of Indiana County exposed the land and nearly completed structure to a sale on the executions of Rome Electric and James Banda.

This litigation finds its origins in certain exceptions which were taken by Rome Electric Co., Inc., and James Banda, Inc., to the distribution of the proceeds of a sheriffs sale held December 15,1972, by the Sheriff of Indiana County. The distribution provided for full payment of a mechanics’ lien claim entered in this court at no. 17, December term 1972, in which Houston-Starr Company, hereinafter Houston, was plaintiff and in the amount of $16,265.61. By memorandum and order of this court dated March 8, 1973, this matter was referred to G. W. Musser, Esq., a member of the bar of Indiana County, for audit.

The auditor took testimony on June 21, 1973. He filed his report on November 12, 1973, the effect of which was to disallow the mechanics’ hen of Hous[170]*170ton. In accordance with the report of the auditor, this court filed a proposed distribution on December 28, 1973. Exceptions were filed to the auditor’s report and the proposed distribution of the court by Houston and later argued. Accordingly, not only has the litigation been protracted but also it involves certain questions relating to a mechanics’ lien, an area of the law considered by most lawyers to be arcane.

DISCUSSION

Houston’s mechanics’ hen claim is based on a certain contract or contracts between R & F Construction, the owner, and Houston. There is no evidence and no contention on the part of exceptants that Houston dealt contractually with the general contractor, Ward. The auditor found as a fact that there was no “identifiable” contract or contracts between R & F Construction, the owner, and Houston for an agreed sum covering the materials furnished in the construction by Houston. The auditor also found as a fact that the mechanics’ hen claim was not filed within four months as required by the relevant law. On this basis, the mechanics’ hen claim was disallowed. This court must respectfully disagree with the auditor.

A mechanics’ hen is a purely statutory creature conferred on certain persons who benefit the land of a person by contributing to a structural improvement on the land. There are at least two lines of authority relative to the interpretation of the statute. The first is that, since the right to such a hen is derived from statute, strict comphance is required in order to create a vahd hen: Brann & Stuart Co. v. Consohdated Sun Ray, Inc., 433 Pa. 574 (1969). An analysis of the hne of cases which this case repre[171]*171sents indicates that this principle is applicable particularly to such matters as notice and time requirements. The second line of authority is that a substantial compliance with the statute is sufficient: American Car Co. v. Alexandria Water Co., 215 Pa. 520 (1906). This principle has been held applicable to the contents of the mechanics’ lien claim and particularly the required averments relating to the contract or contracts under which the benefit was conferred, the object of these requirements being a sufficient conformity to give notice of the nature of the claim to the owner and other lien creditors so that they will have sufficient knowledge to enable them to ascertain the truth in the event of a dispute. The hen in question was filed under the Mechanics’ Lien Law of August 24,1963, P.L. 1175, 49 PS §§1101, et seq. Section 301 of this act contains the basic declaration

“Every improvement and the estate or title of the owner in the property shall be subject to a hen . . . for the payment of all debts due by the owner to the contractor. ...”

Contractor is defined by the act as one who by contract with the owner, express or implied, supplies materials or fixtures in connection with any improvement. It should be apparent that Houston was a contractor within the meaning of the act and was entitled to a hen if it perfected its right in accordance with the act.

Houston filed its statement of mechanics’ hen claim in this court on September 29, 1972. The averment in the claim which is under fire relates to section 503, Subsection 5, 49 PS §1503, of the act, which provides that if the claim is filed by a contractor under a contract or contracts for an agreed sum, the lienor must identify the contract and set [172]*172out a general statement of the kind and character of the materials furnished. Houston complied with these requirements in paragraphs 4 and 7 of the claim.

Exceptants contend that Houston does not have a valid mechanics’ lien claim for the following reasons:

1. That there never was a contract or contracts for a fixed consideration between Houston and the owner.

2. That if materials were delivered to the construction project by Houston and incorporated into the construction, they were the result of a series of isolated orders beginning December 21, 1971, and continuing with regularity until April 28, 1972, to be followed by an isolated final delivery on July 6, 1972, and since the claim was not filed until September 29, 1972, the only claim available to Houston would be for the amount of the last delivery, $279.84.

3. That Houston is not entitled to a hen by reason of section 303(e) relating to security interests, and that Houston had a security interest in the personal property delivered and incorporated into the construction (49 PS §1303).

4. That Houston is barred by the operation of equitable estoppel under section 401 of the act (49 PS §1401).

An extensive hearing on the background of the lien was held by an auditor. The testimony offered by Albert B. Starr, an employe of Houston, and Paul H. Cover, who was president, secretary and owner of 50 percent of the shares of the owner, convinces this court to a certainty that there was either a contract or a series of contracts between Houston and the owner covering the sale and purchase of the [173]*173materials and services included in the claim. Whether or not there was one contract or two contracts is not controlling, because the evidence is clear that Cover, representing the owner, solicited firm price quotations on various materials required in the project from Starr, acting in behalf of Houston, and that these materials and services were furnished and delivered by Houston. Accordingly, it is not necessary to consider whether the owner was bound to purchase all of the materials for which quotations were solicited because the evidence indicates that this is what precisely happened. In stating its claim, Houston considered it as one contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brann & Stuart Co. v. Consolidated Sun Ray, Inc.
253 A.2d 105 (Supreme Court of Pennsylvania, 1969)
McCrady-rodgers Co. v. Nenoff
39 A.2d 260 (Superior Court of Pennsylvania, 1944)
American Car & Foundry Co. v. Alexandria Water Co.
64 A. 683 (Supreme Court of Pennsylvania, 1906)
Murphy & Slota v. Burke
311 A.2d 904 (Supreme Court of Pennsylvania, 1973)
Felheim v. Perry Brewing Co.
63 Pa. Super. 561 (Superior Court of Pennsylvania, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
70 Pa. D. & C.2d 168, 1974 Pa. Dist. & Cnty. Dec. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rome-electric-co-v-r-f-construction-inc-pactcomplindian-1974.